Sukhdev Nagar Phase 2
RG-MH-04653 · RERA P52600019858 · Last updated on MahaRERA portal: 21 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 7 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sukhdev Nagar Phase 2 is a Residential / Group Housing project by RSM NEST DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600019858 on 5 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 7 complaints are on record with the regulator.
At a glance
Project
- NameSukhdev Nagar Phase 2
- TypeResidential / Group Housing
- Location
- Barshi
- 2511 Tel Girni Chowk
- Solapur
- 413401
- Pincode413401
- RERA no.P52600019858
- ReraGenie IDRG-MH-04653
Builder
- NameRSM NEST DEVELOPERS
- Entity typePartnership
- PartnersPOONAM RAJENDRA MIRGANE, POONAM RAJENDRA MIRGANE
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Mar 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
- Buildings8 building records
- Documents filed133 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| F | NA | 5 | 0 | 0 | 0 | 0 |
| G | NA | 5 | 0 | 0 | 0 | 0 |
| H | NA | 5 | 0 | 0 | 0 | 0 |
| I | NA | 5 | 0 | 0 | 0 | 0 |
| J | NA | 5 | 0 | 0 | 0 | 0 |
| L | NA | 5 | 0 | 0 | 0 | 0 |
| K | NA | 5 | 0 | 0 | 0 | 0 |
| M | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 21 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
23 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Staircases, at 90%.
F27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
G27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
H58%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 5% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
I28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 5% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
J28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 3% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
K27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
M24%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed380
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| F | 50 | 50 |
| G | 50 | 50 |
| H | 50 | 50 |
| I | 50 | 50 |
| J | 50 | 50 |
| L | 50 | 50 |
| K | 50 | 50 |
| M | 30 | 30 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Poonam Mirgane |
| Partner | Role in project |
|---|---|
| RSM NEST DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-12-2026. After careful consideration of the current circumstances and the challenges faced, we propose a revised completi
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000238582 | NISHANT DEEPAK JAIN | Vishal Ramesh More And Shweta Vishal More | 29/03/2023 |
| CC005000000289966 | NISHANT DEEPAK JAIN | MRS. MALTI PRASHANT GUND | 29/12/2023 |
| CC005000000289969 | NISHANT DEEPAK JAIN | SHWETA VISHAL MORE | 29/12/2023 |
| CC005000000289970 | NISHANT DEEPAK JAIN | NITIN RAMLING GHULE | 29/12/2023 |
| CC005000000289973 | NISHANT DEEPAK JAIN | ANANT GORAKH PAWAR | 29/12/2023 |
| CC12601494 | NISHANT DEEPAK JAIN | REKHA ARJUN PALKHE | 18/03/2026 |
| CC12601495 | NISHANT DEEPAK JAIN | PRAVIN SHAMSHODDIN MOMIN (RESPONDENT) | 18/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Mar 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed133
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf | 21 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: form 5.pdf | 21 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: Legal Enc.pdf | 18 Jun 2025 |
| CERSAI detailsFile: CERSAI_Search_Report_200358990402_For_Debtor_Based_Search_18_06_2025_16_39_37_934.pdf | 18 Jun 2025 |
| Details of encumbrances concerned to LegalFile: Legal Enc.pdf | 18 Jun 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Sec Unsec Decl.pdf | 18 Jun 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Form 3.pdf | 17 Jun 2025 |
| PAN CardFile: PAN.pdf | 16 Jun 2025 |
| Details of encumbrancesFile: Financial Enc.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 30062024_2_11zon.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31032024_4_11zon.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 30092024_3_11zon.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31122024_1_11zon.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31032025_5_11zon.pdf | 16 Jun 2025 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 16 Jun 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 16 Jun 2025 |
| Deviation Report with respect to Allotment letterFile: No dev Allotment letter.pdf | 16 Jun 2025 |
| Deviation Report with respect to model copy of AgreementFile: No dev AFS.pdf | 16 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf | 16 Jun 2025 |
| Proforma of Agreement for saleFile: afs.pdf | 16 Jun 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DoI.pdf | 16 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf | 16 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 23-24.pdf | 16 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - April to June - 2024.pdf | 11 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - July to Sept - 2024.pdf | 11 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Oct to December - 2024.pdf | 11 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Jan to March - 2025.pdf | 11 Jun 2025 |
| Certificates of CA (Form 3)File: Form - 3 - 31032025.pdf | 11 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - April to June - 2024.pdf | 11 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - July - Sept - 2024.pdf | 11 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Oct to December - 2024.pdf | 11 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Jan to March - 2025.pdf | 11 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2019 - 2020.pdf | 11 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020 - 2021.pdf | 11 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021 - 2022.pdf | 11 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022 - 2023.pdf | 11 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023 - 2024.pdf | 11 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 3 May 2025 |
| Certificates of CA (Form 3)File: Form 3_Q4_Phase 2_11zon.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 3 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3_.pdf | 17 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf | 17 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase 2 FY 2022-23.pdf | 31 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Phase 2 FY 2023-24.pdf | 31 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_23-24 Q-2_11zon.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_23-24 Q-3.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_23-24 Q-4.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_24-25 Q-1.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_24-25 Q-2.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate FY_23-24 Q-1.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned doc_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: scaned Doc_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Document_11zon signed.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: scaned Doc signed_11zon.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc signed_11zon.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc signed_11zon.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Doc signed_11zon.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned doc signed_11zon.pdf | 28 Dec 2024 |
| Certificates of CA (Form 3)File: Scaned Document signed_11zon.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24 Q-1 (1).pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24 Q-2.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24 Q-3.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 23-24 Q-4.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 24-25 Q-1.pdf | 28 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 24-25 Q-2.pdf | 28 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 2022-23 Q1.pdf | 18 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 2022-23 Q2.pdf | 18 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 2022-23 Q3.pdf | 18 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 2022-23 Q4.pdf | 18 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 22-23 Q-1.pdf | 18 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 22-23 Q-2.pdf | 18 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY22-23 Q-3.pdf | 18 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate FY 22-23 Q-4.pdf | 18 May 2024 |
| Certificates of CA (Form 3)File: Form 3 for Q1 FY 2022-23.pdf | 18 May 2024 |
| Certificates of CA (Form 3)File: Form-3 for Q2 FY 2022-23_11zo.pdf | 18 May 2024 |
| Certificates of CA (Form 3)File: Form-3 for Q3 FY 2022-23_11zon DSC.pdf | 18 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 133 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Sukhdev Nagar Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near 2511 Tel Girni Chowk550+ in Solapur
PMAY BARSHI NAGAR PARISHAD AHP
BARSHI NAGAR PARISHAD
VARAD NAGARI
M/S SHRIRAM BUILDERS & DEVELOPERS
RSM HEIGHTS C TOWER
RAJENDRA SUKHADEV MIRGANE
Jaychandajit Surana
JAYCHAND SHANTILAL SURANA
TATHASTU
TATHASTU DEVELOPERS
RSM Heights E Phase
RAJENDRA SUKHADEV MIRGANE
See every Solapur project, with the district possession charts
Builder: RSM NEST DEVELOPERS
RSM NEST DEVELOPERS has 2 registrations on MahaRERA, including Sukhdev Nagar Phase 2 and Sukhdev Nagar Phase 3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What are my rights if Sukhdev Nagar Phase 2 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sukhdev Nagar Phase 2?
The registered promoter entity is RSM NEST DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sukhdev Nagar Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Sukhdev Nagar Phase 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Sukhdev Nagar Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sukhdev Nagar Phase 2?
The professionals named in the filing: Architect: Poonam Mirgane. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sukhdev Nagar Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback