Home / Browse projects / Pune, Maharashtra / Sukhwani Kingsley
Sukhwani Kingsley
By Sukhwani Chawla Constructions
RG-MH-22435 · RERA P52100031299 · Last updated on MahaRERA portal: 30 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sukhwani Kingsley is a Others project by Sukhwani Chawla Constructions in Pune, Maharashtra, registered with MahaRERA as P52100031299 on 15 Oct 2021. Possession is promised by 31 Dec 2028. 360 of the 831 units on this registration are recorded sold or booked, and 62 of 121 construction stages are filed complete.
At a glance
Project
- NameSukhwani Kingsley
- TypeOthers
- Location
- Off Aditya Birla Hospital Road
- Near Padamji Paper Mill Thergaon
- Thergaon
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100031299
- ReraGenie IDRG-MH-22435
Builder
- NameSukhwani Chawla Constructions
- Entity typePartnership
- PartnersPrakash Nandlal Chawla, Sunil Nandlal Chawla
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Oct 2021
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings11 building records
- Documents filed311 files
Current status
Figures as on 30 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 26 | 26 | 80 | 0 | 80 |
| B | NA | 26 | 26 | 79 | 0 | 79 |
| C | NA | 26 | 26 | 80 | 0 | 80 |
| D | NA | 26 | 26 | 80 | 0 | 80 |
| E | NA | 26 | 26 | 80 | 0 | 80 |
| F | NA | 26 | 26 | 80 | 0 | 80 |
| G | NA | 26 | 26 | 40 | 0 | 40 |
| H | NA | 26 | 26 | 80 | 0 | 80 |
| I | NA | 26 | 26 | 80 | 0 | 80 |
| J | NA | 26 | 26 | 80 | 0 | 80 |
| MHADA | NA | 14 | 14 | 72 | 0 | 72 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building11
As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
62 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Stilt Floor, at 70%.
A35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 70% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
B41%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 6% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
C58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 69% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
D88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 67% |
E88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 67% |
F88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 67% |
G88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 67% |
H35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
I26%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
J19%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 11% |
MHADA70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 67% |
Progress on shared amenities15
As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 65% |
| Storm Water Drains | Yes | 40% |
| Landscaping & Tree Planting | Yes | 25% |
| Street Lighting | Yes | 30% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 40% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 25% |
| Electrical meter room, sub-station, receiving station | Yes | 40% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1266
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A | 170 | 170 |
| B | 124 | 124 |
| C | 126 | 126 |
| D | 147 | 147 |
| E | 126 | 126 |
| F | 123 | 123 |
| G | 84 | 84 |
| H | 126 | 126 |
| I | 126 | 126 |
| MHADA | 114 | 114 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 23.21 cr | Rs 6.56 cr |
| D | NA | Rs 23.20 cr | Rs 23.20 cr |
| F | NA | Rs 21.76 cr | Rs 21.76 cr |
| E | NA | Rs 21.73 cr | Rs 21.73 cr |
| G | NA | Rs 21.72 cr | Rs 21.72 cr |
| H | NA | Rs 21.72 cr | Rs 5.28 cr |
| J | NA | Rs 21.72 cr | Rs 3.87 cr |
| B | NA | Rs 20.73 cr | Rs 6.80 cr |
| C | NA | Rs 20.73 cr | Rs 14.35 cr |
| I | NA | Rs 20.73 cr | Rs 5.16 cr |
| MHADA | NA | Rs 12.94 cr | Rs 12.94 cr |
| - | NA | Rs 10.63 cr | Rs 4.68 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK a Architecture |
| Engineer | Vislavnath Walu |
| Chartered Accountant | ANJK & CO LLP |
| Chartered Accountant | R V Nevatia & CO |
| Partner | Role in project |
|---|---|
| Sukhwani Chawla Constructions | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Dec 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Dec 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed311
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 311 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architech Certificate March 2026.pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate March 2026 - Kingsley.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate December 2025.pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate December 2025.pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate - December 2025 - Final.pdf | 2 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate September 2025.pdf | 24 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Engineers Certificate September 2025.pdf | 24 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Kingsley.pdf | 24 Dec 2025 |
| Layout approvalFile: Layout Approved.pdf | 20 Dec 2025 |
| Layout approvalFile: Layout Approved.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 1.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 2.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 3.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 4.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 5.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 6.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 7.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 8.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 9.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 10.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 11.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 12.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 13.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 14.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 15.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 16.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 17.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 18.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 19.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 20.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 21.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 22.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 23.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 24.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 25.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 26.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 27.pdf | 20 Dec 2025 |
| Building plan approvalFile: Building Plan 28.pdf | 20 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate September 2025.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Engineers Certificate September 2025.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate September 2025 - Final.pdf | 8 Dec 2025 |
| Form 5 (FY 2024-2025)File: CA Form 5_Sukhwani Kingsley_FY 2024-25_Signed.pdf | 7 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate - June 2025 Signed.pdf | 25 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate June 2025 - Final.pdf | 25 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 CA Certificate June 2025 - Signed Final.pdf | 25 Jul 2025 |
| Form 1File: Form 1 Architect Cerrtificate - March 2025 Final.pdf | 23 Jul 2025 |
| Form 2File: Form 2 Engineer Certificate - March 2025.pdf | 23 Jul 2025 |
| Form 3File: Form 3 CA Certificate - Sukhwani Kingsley March 2025.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory March 2025 Signed.pdf | 23 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Sukhwani Kingsley.pdf | 27 Feb 2025 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 7 Feb 2025 |
| Layout approvalFile: Layout Plan 1_11zon.pdf | 4 Feb 2025 |
| Layout approvalFile: Layout Plan 2_11zon.pdf | 4 Feb 2025 |
| Layout approvalFile: Layout Plan 3_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 1_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 2_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 3_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 4_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 5_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 6_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 7_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 8_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 9_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 10_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 11_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 12_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 13_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 14_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 15_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 16_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 17_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 18_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 19_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 20_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 21_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 22_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 23_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 24_11zon.pdf | 4 Feb 2025 |
| Building plan approvalFile: Building Plan 25_11zon.pdf | 4 Feb 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 311 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sukhwani Kingsley on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Padamji Paper Mill Thergaon13,700+ in Pune
Filed coordinates, straight-line distance. 109 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: Sukhwani Chawla Constructions
Sukhwani Chawla Constructions has 1 registration on MahaRERA, including Sukhwani Kingsley. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Sukhwani Kingsley is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sukhwani Kingsley?
The registered promoter entity is Sukhwani Chawla Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sukhwani Kingsley?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sukhwani Kingsley?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sukhwani Kingsley?
The professionals named in the filing: Architect: VK a Architecture; Engineer: Vislavnath Walu; Chartered Accountant: ANJK & CO LLP; Chartered Accountant: R V Nevatia & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sukhwani Kingsley?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback