Registered Litigation declared Commercial project

Solitaire Business Hub-III-Phase-III,Baner

By Baner Land Developers LLP

RG-MH-16046 · RERA P52100024890 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 22 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 125.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 97%
4 of 146Units unsoldnot recorded sold or booked
22Complaints at MahaRERAon this registration
Jump to the 263 documents Report an error

Solitaire Business Hub-III-Phase-III,Baner is a Commercial project by Baner Land Developers LLP in Pune, Maharashtra, registered with MahaRERA as P52100024890 on 9 Mar 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 142 of the 146 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 22 complaints are on record with the regulator.

At a glance

Project

  • NameSolitaire Business Hub-III-Phase-III,Baner
  • TypeCommercial
  • Location
    • Baner Road
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024890
  • ReraGenie IDRG-MH-16046

Builder

  • NameBaner Land Developers LLP
  • Entity typePartnership
  • PartnerAtul Ashok Chordia
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2020First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Mar 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2025)
  • Buildings1 building record
  • Documents filed263 files

Current status

97%142 of 146 units booked
100.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PH-1 Ground floor to 22nd floorNA26240146146

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 97%.

PH-1 Ground floor to 22nd floor: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks68%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes79%
Storm Water DrainsYes16%
Landscaping & Tree PlantingYes45%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed387

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots387
Closed/Covered387

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area18,145 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTATA CAPITAL HOUSING FINANCE LIMITED
Secured amountRs 125.00 crore
CERSAI search filedYes
Declared on9 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI42099.6
Proposed, not sanctioned10,118 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGulmohor park ITI Rd Ward No 8 Pushpak Park Aundh Pune Maharashtra 411007
Estimated costRs 59.61 cr
Cost incurredRs 59.61 cr
Work done100.0%
BuildingWingEstimatedIncurred
PH-1 Ground floor to 22nd floorNARs 53.56 crRs 53.56 cr
-NARs 6.04 crRs 6.04 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVenkataramanan Associates
ArchitectANA Consortium Pvt. ltd.
EngineerSTRUDCOM CONSULTANTS PVT. LTD.
EngineerKhandoba Bulbule
EngineerSwapnil Sonawane
EngineerAjaykumar Kusekar
Chartered AccountantSpak & Co
Chartered AccountantGMKS & Co
Chartered AccountantBogati & Co.
PartnerRole in project
Baner Land Developers LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11122518627Dec 2025 → Dec 2026

Reason as filed by the promoterAs per order of the Hon'ble Chairman (MahaRERA) Dated 23/01/2026 we request you kindly to grant us extension till 31/12/2026

Litigation declared2

CaseCourtStatus
980/2017PuneArgument on exh five plaintiff
980/2017171-Shri D.U. DongreOngoing

Complaints filed with MahaRERA22

Case no.ComplainantRespondentFiled
CC12600121Vishal MaluBaner Land Developers LLP08/01/2026
CC12600640Yogesh PatilBaner Land Developers LLP03/02/2026
CC12601404Suwidha MalviBaner Land Developers LLP14/03/2026
CC12601405Suwidha MalviBaner Land Developers LLP14/03/2026
CC12602203Kiran DhamdhereBaner Land Developers LLP15/04/2026
CC12602100Vijeta SinghBaner Land Developers LLP10/04/2026
CC12602430Vipin ShuklaBaner Land Developers LLP25/04/2026
CC12602490Kishor NirmalBaner Land Developers LLP28/04/2026
CC12602660Vijay DharneBaner Land Developers LLP08/05/2026
CC12602867Madhur ChaudhariBaner Land Developers LLP16/05/2026
CC12602870Rajesh WaghuldeBaner Land Developers LLP16/05/2026
CC12602886Nikhil Pramod KarampuriBaner Land Developers LLP16/05/2026
CC12603560Pushpak NavandarBaner Land Developers LLP09/06/2026
CC12603570Rajesh LambaBaner Land Developers LLP09/06/2026
CC12603794Harshali KankariyaBaner Land Developers LLP19/06/2026
CC12604395Trupti BangBaner Land Developers LLP14/07/2026
CC12604761S P SOFTWARE TECHNOLOGIES INDIA PRIVATE LIMITEDBaner Land Developers LLP28/07/2026
CC12605056Abhijit HerwadeBaner Land Developers LLP08/08/2026
CC12605146Praviin JaawalkarBaner Land Developers LLP12/08/2026
CC12605147Archana RathiBaner Land Developers LLP12/08/2026
CC12605151Pratibha GaikwadBaner Land Developers LLP12/08/2026
CC12605152Nilesh BargeBaner Land Developers LLP12/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed263

