Home / Browse projects / Pune, Maharashtra / SPLENDID RADIANCE
SPLENDID RADIANCE
RG-MH-37789 · RERA P52100019065 · Last updated on MahaRERA portal: 30 Mar 2022
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SPLENDID RADIANCE is a Others project by Yashada Brothers in Pune, Maharashtra, registered with MahaRERA as P52100019065 on 28 Dec 2018. The registration is recorded completed; possession was promised by 30 Jun 2023.
At a glance
Project
- NameSPLENDID RADIANCE
- TypeOthers
- Location
- S NO 75
- WAKAD
- Mulshi
- Pune
- 411057
- Pincode411057
- RERA no.P52100019065
- ReraGenie IDRG-MH-37789
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on28 Dec 2018
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings2 building records
- Documents filed66 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A BUILDING | NA | 13 | 0 | 0 | 0 | 0 |
| B BUILDING | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
A BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed81
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A BUILDING | 31 | 10 | 41 |
| B BUILDING | 31 | 9 | 40 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUBHASH BHIMAJI VINODE | Wakad | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR SHITESH AGRAWAL |
| Partner | Role in project |
|---|---|
| Yashada Brothers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Dec 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Jun 2021
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of ConveyanceFile: CONVEYANCE DEED SPLENDID RADIANCE SUBHASH VINODE.pdf | 30 Mar 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: S No 75 Wakad form 4.pdf | 30 Aug 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Splendid Radiance Soc Registration Certificate.pdf | 25 Aug 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FINAL COMPLETION CERTIFICATE.pdf | 18 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: YB_Form 5_2019-2020.pdf | 13 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf | 2 Feb 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_Splendid Radiance_30-09-2020.PDF | 2 Feb 2021 |
| Certificates of CA (Form 3)File: Form 3 Radience YB.pdf | 2 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate UPTO 12 FLOORS.pdf | 2 Sep 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate Splendid Radiance.PDF | 2 Sep 2020 |
| Certificates of CA (Form 3)File: Form 3_Splendid Radiance.pdf | 2 Sep 2020 |
| Details of encumbrancesFile: Letter.pdf | 8 Aug 2020 |
| Certificates of CA (Form 3)File: Form 3 Radiance.pdf | 10 Jul 2020 |
| Layout approvalFile: Layout.pdf | 6 Jan 2020 |
| Building plan approvalFile: A building 3 to 12.pdf | 6 Jan 2020 |
| Building plan approvalFile: B building 2 to 9.pdf | 6 Jan 2020 |
| Building plan approvalFile: B building 2 to 9.pdf | 6 Jan 2020 |
| Building plan approvalFile: B building podium 1st.pdf | 6 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 6 Jan 2020 |
| Building Plan Approval (IOD)File: A building 3 to 12.pdf | 6 Jan 2020 |
| Building Plan Approval (IOD)File: B building 2 to 9.pdf | 6 Jan 2020 |
| Building Plan Approval (IOD)File: B building 2 to 9.pdf | 6 Jan 2020 |
| Building Plan Approval (IOD)File: B building podium 1st.pdf | 6 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - 75 30-09-2019.pdf | 6 Jan 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 y brothers.pdf | 26 Dec 2019 |
| Layout approvalFile: Layout.pdf | 7 Jul 2019 |
| Building plan approvalFile: 2.pdf | 7 Jul 2019 |
| Building plan approvalFile: 3.pdf | 7 Jul 2019 |
| Building plan approvalFile: 4.pdf | 7 Jul 2019 |
| Building plan approvalFile: 5_compressed.pdf | 7 Jul 2019 |
| Building plan approvalFile: 6.pdf | 7 Jul 2019 |
| Building plan approvalFile: 7.pdf | 7 Jul 2019 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 2.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 3.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 4.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 5_compressed.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 6.pdf | 7 Jul 2019 |
| Building Plan Approval (IOD)File: 7.pdf | 7 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: REVISIED SANCTION COMMENCMENT CERTIFICATE.pdf | 7 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect cert_compressed.pdf | 7 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering cert.pdf | 7 Jul 2019 |
| Form 2AFile: Form 2A_Splendid Radiance (1).pdf | 24 Jun 2019 |
| Proforma of Allotment letterFile: Wakad Allotment Form -Pg 1st.pdf | 24 Dec 2018 |
| Proforma of Allotment letterFile: Wakad Allotment Form- Pg-2nd.pdf | 24 Dec 2018 |
| Proforma of Allotment letterFile: Agreement Splendid Rediance - Draft.pdf | 21 Dec 2018 |
| Layout approvalFile: Plan Layout.pdf | 20 Dec 2018 |
| Building plan approvalFile: PLAN NO - 2.pdf | 20 Dec 2018 |
| Building plan approvalFile: PLAN NO - 3.pdf | 20 Dec 2018 |
| Building plan approvalFile: PLAN NO - 4.pdf | 20 Dec 2018 |
| Building plan approvalFile: PLAN NO - 5.pdf | 20 Dec 2018 |
| Building plan approvalFile: PLAN NO - 6.pdf | 20 Dec 2018 |
| PAN CardFile: PAN.pdf | 20 Dec 2018 |
| Copy of the legal title reportFile: SEARCH REPORT - WAKAD 75 8-10-2018 21212.pdf | 20 Dec 2018 |
| Details of encumbrancesFile: No Encumberance.pdf | 20 Dec 2018 |
| Copy of Layout Approval (in case of layout)File: Plan Layout.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: PLAN NO - 2.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: PLAN NO - 3.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: PLAN NO - 4.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: PLAN NO - 5.pdf | 20 Dec 2018 |
| Building Plan Approval (IOD)File: PLAN NO - 6.pdf | 20 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - 75 WAKAD 2018 1112.pdf | 20 Dec 2018 |
| Declaration in FORM BFile: promoters affidavit.pdf | 20 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_Wakad-compressed.pdf | 20 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Splendid Radiance_Engg Certificate.pdf | 20 Dec 2018 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 20 Dec 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| YASHADA FLORENZAP52100029345 | PIMPRI, Pune | May 2021 | Certificate Signed | Jun 2025 | Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
Keep SPLENDID RADIANCE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WAKAD13,700+ in Pune
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: Yashada Brothers
Yashada Brothers has 3 registrations on MahaRERA, including SPLENDID RADIANCE and YASHADA FLORENZA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SPLENDID RADIANCE is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SPLENDID RADIANCE?
The registered promoter entity is Yashada Brothers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SPLENDID RADIANCE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SPLENDID RADIANCE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SPLENDID RADIANCE?
The professionals named in the filing: Architect: AR SHITESH AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SPLENDID RADIANCE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback