Home / Browse projects / Pune, Maharashtra / STELLAR RHYTHMM

Registration lapsed No litigation declared Residential / Group Housing project

STELLAR RHYTHMM

By Wakadkar Patil Associates LLP

RG-MH-90496 · RERA P52100035161 · Last updated on MahaRERA portal: 11 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
11 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 90%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

STELLAR RHYTHMM is a Residential / Group Housing project by Wakadkar Patil Associates LLP in Pune, Maharashtra, registered with MahaRERA as P52100035161 on 10 May 2022. Possession was promised by 31 Dec 2024 and is now 22 months past that date.

At a glance

Project

  • NameSTELLAR RHYTHMM
  • TypeResidential / Group Housing
  • Location
    • Survey No 161 Hissa No 2
    • wakad
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035161
  • ReraGenie IDRG-MH-90496

Builder

  • NameWakadkar Patil Associates LLP
  • Entity typeCompany

Key dates

22 months past promisethis monthRegisteredMay 2022PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2022
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA70000
B wingNA70000
C WingNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

A wing68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
B wing85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
C Wing85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 11 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered43
Open Space41
BuildingClosed/CoveredOpen SpaceTotal
A wing131528
B wing151328
C Wing151328

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,300 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6672.3
Proposed, not sanctioned4,172 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHinjawdi Pune 411057

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKimaya Associates Architects and Planners
EngineerKishor A Patil
Chartered AccountantPramod B Shah
PartnerRole in project
Wakadkar Patil Associates LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Apr 2025

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: WAKADKAR PATIL ASS STELLAR RHYTHMM FORM5.pdf11 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: stellar Rhythmm OC.pdf6 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 Q3 Wakadkar Patil.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 Q4 Wakadkar Patil.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 Q3 Wakadkar Patil.pdf8 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 Q4 Wakadkar Patil.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 Q3 Wakadkar Patil.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 Q4 Wakadkar Patil.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 FORM 1 ARCHITECT CER 2ND Q.pdf23 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 FORM 1ARCHITECT CERTIFICATE.pdf23 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q2 FORM 2 ENGGINEER CERTIFICATE 2ND Q.pdf23 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3 FORM 2 ENGG CERTIFICATE.pdf23 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Q2 QUALITY ASSURANCE.pdf23 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3 FORM 3 CA CERTIFICATE 3RD Q_compressed.pdf23 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Stellar Rhythm April 23.pdf12 Jun 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Stellar Rhythm REGISTRATION CERTIFICATE.pdf12 Jun 2023
Details of encumbrancesFile: NO ENCUMBRANCES (FINANCIAL) Stellar Rhythm.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Rhythm April 2023.pdf17 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold unsold inventory April 2023.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rhythm April 2023.pdf17 Apr 2023
Layout approvalFile: New Sanction Plan Stellar Rhythm Dec 22.pdf4 Jan 2023
Copy of Layout Approval (in case of layout)File: New Sanction Plan Stellar Rhythm Dec 22.pdf4 Jan 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate Stellar Rhythm Dec22.pdf16 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Stellar Rhythm Dec22.pdf16 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance stellar Rhythm Dec22.pdf16 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 22 Stellar Rhythm.pdf16 Dec 2022
Proforma of Agreement for saleFile: Decleration of Sales Inventory.pdf16 Dec 2022
Deviation Report with respect to Allotment letterFile: Decleration of Sales Inventory.pdf16 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Decleration of Sales Inventory.pdf16 Dec 2022
Details of encumbrances concerned to FinanceFile: No Encumbrance Legal Stellar Rhythm Dec22.pdf11 Dec 2022
Details of encumbrances concerned to LegalFile: No Encumbrance Legal Stellar Rhythm Dec22.pdf11 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Stellar Rhythm Dec 22.pdf11 Dec 2022
Disclosure of sold/ booked inventoryFile: Discolsure of sold unsold Stellar Rhythm Dec22.pdf11 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 22 Stellar Rhythm.pdf11 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A Stellar Rhythm Dec22.pdf11 Dec 2022
Layout approvalFile: Floor Plan Parking.pdf5 May 2022
Copy of Layout Approval (in case of layout)File: Floor Plan Parking.pdf5 May 2022
Declaration in FORM BFile: Stellar Rhythmm Form B.pdf5 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Stellar Rhythmm (first).pdf5 May 2022
Layout approvalFile: Layout Plan Stellar Rhythmm.pdf30 Apr 2022
Building plan approvalFile: NA Order Stellar Rhythmm.pdf30 Apr 2022
PAN CardFile: Company Pancard Wakadkar Patil Asso.pdf30 Apr 2022
Copy of the legal title reportFile: Stellar Rhythmm Legal Title Report.pdf30 Apr 2022
Details of encumbrancesFile: No incumbrances Certificate.pdf30 Apr 2022
Copy of Layout Approval (in case of layout)File: Layout Plan Stellar Rhythmm.pdf30 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: NA Order Stellar Rhythmm.pdf30 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Stellar Rhythmm.pdf30 Apr 2022
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate.pdf30 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Stellar Rhythmm (first).pdf30 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Stellar Rhythm (First).pdf30 Apr 2022
CERSAI detailsFile: cersai Report.pdf30 Apr 2022
Proforma of Allotment letterFile: AGREEMENT TO SALE DRAFT - Uploaded RERA.pdf30 Apr 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep STELLAR RHYTHMM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near wakad13,700+ in Pune

2 kmSTELLAR RHYTHMMCompleted 82Lapsed / revoked 32Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: Wakadkar Patil Associates LLP

Wakadkar Patil Associates LLP has 1 registration on MahaRERA, including STELLAR RHYTHMM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that STELLAR RHYTHMM shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if STELLAR RHYTHMM is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of STELLAR RHYTHMM?

The registered promoter entity is Wakadkar Patil Associates LLP, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in STELLAR RHYTHMM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for STELLAR RHYTHMM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at STELLAR RHYTHMM?

The professionals named in the filing: Architect: Kimaya Associates Architects and Planners; Engineer: Kishor A Patil; Chartered Accountant: Pramod B Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STELLAR RHYTHMM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STELLAR RHYTHMM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STELLAR RHYTHMM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.