Home / Browse projects / Mumbai Suburban, Maharashtra / Srushti Raj Siddhi
Srushti Raj Siddhi
RG-MH-09605 · RERA P51800002790 · Last updated on MahaRERA portal: 24 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 17 complaints at MahaRERA
- Completion date moved by 60 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Srushti Raj Siddhi is a Residential / Group Housing project by CHINNAIAH VENKATESH GOWDA in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002790 on 4 Aug 2017. Possession is promised by 25 Dec 2027. The completion date has moved by 60 months from the original filing. 88 of the 133 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 17 complaints are on record with the regulator.
At a glance
Project
- NameSrushti Raj Siddhi
- TypeResidential / Group Housing
- Location
- Road No. 13
- Tilak Nagar
- Kurla
- Mumbai Suburban
- 400089
- Pincode400089
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800002790
- ReraGenie IDRG-MH-09605
Builder
- NameCHINNAIAH VENKATESH GOWDA
- Entity typeIndividual
- Other registrations8 more →
- No longer live6 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Aug 2017
- Promised completion25 Dec 2027
- Revised completionRevised to 25 Dec 2027 (originally 25 Dec 2022)
- Buildings1 building record
- Documents filed81 files
Current status
Figures as on 24 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Srushtiraj Siddhi A and B Wing | NA | 18 | 17 | 133 | 0 | 133 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 53%.
Srushtiraj Siddhi A and B Wing: 56% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 53% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 35% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Progress on shared amenities15
As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 8% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 5% |
| Electrical meter room, sub-station, receiving station | Yes | 15% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed45
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Srushtiraj Siddhi A and B Wing | NA | Rs 28.94 cr | Rs 15.34 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Iqbal Singh |
| Engineer | Associated Consultants through its Proprietor Mr Vikas Vinayak Gokhale |
| Engineer | Neeraj Dubey |
| Chartered Accountant | Omprakash Mishra |
| Chartered Accountant | Suresh Agarwal |
| Chartered Accountant | Vishal Kumar Shaw |
| Chartered Accountant | NITIN VARE |
| Partner | Role in project |
|---|---|
| CHINNAIAH VENKATESH GOWDA | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe could not get the required approvals from MHADA in the right timeframe due to the ongoing pandemic and price fluctuations due to war which has caused the project's delay. Therefore we request you to extend the expiry date of the project under section 6 of Real Estate (Regulation and Development Act, 2016)
Reason as filed by the promoterDelay due to pandemic affects and new guidelines from BMC for pollution control which are resulting in expenses unaccounted for and therefore need more time to mitigate.
Reason as filed by the promoterDue to materialsourcing difficulty, Labour team deficiency resulting from continuous rain through out the year which restricted construction. The project is 70 percent completed and the balance shall be completed within the proposed timeline
Complaints filed with MahaRERA17
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197791 | Vilas Kesarkar | Chinnaiah Gowda | 28/07/2021 |
| CC006000000364528 | prakash pralhad tanksale | Chinnaya Gauda | 28/02/2023 |
| CC006000000479869 | Sunil Sadashiv Kanse | Srushti Raj Enterprises India Ltd. | 31/03/2024 |
| CC006000000479859 | Sujit V Nair | Srushti Raj Enterprises India Ltd. | 31/03/2024 |
| CC12500410 | Sandesh Vilas Patkar | CHINNAIAH VENKATESH GOWDA | 07/02/2025 |
| CC12503946 | Jignesh Shah | CHINNAIAH VENKATESH GOWDA | 10/11/2025 |
| CC12504385 | Savalaram Ganpat Agawane | CHINNAIAH VENKATESH GOWDA | 09/12/2025 |
| CC12504203 | Avinash Pore | CHINNAIAH VENKATESH GOWDA | 28/11/2025 |
