Registered No litigation declared Others project

SUMER LIFE CASA

By SUMER CORPORATION

RG-MH-28612 · RERA P51800026539 · Last updated on MahaRERA portal: 4 Jul 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 42 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 29%
6Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

SUMER LIFE CASA is a Others project by SUMER CORPORATION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800026539 on 30 Sep 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSUMER LIFE CASA
  • TypeOthers
  • Location
    • CHANDIVALI
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800026539
  • ReraGenie IDRG-MH-28612

Builder

  • NameSUMER CORPORATION
  • Entity typePartnership
  • PartnersRahul Ramesh Shah, Ramesh Sumermal Shah
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2020First promiseJun 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Sep 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed85 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA240000
B -WINGNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 29%.

A WING42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure29%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks29%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B -WING42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure29%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks29%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed104

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots104
Closed/Covered104
BuildingClosed/CoveredTotal
A WING5252
B -WING5252

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,244 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority (SRA)
Permissible FSI10842.6
Proposed, not sanctioned5,580 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWorli

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Rajratna Jadhav
ArchitectSHEETAL NIKHARE SS ASSOCIATES
EngineerSK Consultants & Engineers
EngineerMahimtura Consultants Pvt. Ltd Mr. Hiten Mahimtura
Chartered AccountantS T P AND ASSOCIATES MANISH PERIWAL
PartnerRole in project
SUMER CORPORATION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024500Jun 2024 → Dec 2027

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800026539.As per HEARING DATED 10th July 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is uploaded in Other Tab for your reference

Litigation declared1

CaseCourtStatus
975/2010Bombay High Courtpending

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000354362FARHAN IFTEKHAR KHANM/s. Sumer Corporation16/02/2023
CC12500177Niladri Prasad MohapatraSUMER CORPORATION19/01/2025
CC12500191Indresh Shivchand VishwakarmaSUMER CORPORATION20/01/2025
CC12500227Amrita Srikanth RaoSUMER CORPORATION23/01/2025
CC12500229Amrita Srikanth RaoSUMER CORPORATION23/01/2025
CC12500399DONALD DANIEL VARGHESESUMER CORPORATION06/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM _Sumer Life Casa _ Dec 2024.pdf4 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Circular 29 _Sumer Life_ March 2025.pdf4 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM _Sumer Life Casa _ Dec 2024.pdf4 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM _Sumer Life Casa _ March 2025.pdf4 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Sumer Life Casa_ Dec 2024.pdf4 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Sumer Life Casa _ March 2025.pdf4 Jul 2025
Disclosure of sold/ booked inventoryFile: Circular 29 _Sumer Life Casa _ March 2025.pdf4 Jul 2025
Declaration in FORM BFile: FORM B_ SUMER LIFE CASA.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SLC form 1 December 24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ September 2024_compressed.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ September 2024.pdf14 Nov 2024
Disclosure of sold/ booked inventoryFile: SLC_ Ciecular 29_ September 2024.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SLC - Form 1 Sept 2024.pdf11 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-1.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf30 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A _2023-24.pdf25 Oct 2024
Disclosure of sold/ booked inventoryFile: Sumer Life casa_ Circular 29.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SLC_Form 5_April 2021- March 2022.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_ 2023-24.pdf18 Oct 2024
Details of encumbrancesFile: Encumbrance Finance Letter.pdf17 Oct 2024
Details of encumbrances concerned to FinanceFile: Sumer Life Casa_Encumbrance Litigation Letter.pdf17 Oct 2024
Declaration in FORM BFile: Form B.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SLC_ FORM 1_ 31-12-2023.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SLC_ FORM 1_ 31-03-2024.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SLC_ FORM 1_ 30-06-2024.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ June 2023_11zon.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ June 2024_compressed.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ March 2024_compressed.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ December 2023_11zon.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLC_ Form 3_ September 2023_11zon.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ June 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ March 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ September 2023.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ June 2023.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SLC_ Form 2_ December 2023.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A _2020-21.pdf17 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf17 Oct 2024
Details of encumbrances concerned to LegalFile: Sumer Life Casa_Encumbrance Litigation Letter.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A _2021-22.pdf17 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A _2022-23.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A _2023-24.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_ 2023-24.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Sumer Life Casa FY2023-24.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUMER LIFE CASA.pdf6 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sumer Life Casa Form 5.pdf1 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SUMER LIFE CASA Dec 2021.pdf9 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SUMER LIFE CASA March 2022.pdf9 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life Casa June 2021.pdf9 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life Casa Sept 2021.pdf9 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life Casa Dec 2021.pdf9 May 2022
CERSAI detailsFile: Sumer Life Casa.pdf9 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life Casa June 2021.pdf9 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer life Casa 30 September 2021.pdf9 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life Casa December 2021.pdf9 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5 sumer casa life 2020-21.pdf27 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumer Life Casa_compressed.pdf25 Aug 2021
Declaration about Commencement CertificateFile: Sumer Life Casa.pdf22 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Casa Form 3 Sept 2020.pdf19 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Casa Form 3 Dec 2020.pdf19 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Casa Form 3 Mar 2021_compressed.pdf19 Jul 2021
Disclosure of sold/ booked inventoryFile: Sumer Life Casa Shops.pdf20 May 2021
Disclosure of sold/ booked inventoryFile: Sumer Life Casa Residential_compressed.pdf20 May 2021
Details of encumbrancesFile: ENCUMBRANCE SUMER LIFE CASA.pdf26 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (2).pdf26 Sep 2020
Layout approvalFile: PLAN1.pdf25 Sep 2020
Layout approvalFile: PLAN2.pdf25 Sep 2020
Layout approvalFile: PLAN 3.pdf25 Sep 2020
Layout approvalFile: PLAN 4.pdf25 Sep 2020
Layout approvalFile: PLAN 5.pdf25 Sep 2020
Building plan approvalFile: APPROVAL PLAN.pdf25 Sep 2020
PAN CardFile: PANCARD.pdf25 Sep 2020
Copy of the legal title reportFile: TITLE.pdf25 Sep 2020
Copy of Layout Approval (in case of layout)File: PLAN1.pdf25 Sep 2020
Copy of Layout Approval (in case of layout)File: PLAN2.pdf25 Sep 2020
Copy of Layout Approval (in case of layout)File: PLAN 3.pdf25 Sep 2020
Copy of Layout Approval (in case of layout)File: PLAN 4.pdf25 Sep 2020
Copy of Layout Approval (in case of layout)File: PLAN 5.pdf25 Sep 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Sumer LifeCTS NO 11A pt11 191to402 11D pt 16 16 1to92 19 19 1to28 20pt 25pt 25 1to32 50pt Chandivali327CompletedJun 2024Jun 2024

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUMER LIFE CASA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHANDIVALI6,700+ in Mumbai Suburban

2 kmSUMER LIFE CASACompleted 41Lapsed / revoked 32Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 108 registered projects within 2 km.

Builder: SUMER CORPORATION

SUMER CORPORATION has 2 registrations on MahaRERA, including SUMER LIFE and SUMER LIFE CASA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SUMER LIFE CASA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUMER LIFE CASA?

The registered promoter entity is SUMER CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUMER LIFE CASA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUMER LIFE CASA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUMER LIFE CASA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUMER LIFE CASA?

The professionals named in the filing: Architect: Mr Rajratna Jadhav; Architect: SHEETAL NIKHARE SS ASSOCIATES; Engineer: SK Consultants & Engineers; Engineer: Mahimtura Consultants Pvt. Ltd Mr. Hiten Mahimtura; Chartered Accountant: S T P AND ASSOCIATES MANISH PERIWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMER LIFE CASA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMER LIFE CASA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMER LIFE CASA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.