Home / Browse projects / Solapur, Maharashtra / RSM HEIGHTS C TOWER

Registration lapsed No litigation declared Residential / Group Housing project

RSM HEIGHTS C TOWER

By RAJENDRA SUKHADEV MIRGANE

RG-MH-20637 · RERA P52600005087 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 20%
55 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

RSM HEIGHTS C TOWER is a Residential / Group Housing project by RAJENDRA SUKHADEV MIRGANE in Solapur, Maharashtra, registered with MahaRERA as P52600005087 on 9 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. 8 of the 63 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameRSM HEIGHTS C TOWER
  • TypeResidential / Group Housing
  • Location
    • Latur Road
    • Telgirani Chowk
    • Barshi
    • Solapur
    • 413401
  • Pincode413401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52600005087
  • ReraGenie IDRG-MH-20637

Builder

  • NameRAJENDRA SUKHADEV MIRGANE
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredAug 2017PromisedJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed63 files

Current status

13%8 of 63 units booked

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C TOWERNA8863063

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 20%.

C TOWER: 13% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)20%
Podiums (if any)0%
Plinth20%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes95%
Street LightingYes90%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes100%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,917 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 May 2026

Approvals and building plan

Sanctioning authorityBarshi Municipal Council Dist Solapur
Permissible FSI3602.48
Proposed, not sanctioned3,602 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2511, TELGIRNI CHOWK, BARSHI 413401

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMITESH C SIDHPURA
EngineerMUKTAR NASIR SHAIKH
Chartered AccountantANJK & Co LLP
Chartered AccountantS.P. Ladda & Associates
PartnerRole in project
RAJENDRA SUKHADEV MIRGANE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 31032019.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2019.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032019.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory 2019.pdf14 Aug 2026
Form 1File: FORM 1 31032020.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2020.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032020.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory 2020.pdf14 Aug 2026
Form 1File: FORM 1 31032021.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2021.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032021.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory 2021.pdf14 Aug 2026
Form 1File: FORM 1 31032022.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2022.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032022.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory 2022.pdf14 Aug 2026
Form 1File: FORM 1 31032023.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2023.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032023.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory 2023.pdf14 Aug 2026
Form 1File: FORM 1 31032024.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate 2024.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 31032024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory March 24.pdf14 Aug 2026
Form 1File: FORM 1 30062024.pdf14 Aug 2026
Form 2File: FORM 2 Engineer Certificate June 2024.pdf14 Aug 2026
Form 3File: FORM 3 CA Certificate 30062024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure Of Inventory June 2024.pdf14 Aug 2026
Form 5 (FY 2020-2021)File: FORM 5_2021.pdf3 Aug 2026
Form 5 (FY 2021-2022)File: FORM 5_2022.pdf3 Aug 2026
Form 5 (FY 2022-2023)File: FORM 5_2023.pdf3 Aug 2026
Form 5 (FY 2023-2024)File: FORM 5_2024 (1).pdf3 Aug 2026
Form 2A (FY 2018-2019)File: FORM 2A Mar 2019.pdf1 Aug 2026
Form 2A (FY 2019-2020)File: FORM 2A Mar 2020.pdf1 Aug 2026
Form 2A (FY 2020-2021)File: FORM 2A Mar 2021.pdf1 Aug 2026
Form 2A (FY 2021-2022)File: FORM 2A Mar 2022.pdf1 Aug 2026
Form 2A (FY 2022-2023)File: FORM 2A Mar 2023.pdf1 Aug 2026
Form 2A (FY 2023-2024)File: FORM 2A Mar 2024.pdf1 Aug 2026
Form 2A (FY 2024-2025)File: FORM 2A Mar 2025.pdf1 Aug 2026
Form 5 (FY 2018-2019)File: FORM 5_2019.pdf1 Aug 2026
Form 5 (FY 2019-2020)File: FORM 5_2020.pdf1 Aug 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 2511 Tower C.pdf15 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 2511 tower C.pdf15 Oct 2018
Certificates of CA (Form 3)File: fORM 3 Of C Tower (2).pdf13 Oct 2018
Certificates of CA (Form 5)File: form 5.pdf13 Oct 2018
Details of encumbrancesFile: Decleration of Encumberance Certificate.pdf8 Mar 2018
Declaration in FORM BFile: Form-B Tower-C 2511.pdf8 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Tower-C 2511 new.pdf8 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Tower-C 2511 new.pdf8 Mar 2018
Certificates of CA (Form 3)File: CA Certificate.pdf8 Mar 2018
Layout approvalFile: 2511 Layout-min.pdf29 Jul 2017
Building plan approvalFile: Building Approval Plan C Tower.pdf29 Jul 2017
PAN CardFile: RSM PAN.pdf29 Jul 2017
Copy of the legal title reportFile: 2511 Index-II.pdf29 Jul 2017
Details of encumbrancesFile: No Encumbrances.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 2511 Layout-min.pdf29 Jul 2017
Building Plan Approval (IOD)File: Building Approval Plan C Tower.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Build permission RSM.pdf29 Jul 2017
Declaration in FORM BFile: Declaration in Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate Final.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RSM Height Final.pdf29 Jul 2017
Certificates of CA (Form 3)File: Chartered Accountants Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment letter RSM.pdf29 Jul 2017

How this compares with Solapur

13%of this project is bookeddistrict median 15%
15%of Solapur projects moved their completion datethis one has not
39%of Solapur registrations have lapsed or been cancelledthis one is among them

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep RSM HEIGHTS C TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Telgirani Chowk550+ in Solapur

2 kmRSM HEIGHTS C TOWERCompleted 3Lapsed / revoked 3Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: RAJENDRA SUKHADEV MIRGANE

RAJENDRA SUKHADEV MIRGANE has 3 registrations on MahaRERA, including SUKHADEV NAGAR PHASE I PART 1 and RSM HEIGHTS C TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What does it mean that RSM HEIGHTS C TOWER shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RSM HEIGHTS C TOWER is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RSM HEIGHTS C TOWER?

The registered promoter entity is RAJENDRA SUKHADEV MIRGANE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RSM HEIGHTS C TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RSM HEIGHTS C TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RSM HEIGHTS C TOWER?

The professionals named in the filing: Architect: MITESH C SIDHPURA; Engineer: MUKTAR NASIR SHAIKH; Chartered Accountant: ANJK & Co LLP; Chartered Accountant: S.P. Ladda & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RSM HEIGHTS C TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RSM HEIGHTS C TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RSM HEIGHTS C TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.