| CC12504382 | Sudam Laxman Gite | CHINNAIAH VENKATESH GOWDA | 09/12/2025 |
| CC12504384 | Sharad Rambhau Ghuge | CHINNAIAH VENKATESH GOWDA | 09/12/2025 |
| CC12504469 | Tanvvi Naik | CHINNAIAH VENKATESH GOWDA | 15/12/2025 |
| CC12504470 | suhas desai | CHINNAIAH VENKATESH GOWDA | 15/12/2025 |
| CC12604151 | CHINNAIAH VENKATESH GOWDA | SHARAD RAMBHAU GHUGE | 02/07/2026 |
| CC12604166 | CHINNAIAH VENKATESH GOWDA | sudam laxman gite and manisha sudam gite | 03/07/2026 |
| CC12604228 | CHINNAIAH VENKATESH GOWDA | Tanvi Amey Naik | 06/07/2026 |
| CC12604237 | CHINNAIAH VENKATESH GOWDA | Savita Suhas Desai Suhas Sadanand Sesai | 06/07/2026 |
| CC12604244 | CHINNAIAH VENKATESH GOWDA | Savalaram Ganpat Agawane Sangeeta Savalaram Agawane | 06/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 25 Dec 2027
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 105.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Bldg No 105 Form 2.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 105 Dec 25.pdf | 24 Apr 2026 |
| Form 1File: 105 FORM 1 Q4 2425.pdf | 25 Dec 2025 |
| Form 2File: 105 FORM 2 Q4 2425.pdf | 25 Dec 2025 |
| Form 3File: 105 FORM 3 Q4 2425 COMP.pdf | 25 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 105 DISCLOSURE Q4 2425.pdf | 25 Dec 2025 |
| Form 1File: FORM 1 Q1 2526.pdf | 25 Dec 2025 |
| Form 2File: FORM 2 Q1 2526.pdf | 25 Dec 2025 |
| Form 3File: FORM 3105 Q1 of FY 2025 COMP.pdf | 25 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE Q1 2526.pdf | 25 Dec 2025 |
| Form 1File: FORM 1 Q1 2526.pdf | 25 Dec 2025 |
| Form 2File: FORM 2 Q1 2526.pdf | 25 Dec 2025 |
| Form 3File: FORM 3 Q2 FY 2025-26.pdf | 25 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE Q2 2526.pdf | 25 Dec 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 105 Rera FORM 1 29 01 2025.pdf | 23 Feb 2025 |
| Certificates of CA (Form 3)File: FORM 3 Q3 FY 2425.pdf | 23 Feb 2025 |
| Certificates of CA (Form 5)File: FORM 5 105.pdf | 23 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 105 q3.pdf | 23 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 105_Disc Sold_Booked Inventory 31_12_24.pdf | 23 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: 4.pdf | 11 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 10 Apr 2024 |
| Building plan approvalFile: iod.pdf | 5 Apr 2024 |
| Building plan approvalFile: iod.pdf | 5 Apr 2024 |
| Building Plan Approval (IOD)File: iod.pdf | 5 Apr 2024 |
| Building Plan Approval (IOD)File: iod.pdf | 5 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A 105- 31-03-23.pdf | 12 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 105 22-23.pdf | 11 Dec 2023 |
| Declaration in FORM BFile: form b 105_NOTARIZED.pdf | 9 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A 105-30-09-23.pdf | 9 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE 105- 30-09-23.pdf | 9 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf | 23 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf | 23 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-213.pdf | 23 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf | 23 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: FCC 13 06 2023.pdf | 14 Jun 2023 |
| Other - TechnicalFile: Bldg no 105 CC.pdf | 1 Jun 2023 |
| Other - TechnicalFile: 1 (1)_11zon.pdf | 1 Jun 2023 |
| Other - TechnicalFile: 2_11zon.pdf | 1 Jun 2023 |
| Other - TechnicalFile: 05 Office Note 5.pdf | 29 May 2023 |
| Other - TechnicalFile: MYSCAN_20230411_0004.PDF | 29 May 2023 |
| Other - TechnicalFile: MYSCAN_20230411_0005.PDF | 29 May 2023 |
| Other - TechnicalFile: MYSCAN_20230411_0003.PDF | 29 May 2023 |
| Other - TechnicalFile: MYSCAN_20230411_0007.PDF | 29 May 2023 |
| Other - TechnicalFile: MYSCAN_20230411_0008.PDF | 29 May 2023 |
| Other - TechnicalFile: DOC.pdf | 13 Apr 2023 |
