Home / Browse projects / Mumbai Suburban, Maharashtra / SOLITAIRE

Registered Litigation declared Others project

SOLITAIRE

By SOLITAIRE CONSTRUCTIONS

RG-MH-26463 · RERA P51800008101 · Last updated on MahaRERA portal: 28 Nov 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 93 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 93 months from the original
19 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 98%
42 of 156Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 247 documents Report an error

SOLITAIRE is a Others project by SOLITAIRE CONSTRUCTIONS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008101 on 18 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 93 months from the original filing. 114 of the 156 units on this registration are recorded sold or booked, and 19 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSOLITAIRE
  • TypeOthers
  • Location
    • N.L. Cross Road
    • Somwari Bazar
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008101
  • ReraGenie IDRG-MH-26463

Builder

  • NameSOLITAIRE CONSTRUCTIONS
  • Entity typePartnership
  • PartnersABDUL RAHIM VALIMOHAMMED BILAKHYA, ARVIND VALLABHDAS SHAH, IRFAN ABDULRAHIM BILAKHYA
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2019)
  • Buildings2 building records
  • Documents filed247 files

Current status

73%114 of 156 units booked
100.0%Work done, per cost certificate

Figures as on 28 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADITNA212048654
SOLITAIRE HEIGHTSNA2621984102

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 98%.

OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
SOLITAIRE HEIGHTS100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 28 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Closed/Covered42

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,466 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jul 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI6962.6
Proposed, not sanctioned6,963 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP 1 TO 4, MONICA ARCADE ,SUBHASH LANE,OFF DAFTARY RD, MALAD EAST M-97
Estimated costRs 71.96 cr
Cost incurredRs 71.96 cr
Work done100.0%
BuildingWingEstimatedIncurred
OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADITNARs 71.96 crRs 71.96 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS DADDY & ASSOCIATES
EngineerJAYESH SHAH
EngineerALTAF A HINGORA
EngineerSHAH STRUCTURALS PVT. LTD.
Chartered AccountantHIMANSHU TREVADIYA
Chartered AccountantJIGAR ZATAKIA
Chartered AccountantAMAR JUGALKISHOR PAREKH
PartnerRole in project
SOLITAIRE CONSTRUCTIONS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011971Mar 2019 → May 2025

Reason as filed by the promoterINITIAL DELAY DUE TO LOCKDOWN NO SUPPLY OF MATERIALS, SERVICES OF CONTRACTOR, ECONOMICAL CONDITION OF REAL ESTATE SECTOR MARKET SLOWDOWN AND PROLONGED DELAY IN OBTAINING NECESSARY APPROVAL OF THE AUTHORITY FOR THE AMENDED PLAN FOR UTILIAING BALANCE FSI INC CHANGE SCHEME AFTER OBTAINING CONSENT OF 60 FLAT OWNERS OUT OF TOTAL 82 OWNERS.

EXT51800008731Mar 2019 → Sep 2021

Reason as filed by the promoterEXTENDED DUE DATE WAS 30TH SEPTEMBER 2020 , PROMOTER COULD NOT COMPLETE THE PENDING WORK DUE TO VARIETY OF FACTORS MAINLY DUE TO NON-AVAILABILITY OF LABOUR BECAUSE OF COVID SITUATIONS, SHORTAGE OF MATERIALS ETC AND AS STATED IN DECLARATION CUM APPROVAL OF ALLOTTEES LETTER ATTACHED HEREWITH. ALSO PROMOTER FAMILY MEMBERS WERE HOSPITALISED AND TEAM WERE WORKING REMOTELY DUE TO WHICH IT WAS DIFFICULT IN OBTAINING APPROVAL OF ALLOTTEES , SAME HAS BEEN OBTAINED NOW AND ATTACHED HEREWITH. PROMOTER PRAYS HUMBLY THAT EXTENTION FOR 1 YEAR SHOULD BE GIVEN TO COMPLETE THE BALANCE WORK AND HANDOVER THE POS

EXT51800001595Mar 2019 → Mar 2020

Reason as filed by the promoterATTACHED IN OTHER AS PER OTHER ATTACHMENT

EA27102518178Mar 2019 → Dec 2026

Reason as filed by the promoterWe, Solitaire Construnctions, hereby declare the following with respect to the project “SOLITAIRE” bearing registration number P51800008101 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Certificat

Litigation declared1

CaseCourtStatus
1317/2014CITY CIVIL COURT DINDOSHIPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000196049Namrata ShindeSolitaire Construction19/02/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed247

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 247 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2017-2018)File: 1 Certificates of CA (Form 5) FY 17-18.pdf28 Nov 2025
Form 5 (FY 2018-2019)File: FORM 5 FY 2018-19.pdf28 Nov 2025
Form 5 (FY 2019-2020)File: FORM 5 FY 2019-20.pdf28 Nov 2025
Form 5 (FY 2020-2021)File: Form 5 FY 2020-21 final.pdf28 Nov 2025
Form 5 (FY 2022-2023)File: FORM 5-Annual Audit Report of Statutory CA FY 2022-23.pdf28 Nov 2025
Form 5 (FY 2023-2024)File: New Form-5 FY 2023-24.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: New Form-5 FY 2024-25.pdf28 Nov 2025
Form 2A (FY 2017-2018)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2018-19).pdf29 Oct 2025
Form 2A (FY 2018-2019)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2018-19).pdf29 Oct 2025
Form 2A (FY 2019-2020)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf29 Oct 2025
Form 2A (FY 2020-2021)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf29 Oct 2025
Form 2A (FY 2021-2022)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf29 Oct 2025
Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf29 Oct 2025
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf29 Oct 2025
Form 2A (FY 2024-2025)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf29 Oct 2025
Withdrawal Update Form 1File: FORM 1 Architect Certificate Apr to June-25.pdf27 Oct 2025
Withdrawal Update Form 2File: FORM 2 APR TO JUNE-25.pdf27 Oct 2025
Withdrawal Update Form 3File: Form-3.pdf27 Oct 2025
Form 1File: Certificates of Architect (Form 1) OCT TO DEC-22.pdf16 Oct 2025
Form 2File: Certificates of Engineer (Form 2) OCT TO DEC-22.pdf16 Oct 2025
Form 3File: FORM 3 OCT TO DEC-22 FINAL.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-OCT TO DEC-2022.pdf16 Oct 2025
Form 1File: Certificates of Architect (Form 1) JAN TO MARCH-25.pdf16 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JAN TO MARCH-25.pdf16 Oct 2025
Form 3File: FORM 3 JAN TO MAR-25 FINAL.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JAN TO MAR-2025.pdf16 Oct 2025
Form 1File: FORM 1-APR TO JUNE-22.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) APR TO JUN-22.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-APR TO JUN-2022.pdf13 Oct 2025
Form 3File: FORM 3 APR TO JUN-22 FINAL.pdf13 Oct 2025
Form 1File: FORM 1-JUL TO SEPT-22.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JUL TO SEP-22.pdf13 Oct 2025
Form 3File: FORM 3 JUL TO SEPT-22 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JUL TO SEPT-2022.pdf13 Oct 2025
Form 1File: Certificates of Architect (Form 1) JAN TO MAR-23.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JAN TO MAR-23.pdf13 Oct 2025
Form 3File: FORM 3 JAN TO MAR 23 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JAN TO MAR-2023.pdf13 Oct 2025
Form 1File: FORM 1-APR TO JUN-2023.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) APR TO JUNE-23.pdf13 Oct 2025
Form 3File: FORM 3 APR TO JUN-23 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-APR TO JUN-2023.pdf13 Oct 2025
Form 1File: FORM 1-JUL TO SEPT-2023.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JUL TO SEPT-23.pdf13 Oct 2025
Form 3File: FORM 3 JUL TO SEP-23 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JUL TO SEPT-2023.pdf13 Oct 2025
Form 1File: FORM 1-OCT TO DEC-2023.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) OCT TO DEC-23.pdf13 Oct 2025
Form 3File: FORM 3 OCT TO DEC-23 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-OCT TO DEC-2023.pdf13 Oct 2025
Form 1File: FORM 1-JAN TO MAR-2024.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JAN TO MARCH-24.pdf13 Oct 2025
Form 3File: FORM 3 JAN TO MAR-24 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JAN TO MAR-2024.pdf13 Oct 2025
Form 1File: Certificates of Architect (Form 1) APR TO JUNE-24.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) APR TO JUNE-24.pdf13 Oct 2025
Form 3File: FORM 3 APR TO JUN-24 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-APR TO JUN-2024.pdf13 Oct 2025
Form 1File: Certificates of Architect (Form 1) JUL TO SEPT-24.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JUL TO SEPT-24.pdf13 Oct 2025
Form 3File: FORM 3 JUL TO SEPT-24 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-JUL TO SEPT-2024.pdf13 Oct 2025
Form 1File: Certificates of Architect (Form 1) OCT TO DEC-24.pdf13 Oct 2025
Form 2File: Certificates of Engineer (Form 2) OCT TO DEC-24.pdf13 Oct 2025
Form 3File: FORM 3 OCT TO DEC-24 FINAL.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOUSER-OCT TO DEC-2024.pdf13 Oct 2025
Form 1File: 1 Certificates of Architect (Form 1) OCT TO DEC-17.pdf13 Oct 2025
Form 2File: 3 Certificates of Engineer (Form 2) OCT TO DEC-17.pdf13 Oct 2025
Form 3File: 4 Certificates of CA (Form 3) OCT TO DEC-17.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Oct-Dec- 2017.pdf13 Oct 2025
Form 1File: APR TO JUN-2020.pdf11 Oct 2025
Form 2File: Certificates of Engineer (Form 2) APR TO JUN-20.pdf11 Oct 2025
Form 3File: FORM 3 APR TO JUN-2020 FINAL.pdf11 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Apr to Jun-2020.pdf11 Oct 2025
Form 1File: JUL TO SEPT-2020.pdf11 Oct 2025
Form 2File: Certificates of Engineer (Form 2) JUL TO SEP-20..pdf11 Oct 2025
Form 3File: FORM 3 JUL TO SEPT-2020 FINAL.pdf11 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Jul to Sep-2020.pdf11 Oct 2025
Form 1File: OCT TO DEC-2020.pdf11 Oct 2025
Form 2File: Certificates of Engineer (Form 2) OCT TO DEC-20..pdf11 Oct 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SOLITAIRE STARSOLITAIRE STAR OM DATTA MANDIR MARG N L CROSS ROAD NEAR SOMVARI BAZAR MUMBAI 40006442CompletedJul 2012Jul 2012

How this compares with Mumbai Suburban

73%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 93 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOLITAIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Somwari Bazar6,700+ in Mumbai Suburban

2 kmSOLITAIRECompleted 139Lapsed / revoked 84Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 364 registered projects within 2 km.

Builder: SOLITAIRE CONSTRUCTIONS

SOLITAIRE CONSTRUCTIONS has 1 registration on MahaRERA, including SOLITAIRE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SOLITAIRE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOLITAIRE?

The registered promoter entity is SOLITAIRE CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOLITAIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SOLITAIRE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SOLITAIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOLITAIRE?

The professionals named in the filing: Architect: MS DADDY & ASSOCIATES; Engineer: JAYESH SHAH; Engineer: ALTAF A HINGORA; Engineer: SHAH STRUCTURALS PVT. LTD.; Chartered Accountant: HIMANSHU TREVADIYA; Chartered Accountant: JIGAR ZATAKIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOLITAIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOLITAIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOLITAIRE to a free account