Home / Browse projects / Dakshina Kannada, Karnataka / SOMAYAJI GREENWOOD
SOMAYAJI GREENWOOD
By Somayaji Estates Private Limited
RG-KA-66600 · RERA PRM/KA/RERA/1257/334/PR/300622/005024 · Last updated on RERA Karnataka portal: 14 Jul 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
SOMAYAJI GREENWOOD is a Mixed Development project by Somayaji Estates Private Limited in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/300622/005024 on 30 Jun 2022. Possession is promised by 30 Jun 2026. The completion date has moved by 12 months from the original filing. 0 of the 85 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.
At a glance
Project
- NameSOMAYAJI GREENWOOD
- TypeMixed Development
- Location
- Mangalore
- Dakshina Kannada
- 575006
- Pincode575006
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/300622/005024
- ReraGenie IDRG-KA-66600
Builder
- NameSomayaji Estates Private Limited
- Entity typeCompany
- CINU70101KA1993PTC014586
- GSTIN29AAFCS3435F1ZC
- Authorized SignatoryB. Raghunath Somayaji
- Managing DirectorB. R. Somayaji
- DirectorsBANTWAL RAGHUNATH SOMAYAJI, ARUNDHATHI RAGHUNATH SOMAYAJI
- Project HeadBANTWAL RAGHUNATH SOMAYAJI
- Other registrations2 more →
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Jun 2022
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed151 files
Current status
Figures as on 14 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SOMAYAJI GREENWOOD | - | - | - | - | - | 85 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 18 construction stages are filed complete. The stage furthest along is Masonry Construction, at 90%.
Building: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 90% |
| Plastering inside , outside & Ceiling | 50% |
| Joinery: Doors, Windows, Ventilators etc | 50% |
| Basic work of Water supply, Sanitary and Electrification | 50% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 25% |
| Railing and Grill fixing | 25% |
| Electrification, Water supply and Sanitary Finishing | 30% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 30% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 30% |
| Internal and External work including landscapes as per sanctioned drawings | 10% |
Progress on shared amenities40
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 30% |
| Sewage and Drainage System | Yes | 30% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 50% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Solid waste management and disposal | Yes | 50% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 30% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 40% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 56% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 56% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 40% |
| Lifts | Yes | 50% |
| Corridor/Lobbies | Yes | 40% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 56% |
| Basement | Yes | 100% |
| Terrace | Yes | 50% |
| Outer Wall | Yes | 60% |
| Open parking areas | Yes | 56% |
| Provision for lodging of management staff and security staff | Yes | 56% |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| somayaji estates pvt ltd, 6th floor ,essel tower, ,bunts hostel circle,mangalore | - | - |
| Somayaji Estates Pvt Ltd | - | - |
| Somayaji Estates Pvt Ltd | - | - |
| SOMAYAJI ESTATES PVT LTD | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 12.00 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | damodar shenoy |
| Engineer | Anand Bhat |
| Chartered Accountant | Ganesh Rao P |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed151
As listed on the registration, under the names the promoter filed them with; the newest 80 of 151 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/300622/005024 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Samayoji Greenwood.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Samayoji Greenwood.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Samayoji Greenwood.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA March 26 Greenwood.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect March 26 Greenwood.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer March 26 Greenwood.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4- Samayoji Greenwood.pdf | 12 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Samayoji Greenwood.pdf | 12 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6- Samayoji Greenwood.pdf | 12 Mar 2026 |
| Q3 2025-26 Water supply and sewage board | 12 Mar 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 12 Mar 2026 |
| Q3 2025-26 KPTCL- BESCOM | 12 Mar 2026 |
| Q3 2025-26 Fire and Safety | 12 Mar 2026 |
| Affidavit - Clarification on PlanFile: 1 Affidavit - Clarification on Plan.pdf | 3 Mar 2026 |
| Covering LetterFile: 2 Covering Letter.pdf | 3 Mar 2026 |
| ARCHITECT CERTIFICATE FOR COMPLETED WORKFile: ARCHITECT CERTIFICATE FOR COMPLETED WORK.pdf | 3 Mar 2026 |
| ARCHITECT CERTIFICATE FOR PENDING WORKFile: ARCHITECT CERTIFICATE FOR PENDING WORK.pdf | 3 Mar 2026 |
| Engineer Certificate - Pending WorkFile: Engineer Certificate - Pending Work.pdf | 3 Mar 2026 |
| Engineer Certificate for Status of workFile: Engineer's Certificate for Status of work.pdf | 3 Mar 2026 |
| Form Ex3 CA Fund UtilisedFile: Form Ex3 CA Fund Utilised.pdf | 3 Mar 2026 |
| FormEx4 CA Fund RequiredFile: FormEx4 CA Fund Required.pdf | 3 Mar 2026 |
| Reason for ExtensionFile: Reason for Extension.pdf | 3 Mar 2026 |
| Sold Unsold DetailsFile: SoldUnsoldDetails.xlsx | 3 Mar 2026 |
| Extension AffidavitFile: Extension Affidavit.pdf | 3 Mar 2026 |
| Extension Form BFile: Extension Form B.pdf | 3 Mar 2026 |
| Query AnswersFile: Query Answers.pdf | 3 Mar 2026 |
| UPPER GROUND SECOND THIRD AND FOURTH FLOOR PLANSFile: UPPER GROUND SECOND THIRD AND FOURTH FLOOR.PDF | 9 Apr 2022 |
| LOWER GROUND AND FIRST FLOOR PLANSFile: LOWER GROUND AND FIRST FLOOR.PDF | 9 Apr 2022 |
| Non- litigation affidavitFile: Affidavit - Non Litigation-green wood.pdf | 24 Feb 2022 |
| KSPCB NOCFile: KPSCB NOC Greenwood.pdf | 24 Feb 2022 |
| MESCOM NOCFile: MESCOM NOC - GREENWOOD.pdf | 24 Feb 2022 |
| WATER NOCFile: greenwood - Water NOC.pdf | 24 Feb 2022 |
| UPPER GROUND,2,3,4TH FLOORFile: UPPER GROUND,2,3, AND 4TH FLOOR.PDF | 24 Feb 2022 |
| LOWER GROUND AND 1ST FLOORFile: LOWER GROUND,1ST FLOOR.PDF | 24 Feb 2022 |
| SITE PLANFile: SITE PLAN.PDF | 24 Feb 2022 |
| title deed in the name of smt. Geetha ram, Narasimha Rao and others for extent 0.12 cents.File: Sale Deed - 12 Cents.pdf | 7 Jan 2022 |
| title deed in the name of Narasimha Rao and others for extent 0.12 cents. 2uploaFile: EC - Landlinks.pdf | 7 Jan 2022 |
| joint affidavit cum declarationFile: Affidavit cum Declaration.pdf | 7 Jan 2022 |
| NOC issued by KSPCB.File: NOC KSPCB.pdf | 7 Jan 2022 |
| MESCOM NOCFile: MESCOM NOC- Somayaji Greenwood.pdf | 7 Jan 2022 |
| WATER NOCFile: Water NOC - Somayaji Greenwood (1).pdf | 7 Jan 2022 |
| AGREEMENT FOR SALE WITH SPECIFICATIONFile: AGREEMENT FOR SALE WITH SPECIFICATION.pdf | 7 Jan 2022 |
| SALE DEEDFile: Sale Deed - Somayaji Greenwood.pdf | 7 Jan 2022 |
| title deed in the name of smt. Geetha ram, Narasimha Rao and others for extent 0.12 cents.File: Sale Deed - 12 Cents.pdf | 25 Dec 2021 |
| EC from 01-04-2006 to uptodate in the name of land owner and promoter in form-15.File: Latest EC - Form 15.pdf | 25 Dec 2021 |
| Non- litigation affidavit with respect the property regarding court cases Judicial/ tribunal and amFile: Affidavit cum Declaration.pdf | 25 Dec 2021 |
| NOC issued by Fire forceFile: Fire NOC.pdf | 25 Dec 2021 |
| NOC issued by KSPCBFile: NOC KSPCB.pdf | 25 Dec 2021 |
| NOC MESCOMFile: Landlinks MEscom NOC.pdf | 25 Dec 2021 |
| AOS in Notified GOK formatFile: Rera agreement SOMAYAJI GREENWOOD.pdf | 25 Dec 2021 |
| SALE DEED IN RERA FORMATFile: Sale Deed - Somayaji Greenwood.pdf | 25 Dec 2021 |
| STP PLANFile: STP TANK Provision Plan.pdf | 25 Dec 2021 |
| AFFIDAVIT 3(1)File: Affidavit -3(1).pdf | 25 Dec 2021 |
| AUTHORISED SIGNED COPY OF SPECIFICATIONFile: Specifications - Somayaji Greenwood.pdf | 25 Dec 2021 |
| RTC, survey 167/2P | - |
| Mutation, survey 167/2P | - |
| Encumbrance Certificate, survey 167/2P | - |
| Conversion/Alienation Order, survey 167/2P | - |
| Sale/Title/Gift Deed, survey 167/2P | - |
| Khatha, survey 167/2P | - |
| RTC, survey 162/7 | - |
| Mutation, survey 162/7 | - |
| Encumbrance Certificate, survey 162/7 | - |
| Conversion/Alienation Order, survey 162/7 | - |
| Sale/Title/Gift Deed, survey 162/7 | - |
| Khatha, survey 162/7 | - |
| RTC, survey 162/7 | - |
| Mutation, survey 162/7 | - |
| Encumbrance Certificate, survey 162/7 | - |
| Conversion/Alienation Order, survey 162/7 | - |
| Sale/Title/Gift Deed, survey 162/7 | - |
| Khatha, survey 162/7 | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| SOMAYAJI ELITE | NH169, SHAKTHINAGAR ROAD JUNCTION, KULSHEKAR, MANGALORE | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep SOMAYAJI GREENWOOD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 45 registered projects within 2 km.
LUCENT
M/s MOHTISHAM COMPLEXES PVT LTD
Rudraksh
Mukund MGM Realty
PRISTINE
Land Trades Builders and Developers
LOTUS ATHARVA
Lotus Properties
Kedar
Mukund MGM Realty
Ashoka Business Center
Mukund MGM Realty
See every Dakshina Kannada project, with the district possession charts
Builder: Somayaji Estates Private Limited
Somayaji Estates Private Limited has 3 registrations on RERA Karnataka, including Somayaji Kalpavruksha and SOMAYAJI ENCLAVE. Its filings declare 3 earlier projects, none of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if SOMAYAJI GREENWOOD is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SOMAYAJI GREENWOOD?
The registered promoter entity is Somayaji Estates Private Limited, a company as per the filing. Its CIN U70101KA1993PTC014586 and GSTIN 29AAFCS3435F1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SOMAYAJI GREENWOOD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SOMAYAJI GREENWOOD?
The professionals named in the filing: Architect: damodar shenoy; Engineer: Anand Bhat; Chartered Accountant: Ganesh Rao P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SOMAYAJI GREENWOOD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.