Home / Browse projects / Pune, Maharashtra / Stellar Homes - Phase I
Stellar Homes - Phase I
RG-MH-21495 · RERA P52100029687 · Last updated on MahaRERA portal: 11 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Stellar Homes - Phase I is a Residential / Group Housing project by Shyam Hanumant Wakadkar in Pune, Maharashtra, registered with MahaRERA as P52100029687 on 26 Jun 2021. Possession was promised by 30 Mar 2025 and is now 19 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameStellar Homes - Phase I
- TypeResidential / Group Housing
- Location
- Phase 2 Road
- Bhumkar Chowk to Rajiv Gandhi Info Tech Park
- Hinjavadi (CT)
- Mulshi
- Pune
- 411057
- Pincode411057
- RERA no.P52100029687
- ReraGenie IDRG-MH-21495
Builder
- NameShyam Hanumant Wakadkar
- Entity typeIndividual
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Jun 2021
- Promised completion30 Mar 2025
- Revised completionRevised to 30 Mar 2025 (originally 31 Mar 2024)
- Buildings1 building record
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing B | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Wing B: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed71
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Sangram Salunke Projection Studio |
| Engineer | Kiran Bagadi |
| Chartered Accountant | Parag Patwa and Associates |
| Chartered Accountant | Pramod Babulal Shah |
| Partner | Role in project |
|---|---|
| Shyam Hanumant Wakadkar | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExtension required for completion process and the same is proposed under provisions of 7 (2)
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 26 Feb 2025
Documents filed73
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RAJLUCKXMI REALCON BWING PH-1 FORM5.pdf | 11 Apr 2025 |
| OtherFile: final 06 feb 2024 completion certificate Hinjewadi.pdf | 6 Apr 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REG CERTIFICATE.pdf | 26 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate.pdf | 26 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PH 1 B WING.pdf | 25 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PH 1 B WING.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PH1 B WING.pdf | 25 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 B WING.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PH1 B WING.pdf | 25 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 B WING.pdf | 25 Oct 2024 |
| Layout approvalFile: Club House Plan.pdf | 2 May 2024 |
| Layout approvalFile: New layout Entire plot.PDF | 2 May 2024 |
| Layout approvalFile: New layout Entire plot.PDF | 2 May 2024 |
| Building plan approvalFile: B wing 13th floor plan.PDF | 2 May 2024 |
| Copy of Layout Approval (in case of layout)File: New layout Entire plot.PDF | 2 May 2024 |
| Copy of Layout Approval (in case of layout)File: New layout Entire plot.PDF | 2 May 2024 |
| Copy of Layout Approval (in case of layout)File: Club House Plan.pdf | 2 May 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: B wing 13th floor plan.PDF | 2 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: NEW COMMECEMENT CERTIFICATE 29 april 24.pdf | 2 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ph 1 B wing FORM 1 Q4.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ph 1 B wing FORM 2 Q4.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ph 1 B wing Form 3 Q4.pdf | 19 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A New Eng Quality assuarnce.pdf | 10 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf | 10 Apr 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Seperate BAnk account confirmation.pdf | 10 Apr 2024 |
| Declaration in FORM BFile: FORM B Phase 1_organized.pdf | 6 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B WING march 24.pdf | 1 Apr 2024 |
| Layout approvalFile: ph 1 plan stellar.pdf | 30 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: ph 1 plan stellar.pdf | 30 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1.pdf | 30 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2.pdf | 30 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3.pdf | 30 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1_0001.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 2 Q B WING_.pdf | 29 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_.pdf | 29 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 2Q B WING.pdf | 29 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: HOMES B WING SOLD UNSOLD 2Q_.pdf | 29 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3_CA Certificate _0001.pdf | 29 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 STELLAR HOMES B WING 2Q.pdf | 29 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase I Form 5 FY 2022-23 signed copy.pdf | 21 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5_21-22_Signed.pdf | 18 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1_0001.pdf | 1 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2.pdf | 1 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form 3_0001.pdf | 1 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Rajluckxmi_ 4th Qtr Sold Inventory.pdf | 1 Jun 2022 |
| CERSAI detailsFile: Cersai SBI Report_7-1-2022_compressed.pdf | 8 Jan 2022 |
| Copy of the legal title reportFile: Updated Search and Title Report_compressed.pdf | 7 Jan 2022 |
| Details of encumbrancesFile: Self Encumbrance Ltr -SBI.pdf | 7 Jan 2022 |
| Proforma of Allotment letterFile: Flat Agreement Updated Draft - Final 04- Jan - 2022.pdf | 7 Jan 2022 |
| Proforma of Allotment letterFile: Sale Agreement- R.pdf | 25 Aug 2021 |
| Copy of the legal title reportFile: CORRIGENDUM -to Search Title dt 10 05 2021.pdf | 2 Jul 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf | 18 Jun 2021 |
| PAN CardFile: Pancard.pdf | 15 Jun 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 8 Jun 2021 |
| OtherFile: PMRDA NOC.pdf | 8 Jun 2021 |
| Layout approvalFile: Stellar Homes -Layout.pdf | 7 Jun 2021 |
| Building plan approvalFile: Building Plan 1.pdf | 7 Jun 2021 |
| Building plan approvalFile: Building Plan 2.pdf | 7 Jun 2021 |
| Building plan approvalFile: Building Plan 3.pdf | 7 Jun 2021 |
| Building plan approvalFile: Building Plan 4.pdf | 7 Jun 2021 |
| Building plan approvalFile: Building Plan 5.pdf | 7 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Stellar Homes -Layout.pdf | 7 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf | 7 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf | 7 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf | 7 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf | 7 Jun 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan 5.pdf | 7 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 7 Jun 2021 |
| Declaration in FORM BFile: Form B Affidavit.pdf | 7 Jun 2021 |
| Proforma of Allotment letterFile: Draft Agreement.pdf | 7 Jun 2021 |
| Proforma of Allotment letterFile: Draft Allotment Letter.pdf | 7 Jun 2021 |
| Copy of the legal title reportFile: Search Report R.pdf | 26 May 2021 |
| Details of encumbrancesFile: NO Encumbrances.pdf | 26 May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 73 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Stellar Homes - Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhumkar Chowk to Rajiv Gandhi Info Tech Park13,700+ in Pune
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: Shyam Hanumant Wakadkar
Shyam Hanumant Wakadkar has 2 registrations on MahaRERA, including Stellar Homes - Phase I and Stellar Homes Phase 2 - A wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Stellar Homes - Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Stellar Homes - Phase I is delayed beyond 30 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Stellar Homes - Phase I?
The registered promoter entity is Shyam Hanumant Wakadkar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Stellar Homes - Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Stellar Homes - Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Stellar Homes - Phase I?
The professionals named in the filing: Architect: Ar Sangram Salunke Projection Studio; Engineer: Kiran Bagadi; Chartered Accountant: Parag Patwa and Associates; Chartered Accountant: Pramod Babulal Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Stellar Homes - Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback