ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SRI PARKVIEW

Registered No litigation declared Mixed project

SRI PARKVIEW

By Sri Lifespace

RG-MH-06053 · RERA P51700051657 · Last updated on MahaRERA portal: 23 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 86%
38 of 43Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

SRI PARKVIEW is a Mixed project by Sri Lifespace in Thane, Maharashtra, registered with MahaRERA as P51700051657 on 27 Jun 2023. Possession is promised by 31 Dec 2027. 5 of the 43 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSRI PARKVIEW
  • TypeMixed
  • Location
    • Vasant valley road
    • khadakpada
    • Gandhare
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700051657
  • ReraGenie IDRG-MH-06053

Builder

  • NameSri Lifespace
  • Entity typePartnership
  • PartnersVinod Shrichand Kimtani, Mukesh Gobindram Kimtani, Sanjay Shrichand Kimtani, Shailesh Sagarmal Jain
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed89 files

Current status

12%5 of 43 units booked
52.1%Work done, per cost certificate

Figures as on 23 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sri Parkview / Wing BNA2321331043

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 86%.

Sri Parkview / Wing B: 35% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure86%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed112

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots112
Closed/Covered112

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,155 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2024

Approvals and building plan

Sanctioning authorityKALYAN DOMBVALI MUNICIPAL COPORATION
Permissible FSI5082.0
Proposed, not sanctioned4,333 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO. 2 TO 5, ORBIT COMMERCIAL COMPLEX, BARAVE ROAD, GODREJ HILL, KHADAKPADA, KALYAN (W)
Estimated costRs 35.11 cr
Cost incurredRs 18.30 cr
Work done52.12%
BuildingWingEstimatedIncurred
Sri Parkview / Wing BNARs 35.11 crRs 18.30 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT INC KANADE
EngineerJW CONSULTANT
EngineerDILIP PATARE
Chartered AccountantKishnani and Co Mukesh Kishnani
Chartered AccountantKAPIL MAKHIJA
PartnerRole in project
Sri Lifespace-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: PARKVIEW FORM 1.pdf23 Apr 2026
Withdrawal Update Form 2File: FORM 2 SRI PARKVIEW.pdf23 Apr 2026
Withdrawal Update Form 3File: SRI PARKVIEW FORM 3.pdf23 Apr 2026
Withdrawal Update Form 1File: SRI PARKVIEW FORM 1.pdf16 Feb 2026
Withdrawal Update Form 2File: SRI PARKVIEW FORM 2.pdf16 Feb 2026
Withdrawal Update Form 3File: PARKVIEW RERA FORM-3.pdf16 Feb 2026
Withdrawal Update Form 1File: PARKVIEW ARCHITECT CERTIFICATE.pdf23 Oct 2025
Withdrawal Update Form 2File: SRI PARKVIEW FORM 2.pdf23 Oct 2025
Withdrawal Update Form 3File: FINAL FORM 3-Parkview Rera Certificate.pdf23 Oct 2025
Form 2A (FY 2024-2025)File: PARKVIEW FORM 2A .pdf21 Oct 2025
Form 5 (FY 2024-2025)File: PARKVIEW FORM 5.pdf15 Oct 2025
Withdrawal Update Form 1File: PARKVIEW ARCHITECT CERTIFICATE .pdf8 Aug 2025
Withdrawal Update Form 2File: PARKVIEW FORM 2.pdf8 Aug 2025
Withdrawal Update Form 3File: SRI PARKVIEW FORM 3 SIGNED CA CERTIFICATE.pdf8 Aug 2025
Building plan approvalFile: SRI PARKVIEW LAYOUT PLAN1_compressed.pdf7 Aug 2025
Building plan approvalFile: SRI PARKVIEW APPROVAL PLAN 1.pdf7 Aug 2025
Building plan approvalFile: SRI PARKVIEW APPROVAL PLAN 2_compressed.pdf7 Aug 2025
Building plan approvalFile: SRI PARKVIEW APPROVAL PLAN -3_compressed.pdf7 Aug 2025
Building plan approvalFile: SRI PARKVIEW APPROVAL PLAN -4_compressed.pdf7 Aug 2025
Building plan approvalFile: SRI PARKVIEW APPROVAL PLAN 5_compressed.pdf7 Aug 2025
Building plan approvalFile: SRI PAKRVIEW APPROVAL PLAN 6_compressed.pdf7 Aug 2025
Withdrawal Update Form 1File: PARKVIEW ARCHITECT CERTIFICATE .pdf4 Aug 2025
Withdrawal Update Form 2File: PARKVIEW FORM 2.pdf4 Aug 2025
Withdrawal Update Form 3File: Sri Parkview FORM 3 SIGNED CA CERTIFICATE .pdf4 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PARKVIEW ARCHITECTS INC.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parkview- CA CERTIFICATE.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE PARKVIEW 001 (5 files merged).pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: PARKVIEW SOLD UNSOLD 001.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PARKVIEW QUALITY 001.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Sri Parkview form 5.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PARKVIEW ARCHITECTS CERTIFICATE.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Park view_0001 (1) (2 files merged)_compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PARKVIEW ENGINEER CERTIFICATE 001 (5 files merged).pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: PARKVIEW UNSOLD 001 (2 files merged).pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PARKVIEW ARCHITECTS 001 (3 files merged).pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PARKVIEW ENGINEER CERTIFICATE.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD SRI PARKVIEW (2 files merged).pdf20 Oct 2024
Form 5 (FY 2023-2024)File: Sri Parkview ANNUAL CERTIFICATE.pdf25 Sep 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: PARKVIEW UNSOLD .pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B-PARKVIEW ARCHITECTS 001 (3 files merged).pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PARKVIEW-ENG 001 (3 files merged).pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE PARKVIEW.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PARKVIEW-ARCHITECTS-compressed.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: PARKVIEW - SOLD UNSOLD 001 (2 files merged)-compressed.pdf15 Apr 2024
Other - FinanceFile: PARKVIEW SELF DECLARATION.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CA CERTIFICATE.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFCATE.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold -Sri parkview.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 17 OCT 2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sri Parkview 16 oct 2023_compressed.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sri Parkview.pdf6 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 Sri Parkview.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Doc 2023-06-08 125032 (1)_compressed (1).pdf8 Jun 2023
Layout approvalFile: sheet 1.PDF6 Jun 2023
Building plan approvalFile: sheet 8.PDF6 Jun 2023
Building plan approvalFile: sheet 9.PDF6 Jun 2023
Building plan approvalFile: sheet 10.PDF6 Jun 2023
Building plan approvalFile: sheet 11.PDF6 Jun 2023
Building plan approvalFile: sheet 12.PDF6 Jun 2023
PAN CardFile: sri lifespace pan.pdf6 Jun 2023
Copy of the legal title reportFile: Legal title report.pdf6 Jun 2023
Details of encumbrances concerned to FinanceFile: Finance declaration.pdf6 Jun 2023
Details of encumbrances concerned to FinanceFile: Legal declaration.pdf6 Jun 2023
Details of encumbrances concerned to LegalFile: Finance declaration.pdf6 Jun 2023
Details of encumbrances concerned to LegalFile: Legal declaration.pdf6 Jun 2023
Copy of Layout Approval (in case of layout)File: sheet 1.PDF6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: sheet 8.PDF6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: sheet 9.PDF6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: sheet 10.PDF6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: sheet 11.PDF6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: sheet 12.PDF6 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf6 Jun 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf6 Jun 2023

How this compares with Thane

12%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SRI PARKVIEW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near khadakpada7,600+ in Thane

2 kmSRI PARKVIEWCompleted 80Lapsed / revoked 44Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 252 registered projects within 2 km.

Builder: Sri Lifespace

Sri Lifespace has 2 registrations on MahaRERA, including 36 Mansions A wing and SRI PARKVIEW. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SRI PARKVIEW is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SRI PARKVIEW?

The registered promoter entity is Sri Lifespace, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SRI PARKVIEW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SRI PARKVIEW?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SRI PARKVIEW?

The professionals named in the filing: Architect: ARCHITECT INC KANADE; Engineer: JW CONSULTANT; Engineer: DILIP PATARE; Chartered Accountant: Kishnani and Co Mukesh Kishnani; Chartered Accountant: KAPIL MAKHIJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRI PARKVIEW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRI PARKVIEW. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRI PARKVIEW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.