Home / Browse projects / Thane, Maharashtra / SUDAMA REGENCY BUILDING NO 2,3,4

Registration lapsed No litigation declared Others project

SUDAMA REGENCY BUILDING NO 2,3,4

By SHREE SIDDHIVINAYAK ENTERPRISES

RG-MH-12204 · RERA P51700001217 · Last updated on MahaRERA portal: 30 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
12 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 43%
6Complaints at MahaRERAon this registration
Jump to the 132 documents Report an error

SUDAMA REGENCY BUILDING NO 2,3,4 is a Others project by SHREE SIDDHIVINAYAK ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700001217 on 27 Jul 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSUDAMA REGENCY BUILDING NO 2,3,4
  • TypeOthers
  • Location
    • Diva Shill Road
    • Khardi Pada
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001217
  • ReraGenie IDRG-MH-12204

Builder

  • NameSHREE SIDDHIVINAYAK ENTERPRISES
  • Entity typePartnership
  • PartnersMUSTAK SAIFAN SHAIKH, Mohammed Tahir Mustak Shaikh
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

22 months past promisethis monthRegisteredJul 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jul 2017
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed132 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUDAMA REGENCY BUILDING NO 2NA240000
SUDAMA REGENCY BUILDING NO 3NA240000
SUDAMA REGENCY BUILDING NO 4NA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 43%.

SUDAMA REGENCY BUILDING NO 242%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure39%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks7%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SUDAMA REGENCY BUILDING NO 342%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks7%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SUDAMA REGENCY BUILDING NO 442%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure43%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises14%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks7%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes15%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes25%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes15%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed71

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots71
Closed/Covered3
Open Space68
BuildingClosed/CoveredOpen SpaceTotal
SUDAMA REGENCY BUILDING NO 212223
SUDAMA REGENCY BUILDING NO 312223
SUDAMA REGENCY BUILDING NO 412425

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,590 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
RAMA DINKAR MHATREThane (M Corp.)Thane
SAVITRI SUDAM PATILThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI13613.05
Proposed, not sanctioned13,613 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNANDANWAN INDUSTRIAL ESTATE GROUND FLOOR GALA NO AB/B2 IBS MARG OPP ETERNITY MALL THANE 400 604

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAKARAND TORASKAR ASSOCIATES
EngineerAJAY MAHALE AND ASSOCIATES
Chartered AccountantMs Singh Ranjan & Co
PartnerRole in project
SHREE SIDDHIVINAYAK ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018729Dec 2023 → Dec 2024

Reason as filed by the promoterThe project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction.Hence we request you to grant the extension.

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000054718Bhavanj Kanji ShahShree Siddhivinayak Enterprises01/06/2018
CC006000000054721Jigna A. ShahShree Siddhivinayak Enterprises01/06/2018
CC12500748Ashwin Bhavanji ShahSHREE SIDDHIVINAYAK ENTERPRISES05/03/2025
CC12500745Jigna Ashwin ShahSHREE SIDDHIVINAYAK ENTERPRISES05/03/2025
CC12500750Maitri Ashwin ShahSHREE SIDDHIVINAYAK ENTERPRISES05/03/2025
CC12500942Jigna Ashwin ShahSHREE SIDDHIVINAYAK ENTERPRISES18/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed132

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 132 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 (31-12-2023).pdf30 May 2026
Form 2File: Form 2 (31-12-2023).pdf30 May 2026
Form 3File: Form 3 (31-12-2023).pdf30 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (31-12-2023).pdf30 May 2026
Form 1File: Form 1 (30-09-2023).pdf30 May 2026
Form 2File: Form 2 (30-09-2023).pdf30 May 2026
Form 3File: Form 3 (30-09-2023).pdf30 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (30-09-2023).pdf30 May 2026
Form 1File: Form 1(31-12-2023).pdf30 May 2026
Form 2File: Form 2 (31-12-2023).pdf30 May 2026
Form 3File: Form 3 (31-12-2023).pdf30 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (31-12-2023).pdf30 May 2026
Form 1File: Form 1 Dec 2024.pdf25 May 2026
Form 2File: Form 2(31-12-2024).pdf25 May 2026
Form 3File: Form 3(31-12-2024).pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (31-12-2024).pdf25 May 2026
Form 1File: Form 1 Sep 2024.pdf25 May 2026
Form 2File: Form 2(30-09-2024).pdf25 May 2026
Form 3File: Form 3 (30-09-2024).pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (30-09-2024).pdf25 May 2026
Form 1File: Form 1 June 2024.pdf25 May 2026
Form 2File: Form 2(30-06-2024).pdf25 May 2026
Form 3File: Form 3 (30-06-2024).pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (30-06-2024).pdf25 May 2026
Form 1File: Form 1 Mar 2024.pdf25 May 2026
Form 2File: Form 2(31-03-2024).pdf25 May 2026
Form 3File: Form 3(31-03-2024).pdf25 May 2026
Disclosure of Sold and Booked InventoryFile: Booked and sold (1-4-2024).pdf25 May 2026
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 Feb 2025
Details of encumbrances concerned to FinanceFile: Self Declaration-SSE.pdf13 Jan 2025
CERSAI detailsFile: Aeest Based Report- SSE.pdf13 Jan 2025
CERSAI detailsFile: Debtor Based Report- SSE.pdf13 Jan 2025
Details of encumbrances concerned to LegalFile: Self Declaration-SSE.pdf13 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Siddhivinayak Enterprises.pdf2 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Intrest-SSE.pdf1 Mar 2024
Disclosure of sold/ booked inventoryFile: Revised Sold Unsold inventory dec 23.pdf22 Feb 2024
Certificates of CA (Form 3)File: Form 3 31-12-2023 SSE.pdf22 Feb 2024
Declaration about Commencement CertificateFile: Declaration about CC- SSE.pdf6 Feb 2024
Declaration in FORM BFile: Form B SSE.pdf5 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shree Siddhivinayak Enterprises Form 1.pdf3 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shree Siddhivinayak Enterprises Form 1 For QE Dec-23_removed.pdf3 Feb 2024
Disclosure of sold/ booked inventoryFile: Shree Siddhivianayak Enterprises - sold-unsold.pdf3 Feb 2024
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold-unsold Inventory SSE.pdf3 Jan 2024
Certificates of CA (Form 3)File: Form 3 30-09-2023.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SSE sept 23.pdf26 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 SSE june 23.pdf26 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHREE SIDDHIVINAYAK SUDAMA REGENCY RERA.pdf11 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHREE SIDDHIVINAYAK SUDAMA REGENCY RERA JUNE.pdf11 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Shree Siddhivinayak Enterprises Form 2A.pdf11 Dec 2023
Certificates of CA (Form 3)File: Form 3 31-03-2023.pdf11 Dec 2023
Certificates of CA (Form 3)File: Form 3 30-06-2023.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SSE Form 5 FY 22-23 Sign.pdf7 Dec 2023
Building plan approvalFile: 8TH to 12 TH FLOOR PLAN (1).pdf21 Aug 2023
Building plan approvalFile: 17TH to 22ND (REFUGE) FLOOR PLAN.pdf21 Aug 2023
Building plan approvalFile: 18TH TO 21ST FLOOR PLAN (1).pdf21 Aug 2023
Building plan approvalFile: 2ND FLOOR PLAN.pdf21 Aug 2023
Building plan approvalFile: TYPICAL FLOOR PLAN------.pdf21 Aug 2023
Building Plan Approval (IOD)File: 2ND FLOOR PLAN.pdf21 Aug 2023
Building Plan Approval (IOD)File: TYPICAL FLOOR PLAN------.pdf21 Aug 2023
Building Plan Approval (IOD)File: 8TH to 12 TH FLOOR PLAN (1).pdf21 Aug 2023
Building Plan Approval (IOD)File: 17TH to 22ND (REFUGE) FLOOR PLAN.pdf21 Aug 2023
Building Plan Approval (IOD)File: 18TH TO 21ST FLOOR PLAN (1).pdf21 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-12-2022 updated.pdf16 Jun 2023
Certificates of CA (Form 3)File: Form 3 31-01-2023.pdf16 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SSE Form 2 31-03-2022.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SSE Form 2 30-06-2022.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SSE Form 2 30-09-2022.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SSE Form 2 31-03-2022.pdf6 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SSE Form 2 31-12-2022.pdf6 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf6 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf6 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5-2020-21.pdf6 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From 5 21-22.pdf6 Apr 2023
Details of encumbrances concerned to FinanceFile: Declaration of No Encumbrances - Legal.pdf17 Feb 2023
Details of encumbrances concerned to LegalFile: Declaration of No Encumbrances - Legal.pdf17 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account for Real Estate Projects.pdf17 Feb 2023
Deviation Report with respect to Allotment letterFile: No Deviation Report for Allotment Letter.pdf17 Feb 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Report for Agreement for Sale.pdf17 Feb 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SUDAMA REGENCY BUILDING NO 8KHARDI PADA DIVA SHILL ROAD DAWALE VILLAGE THANE 400 61256CompletedMar 2017Late, Apr 2017
SUDAMA REGENCY BUILDING NO 6, 7KHARDI PADA DIVA SHILL ROAD DAWALE VILLAGE THANE 400 61284CompletedDec 2015Late, Jan 2016
SUDAMA REGENCY BUILDING NO 9 , 10KHARDI PADA DIVA SHILL ROAD DAWALE VILLAGE THANE 400 61284CompletedMay 2015Late, Aug 2015
SUDAMA REGENCY BUILDING NO 11,12,13,14KHARDI PADA DIVA SHILL ROAD DAWALE VILLAGE THANE 400 612154CompletedOct 2014Sep 2014

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUDAMA REGENCY BUILDING NO 2,3,4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khardi Pada7,600+ in Thane

2 kmSUDAMA REGENCY BUILDING Completed 27Lapsed / revoked 7Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: SHREE SIDDHIVINAYAK ENTERPRISES

SHREE SIDDHIVINAYAK ENTERPRISES has 6 registrations on MahaRERA, including SUDAMA REGENCY BUILDING NO 1, 5 and SUDAMA REGENCY BUILDING NO 2,3,4. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SUDAMA REGENCY BUILDING NO 2,3,4 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SUDAMA REGENCY BUILDING NO 2,3,4 is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUDAMA REGENCY BUILDING NO 2,3,4?

The registered promoter entity is SHREE SIDDHIVINAYAK ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUDAMA REGENCY BUILDING NO 2,3,4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUDAMA REGENCY BUILDING NO 2,3,4?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUDAMA REGENCY BUILDING NO 2,3,4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUDAMA REGENCY BUILDING NO 2,3,4?

The professionals named in the filing: Architect: MAKARAND TORASKAR ASSOCIATES; Engineer: AJAY MAHALE AND ASSOCIATES; Chartered Accountant: Ms Singh Ranjan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUDAMA REGENCY BUILDING NO 2,3,4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUDAMA REGENCY BUILDING NO 2,3,4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUDAMA REGENCY BUILDING NO 2,3,4 to a free account