| Other - TechnicalFile: NEW OFFER LETTER.pdf | 13 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FY 2018-19 Form 1 Final Architect Certificate Digital Signed.pdf | 19 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FY 2019-20 Form 1 Final Architect Certificate Digital Signed.pdf | 19 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FY 2020-21 Form 1 Final Architect Certificate Digital Signed_compressed.pdf | 19 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FY 2021-22 Form 1 Final Architect Certificate Digital Signed.pdf | 19 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 2020-21 Form 2A.pdf | 19 Sep 2022 |
| Certificates of CA (Form 5)File: Final Form 5 105 Signed.pdf | 19 Sep 2022 |
| Certificates of CA (Form 5)File: Final Form 5 -Signed.pdf | 19 Sep 2022 |
| Certificates of CA (Form 5)File: Final Form 5 - Signed.pdf | 19 Sep 2022 |
| Certificates of CA (Form 5)File: Final Form 5 Signed_compressed.pdf | 19 Sep 2022 |
| Declaration about Commencement CertificateFile: Commencement Certificate.pdf | 5 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure_compressed.pdf | 5 Aug 2022 |
| CERSAI detailsFile: CERSAI_compressed.pdf | 5 Aug 2022 |
| Proforma of Allotment letterFile: Allottment Letter1.pdf | 5 Aug 2022 |
| Proforma of Allotment letterFile: sale (1)_compressed.pdf | 5 Aug 2022 |
| Proforma of Allotment letterFile: sale (2)_compressed.pdf | 5 Aug 2022 |
| Proforma of Allotment letterFile: sale (3)_compressed.pdf | 5 Aug 2022 |
| Layout approvalFile: Amended Plan_compressed.pdf | 17 Oct 2019 |
| Copy of Layout Approval (in case of layout)File: Amended Plan_compressed.pdf | 17 Oct 2019 |
| Certificates of CA (Form 3)File: Form 3 Bldg 105 March 2018.pdf | 30 Jan 2019 |
| Certificates of CA (Form 5)File: Form 5 CA Signed Bldg No105.pdf | 30 Jan 2019 |
| Declaration in FORM BFile: Form B 105.pdf | 1 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 1.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 2.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate 3.pdf | 28 Jul 2017 |
| Certificates of CA (Form 5)File: CA Certificate 5.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: RERA Draft Agreement 105.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: IMG_20100101_0002.pdf | 10 Jul 2017 |
| Layout approvalFile: PLAN.pdf | 8 Jul 2017 |
| PAN CardFile: IMG_20100101_0001.pdf | 8 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 8 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: PLAN.pdf | 8 Jul 2017 |
| Building plan approvalFile: pg 931 to 935 IOD_signed (4).pdf | 7 Jul 2017 |
| Building Plan Approval (IOD)File: pg 931 to 935 IOD_signed (4).pdf | 7 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Srushti Raj Siddhi on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tilak Nagar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 510 registered projects within 2 km.
Atmosphere O2 Tower-G
Atmosphere Realty Pvt Ltd
VARDHAN HEIGHTS
VARDHAN HOUSING
Promesa Midtown
Darshan Properties
ELYSIUM
KRIPA ELITE HOMES
JADE
PRIYA CONSTRUCTIONS
Gami and Jaydeep Elanza
M/S REAL INFRASTRUCTURE CO
See every Mumbai Suburban project, with the district possession charts
Builder: CHINNAIAH VENKATESH GOWDA
CHINNAIAH VENKATESH GOWDA has 9 registrations on MahaRERA, including SRUSHTIRAJ TOWER and Srushti Raj Siddhi. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Srushti Raj Siddhi is delayed beyond 25 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Srushti Raj Siddhi?
The registered promoter entity is CHINNAIAH VENKATESH GOWDA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Srushti Raj Siddhi?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Srushti Raj Siddhi?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Srushti Raj Siddhi?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Srushti Raj Siddhi?
The professionals named in the filing: Architect: Iqbal Singh; Engineer: Associated Consultants through its Proprietor Mr Vikas Vinayak Gokhale; Engineer: Neeraj Dubey; Chartered Accountant: Omprakash Mishra; Chartered Accountant: Suresh Agarwal; Chartered Accountant: Vishal Kumar Shaw. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Srushti Raj Siddhi?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback