ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Solitaire Business Hub Baner

Registered No litigation declared Commercial project

Solitaire Business Hub Baner

By Atul Builders

RG-MH-23932 · RERA P52100008740 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • 21 complaints at MahaRERA
  • Completion date moved by 41 months
  • 4 extensions taken
  • Rs 50.00 crore secured on the land, in favour of Aditya Birla Finance Ltd

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 41 months from the original
36 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
29 of 269Units unsoldnot recorded sold or booked
21Complaints at MahaRERAon this registration
Jump to the 239 documents Report an error

Solitaire Business Hub Baner is a Commercial project by Atul Builders in Pune, Maharashtra, registered with MahaRERA as P52100008740 on 19 Aug 2017. Possession is promised by 6 Nov 2026. The completion date has moved by 41 months from the original filing. 240 of the 269 units on this registration are recorded sold or booked, and 36 of 44 construction stages are filed complete. 21 complaints are on record with the regulator.

At a glance

Project

  • NameSolitaire Business Hub Baner
  • TypeCommercial
  • Location
    • Mumbai Banglore Highway
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100008740
  • ReraGenie IDRG-MH-23932

Builder

  • NameAtul Builders
  • Entity typePartnership
  • PartnerAshok Dhanraj Chordia
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2023Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion6 Nov 2026
  • Revised completionRevised to 6 Nov 2026 (originally 30 Jun 2023)
  • Buildings4 building records
  • Documents filed239 files

Current status

89%240 of 269 units booked
102.1%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1 - Ground to Third FloorNA9007070
Building 3 Sixth to Eighth FloorNA3306767
Building 2 - Fourth to Fifth FloorNA2204444
Building 4 - 9th Floor to 12th FloorNA4308888

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

Building 1 - Ground to Third Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 3 Sixth to Eighth Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 2 - Fourth to Fifth Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building 4 - 9th Floor to 12th Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1580

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,580
Closed/Covered1,580

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area18,205 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Ltd
Secured amountRs 50.00 crore
Declared on10 Jun 2025
LandownerVillageDistrict
M/s Creative LandmarksPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI30224.0
Proposed, not sanctioned30,224 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor,Laukik Apartment Bhandarkar Road, Pune- 411014
Estimated costRs 143.30 cr
Cost incurredRs 146.31 cr
Work done102.1%
BuildingWingEstimatedIncurred
Building 1 - Ground to Third FloorNARs 55.96 crRs 57.26 cr
Building 4 - 9th Floor to 12th FloorNARs 33.11 crRs 33.88 cr
Building 3 Sixth to Eighth FloorNARs 24.93 crRs 25.51 cr
Building 2 - Fourth to Fifth FloorNARs 16.47 crRs 16.85 cr
-NARs 12.82 crRs 12.82 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudioSA
ArchitectANA Consortium Pvt. Ltd.
ArchitectVenkataramanan Associates
EngineerG A Bhilare Consultants Private Limited
EngineerSwapnil Sonawane
Chartered AccountantBogati & Company
Chartered AccountantGMKS & Co.
Chartered AccountantRSVA & Co
Chartered AccountantSPAK & Co
PartnerRole in project
Atul Builders-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100016644Jun 2023 → Jun 2024

Reason as filed by the promoterdue to the covid 19 pandemic, we were not able to construct anymore because of lack of labour contractors and the poor market conditions we were unable to complete the project within the due time.

EXT52100022949Jun 2023 → Jun 2025

Reason as filed by the promoterThe construction and development of the said Project started as per the timelines under RERA. However, the project got delayed due to the effect of Covid-19 pandemic, wherein the Government declared nationwide lockdown entire nation suffered a global pandemic i.e., Covid-19 pandemic and various circular orders were passed due to which the construction and development of the said Project stalled, we faced several challenges that adversely affected the construction activities and the project got delayed due to major challenges i.e., disruption of supply chains for procuring construction material

EA13062501583Jun 2023 → Dec 2025

Reason as filed by the promoterWe, Atul Builders, are developing a commercial project under the name and style “Solitaire Business Hub Baner,” which is registered under the Real Estate (Regulations and Development) Act, 2016 (“RERA”), bearing Project Registration Number P52100008740. We had applied for a RERA extension on 7th June 2024 via Application No. EXT52100022949 for one year under Section 7(3), as per Order 40/2022 & 40A/2023. During the extension hearing, we requested Hon’ble Chairperson Shri Manoj Saunik to grant an extension of one and a half years. Our request was approved, and as per the Rozanama dated 10th Dec

EA30062621635Jun 2023 → Nov 2026

Reason as filed by the promoterWe hereby apply for extension of registration of the following project “Solitaire Business Hub Baner”, registered with the regulatory authority vide project registration certificate bearing No. P52100008740, which is expired on 31/12/2025. We respectfully submit that the project has already received the Full Occupation Certificate on 12/12/2025 bearing OC No. OCC/0978/25, and the same was submitted to MahaRERA through a Completion Application. However, during scrutiny, certain observations were raised regarding mismatch of the Built-up Area (BUA) and building details with the Occupation Certif

Complaints filed with MahaRERA21

Case no.ComplainantRespondentFiled
CC005000000167626Shyam Manohar JuriasinghaniAtul Builders29/12/2022
CC005000000064676Smaran Choudhuryatul builders and ronisun realty28/09/2020
CC005000000259290DHANANJAY TUKARAM KATEAtul Builders24/08/2023
CC005000000279787Snehlata JainAtul Builders02/01/2024
CC005000000279791Vaibhav GuptaAtul Builders29/11/2023
CC005000000290109Sagar KapileAtul Builders18/01/2024
CC005000000370924FUSION SPACES LLPAtul Builders24/05/2024
CC12400129Sachin DhorageAtul Builders17/09/2024
CC12400380Vishwajit PatilAtul Builders09/10/2024
CC12400556MAHENDRA MADHODAS MUNDADAATUL BUILDERS24/10/2024
CC12500375SWATI KAILASH KAKDE SWATI KAKDECREATIVE LANDMARKS04/02/2025
CC12501593Subrahmanyam KavuriAtul Builders14/05/2025
CC12501624ATUL AUGUSTINE GOVANDEAtul Builders19/05/2025
CC12502802Ajinkya Anant KhaiwaleAtul Builders09/08/2025
CC12504025Rahul GargAtul Builders15/11/2025
CC12504029Sudha BhatiAtul Builders15/11/2025
CC12504030Sudha BhatiAtul Builders15/11/2025
CC12601338Revanth KazaAtul Builders11/03/2026
CC12601314CHITRA NILESH TAMBEAtul Builders10/03/2026
CC12603619Sunita DixitAtul Builders12/06/2026
CC12605383Sachin DhorageAtul Builders22/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Aug 2024

Documents filed239

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 239 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - SBH Baner I_Mar 26 Signed.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 - SBH Baner I_Mar 26 Signed.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 - SBH Baner I - Jun 26.pdf19 Aug 2026
Withdrawal Update Form 2File: Form 2- SBH Baner I_Mar 26.pdf19 Aug 2026
Withdrawal Update Form 2File: Form 2- SBH Baner I_Mar 26.pdf19 Aug 2026
Withdrawal Update Form 2File: Form 2 - SBH Baner - Jun 26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form-3_SBH Baner_Mar26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form-3_SBH Baner_Mar26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 - SBH Baner - Jun 26.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A- SBH Baner I_Mar 26.pdf8 Jun 2026
Withdrawal Update Form 1File: Form 1- SBH Baner - Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2- SBH Baner - Dec 2025 .pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - SBH Baner - Dec 2025.pdf20 Jan 2026
Layout approvalFile: Layout.pdf31 Dec 2025
Building plan approvalFile: Scan_3843-02.pdf31 Dec 2025
Building plan approvalFile: Building Plan-03.pdf31 Dec 2025
Building plan approvalFile: Building Plan-04.pdf31 Dec 2025
Building plan approvalFile: Building Plan -05.pdf31 Dec 2025
Building plan approvalFile: Building Plan -06.pdf31 Dec 2025
Building plan approvalFile: Building Plan-07.pdf31 Dec 2025
Building plan approvalFile: Building Plan-08.pdf31 Dec 2025
Building plan approvalFile: Building Plan-09.pdf31 Dec 2025
Building plan approvalFile: Building Plan-10.pdf31 Dec 2025
Building plan approvalFile: Building Plan-11.pdf31 Dec 2025
Withdrawal Update Form 1File: Form 1- SBH Baner I - Sept 2025.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2- SBH Baner I - Sept 2025.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3- SBH Baner I - Sept 2025.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: SBH Baner-Form 5-FY 24-25.pdf18 Sep 2025
Withdrawal Update Form 1File: Form 1 - SBH Baner Jun 25.pdf30 Jul 2025
Withdrawal Update Form 2File: Form 2 - SBH Baner Jun 25.pdf30 Jul 2025
Withdrawal Update Form 3File: Form 3 - SBH Baner Jun 25_compressed.pdf30 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- SBH Baner_ Mar 2025.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 - SBH Baner - Mar 25.pdf26 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - SBH Baner - Mar 25.pdf26 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Disclosure - SBH Baner I - Mar 25.pdf26 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - SBH Baner - Mar 25.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 - SBH Baner - Dec 24.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - SBH Baner - Dec 24.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Disclosure - SBH Baner- Dec 24.pdf20 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - SBH Baner - Dec 24.pdf18 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SBH Baner - FY 23-24 - Form 5.pdf13 Dec 2024
Certificates of CA (Form 3)File: Form 3 - SBH Baner - Sept 2024.pdf10 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - SBH Baner - Sept 2024.pdf10 Dec 2024
Certificates of CA (Form 3)File: SBH BANER MAY 2020.pdf26 Nov 2024
Certificates of CA (Form 3)File: SBH BANER SEPT 2021.pdf26 Nov 2024
Certificates of CA (Form 3)File: SBH BANER JUNE 2021.pdf26 Nov 2024
Certificates of CA (Form 3)File: 7Form 3 SBH Baner Jan 19.pdf14 Nov 2024
Certificates of CA (Form 3)File: 6Form 3 SBH Baner Oct 18.pdf14 Nov 2024
Certificates of CA (Form 3)File: 5Form 3 SBH Baner Aug 18.pdf14 Nov 2024
Certificates of CA (Form 3)File: 4Form 3SBH Baner May 18.pdf14 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - SBH Baner - Sept 2024.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Discloure - SBH Baner - Sept 2024.pdf19 Oct 2024
Certificates of CA (Form 3)File: Form 3 - SBH Baner - May 19.pdf8 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 Nov 2017.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 Feb 2018.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2 may 2018.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2 Aug 2018.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2 Oct 2018.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Form 2 Jan 2019.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Form 2 May 2019.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 Form 2 Aug 2019.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Form 2 Nov 2019.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Form 2 Feb 2020.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Form 2 May 2020.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 Form 2 Aug 2020.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 Form 2 Nov 2020.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15 Form 2 Feb 2021.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 Form 2 Jun 2021.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 17 Form 2 Sep 2021.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18 Form 2 Dec 2021.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19 Form 2 March 2022.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20 Form 2 Jun 2022.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 21 Form 2 Sep 2022.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 22 Form 2 Dec 2022.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 23 Form 2 March 2023.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 24 Form 2 Jun 2023.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 25 Form 2 Sep 2023.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 Form 2 Dec 2023.pdf9 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 28 FORM 2 -Engineer certificate-SBH 1 Jun 24.pdf9 Aug 2024
Certificates of CA (Form 3)File: 2 Form 3 SBH Baner Nov-17.pdf9 Aug 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AVALON CITY C-3P52100003105Pune, Pune47Aug 2017CompletedDec 2021Registered original: Dec 2019Feb 2020

How this compares with Pune

89%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 41 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Solitaire Business Hub Baner on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Baner13,700+ in Pune

2 kmSolitaire Business Hub BCompleted 183Lapsed / revoked 65Other 147Dot size: filed unitsN

Filed coordinates, straight-line distance. 395 registered projects within 2 km.

Builder: Atul Builders

Atul Builders has 3 registrations on MahaRERA, including Solitaire Nine and SOLITAIRE SEVEN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Solitaire Business Hub Baner is delayed beyond 6 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Solitaire Business Hub Baner?

The registered promoter entity is Atul Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Solitaire Business Hub Baner?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Solitaire Business Hub Baner?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Solitaire Business Hub Baner?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Solitaire Business Hub Baner?

The professionals named in the filing: Architect: StudioSA; Architect: ANA Consortium Pvt. Ltd.; Architect: Venkataramanan Associates; Engineer: G A Bhilare Consultants Private Limited; Engineer: Swapnil Sonawane; Chartered Accountant: Bogati & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Solitaire Business Hub Baner?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Solitaire Business Hub Baner. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Solitaire Business Hub Baner to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.