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 263 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - SBH Baner III-PH - III- Jun 26.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 - SBH Baner III - PH - III-Jun 26.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 - SBH Baner III - PH - III-Jun 26..pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A - SBH Baner III -PH - III - Mar 2026 Singed.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 - SBH Baner III -PH - III - Mar 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - SBH Baner III -PH - III - Mar 2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3_SBH 3 Ph 3_Mar-26.pdf20 Apr 2026
Form 1File: Form-1 - SBH Baner III PH III - Mar 24.pdf30 Jan 2026
Form 2File: Form-2- SBH Baner III PH III - Mar 24.pdf30 Jan 2026
Form 3File: Form-3 - SBH Baner III PH III - Mar 24.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III Ph III Mar 24-.pdf30 Jan 2026
Form 1File: Form 1 - SBH Baner III - PH III - Jun 24.pdf30 Jan 2026
Form 2File: Form 2- SBH Baner III - PH III - Jun 24.pdf30 Jan 2026
Form 3File: Form 3 - SBH Baner III - PH III - Jun 24.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure-SBH Baner 3 -Phase III June 24 .pdf30 Jan 2026
Form 1File: Form 1- SBH Baner III - PH - III - Sept 24.pdf30 Jan 2026
Form 2File: FORM 2-SBH-Baner III -Phase III- Sept 24.pdf30 Jan 2026
Form 3File: Form 3- SBH Baner III - PH - III - Sept 24.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure SBH 3 Phase 3-Sept 24.pdf30 Jan 2026
Form 1File: Form 1 - SBH Baner III PH - III - Dec 24.pdf30 Jan 2026
Form 2File: Form 2 - SBH Baner III PH - III - Dec 24.pdf30 Jan 2026
Form 3File: Form 3 - SBH Baner III PH - III - Dec 24.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - Baner III - PH - III - Dec 24.pdf30 Jan 2026
Form 1File: Form 1- SBH Baner III-PH-III _ Mar 2025.pdf30 Jan 2026
Form 2File: Form 2- SBH Baner III-PH-III _ Mar 2025.pdf30 Jan 2026
Form 3File: Form 3- SBH Baner III-PH-III _ Mar 2025.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III - PH III - Mar 25.pdf30 Jan 2026
Form 1File: Form -1 - SBH Baner III - Phase III - Dec 21.pdf29 Jan 2026
Form 2File: Form -2 - SBH Baner III - Phase III - Dec 21.pdf29 Jan 2026
Form 3File: Form -3 - SBH Baner III - Phase III - Dec 21.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH III -Dec 21.pdf29 Jan 2026
Form 1File: Form 1-SBH Baner III-Phase III March-22.pdf29 Jan 2026
Form 2File: Form 2-SBH Baner III-Phase III March-22.pdf29 Jan 2026
Form 3File: Form 3-SBH Baner III-Phase III March-22.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III-PH - III Mar 22.pdf29 Jan 2026
Form 1File: Form -1 - SBH Baner III -Phase III Jun-22.pdf29 Jan 2026
Form 2File: Form -2 - SBH Baner III -Phase III Jun-22.pdf29 Jan 2026
Form 3File: Form -3 - SBH Baner III -Phase III Jun-22.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III - PH - III - Jun 2022.pdf29 Jan 2026
Form 1File: Form 1 - SBH Baner III-Phase III- Sept-22 .pdf29 Jan 2026
Form 2File: Form 2 - SBH Baner III-Phase III- Sept-22 .pdf29 Jan 2026
Form 3File: Form 3 - SBH Baner III-Phase III- Sept-22 .pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III- PH - III- Sept 22.pdf29 Jan 2026
Form 1File: Form 1- SBH Baner III-Phase III- Dec-22.pdf29 Jan 2026
Form 2File: Form 2- SBH Baner III-Phase III- Dec-22.pdf29 Jan 2026
Form 3File: Form 3- SBH Baner III-Phase III- Dec-22.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III - PH -III - Dec 22.pdf29 Jan 2026
Form 1File: Form -1 - SBH Baner III -Phase III- Mar-23.pdf29 Jan 2026
Form 2File: Form -2 - SBH Baner III -Phase III- Mar-23.pdf29 Jan 2026
Form 3File: Form -3 - SBH Baner III -Phase III- Mar-23.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III- PH - III- Mar 23.pdf29 Jan 2026
Form 1File: Form 1- SBH Baner III Phase III- Jun 23.pdf29 Jan 2026
Form 2File: Form 2- SBH Baner III Phase III- Jun 23.pdf29 Jan 2026
Form 3File: Form 3- SBH Baner III Phase III- Jun 23.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III - PH III - Jun 23.pdf29 Jan 2026
Form 1File: Form 1 SBH Bane III PH III Sept 23.pdf29 Jan 2026
Form 2File: Form 2 SBH Baner III PH III Sept 23.pdf29 Jan 2026
Form 3File: Form 3 SBH Bane III PH III- Sept 23.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure - SBH Baner III PH III - Sept 23 - .pdf29 Jan 2026
Form 1File: Form 1- SBH Baner III - Ph - III - Dec 23.pdf29 Jan 2026
Form 2File: Form 2- SBH Baner III - Ph - III - Dec 23.pdf29 Jan 2026
Form 3File: Form 3- SBH Baner III - Ph - III - Dec 23.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH-III Dec 23 .pdf29 Jan 2026
Form 1File: Form 1 - SBH Baner-III-PH-III- Mar 20.pdf28 Jan 2026
Form 2File: Form 2 - SBH Baner-III-PH-III- Mar 20.pdf28 Jan 2026
Form 3File: Form 3 - SBH Baner-III-PH-III- Mar 20.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH III - Mar 20.pdf28 Jan 2026
Form 1File: Form 1 - SBH Baner III-PHASE III- Jun 20 .pdf28 Jan 2026
Form 2File: Form 2 - SBH Baner III-PHASE III- Jun 20 .pdf28 Jan 2026
Form 3File: Form 3 - SBH Baner III-PHASE III- Jun 20 .pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH III - Jun 20.pdf28 Jan 2026
Form 1File: Form 1 - SBH Baner III-Phase III_Sept 20.pdf28 Jan 2026
Form 2File: Form 2 - SBH Baner III-Phase III_Sept 20.pdf28 Jan 2026
Form 3File: Form 3 - SBH Baner III-Phase III_Sept 20.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH III - Sept 20.pdf28 Jan 2026
Form 1File: Form 1 - SBH Baner III-PH -III- Dec 2020.pdf28 Jan 2026
Form 2File: Form 2 - SBH Baner III-PH -III- Dec 2020.pdf28 Jan 2026
Form 3File: Form 3 - SBH Baner III-PH -III- Dec 2020.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Disclosure -SBH Baner III PH III - Dec 20.pdf28 Jan 2026
Form 1File: Form 1- SBH Baner III- PH III- Mar 21.pdf28 Jan 2026

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Solitaire Business Hub-III-Phase-III,Baner on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner13,700+ in Pune

2 kmSolitaire Business Hub-ICompleted 145Lapsed / revoked 54Other 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 359 registered projects within 2 km.

Builder: Baner Land Developers LLP

Baner Land Developers LLP has 3 registrations on MahaRERA, including Solitaire Business Hub -III, Phase- I, Baner and Solitaire Business Hub-III-Phase-III,Baner. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Solitaire Business Hub-III-Phase-III,Baner is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Solitaire Business Hub-III-Phase-III,Baner?

The registered promoter entity is Baner Land Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Solitaire Business Hub-III-Phase-III,Baner?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Solitaire Business Hub-III-Phase-III,Baner?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Solitaire Business Hub-III-Phase-III,Baner?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Solitaire Business Hub-III-Phase-III,Baner?

The professionals named in the filing: Architect: Venkataramanan Associates; Architect: ANA Consortium Pvt. ltd.; Engineer: STRUDCOM CONSULTANTS PVT. LTD.; Engineer: Khandoba Bulbule; Engineer: Swapnil Sonawane; Engineer: Ajaykumar Kusekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Solitaire Business Hub-III-Phase-III,Baner?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Solitaire Business Hub-III-Phase-III,Baner. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Solitaire Business Hub-III-Phase-III,Baner to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.