Home / Browse projects / Palghar, Maharashtra / SMRITI HEIGHTS

Registration lapsed No litigation declared Others project

SMRITI HEIGHTS

By SMRITI DEVELOPER

RG-MH-70367 · RERA P99000006440 · Last updated on MahaRERA portal: 29 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

SMRITI HEIGHTS is a Others project by SMRITI DEVELOPER in Palghar, Maharashtra, registered with MahaRERA as P99000006440 on 14 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameSMRITI HEIGHTS
  • TypeOthers
  • Location
    • MANVEL PADA ROAD
    • VIRAR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401305
  • Pincode401305
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000006440
  • ReraGenie IDRG-MH-70367

Builder

  • NameSMRITI DEVELOPER
  • Entity typePartnership
  • PartnersANANDKUMAR SINGH, RAKESH KUMAR YADAV, PRAMOD CHATURVEDI, SANJAY CHATURVEDI

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SMRITI HEIGHTS BUILDING NO 1NA1414000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

SMRITI HEIGHTS BUILDING NO 1: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 29 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes10%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,815 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityVasai-Virar City Municipal Corporation
Permissible FSI4464.29
Proposed, not sanctioned4,464 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIKHIL HERITAGE, NALLASOPARA EAST

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJAY WADE
EngineerMUKESH KUMAR
Chartered AccountantHARESH MEHTA & ASSOCIATES
Chartered AccountantSTR AND ASSOCIATES
PartnerRole in project
SMRITI DEVELOPER-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000018394Dec 2023 → Dec 2024

Reason as filed by the promoterDear Sir, With reference to cited subject, I the undersigned Partner of M/s SMRITI DEVELOPER carrying on Project: SMRITI HEIGHTS situated At Survey No. 82, Hissa No. 2,3, & 6(Pt), Survey No. 83, Hissa No. 4,5,6,& 7,At Vasai Virar City(M Corp), Vasai, Dist.: Palghar, Pin: 401305 would like to inform you that our Maharera Project due date is about to expire on 30-12-2023, Due to market slow down and slow collection from unit allottees we could not complete the entire project within the stipulated timeline of 30-12-2023 as per Maharera Registration Certificate. Thus, our honour, in the larger int

EXT99000028175Dec 2023 → Dec 2025

Reason as filed by the promoterRespected Sir/Madam, This is to submit that the project Smriti Heights, registered under MahaRERA No. P99000006440, has been 100% completed as per the architect’s letter dated 24-12-2024(Attached herewith) and we have applied for the Occupancy Certificate (O.C.) to the competent authority In view of the above, and to ensure full statutory compliance, implementation of final safety measures, and readiness for formal occupancy, we kindly request the Hon’ble MahaRERA Authority to grant an extension of one year, i.e., up to 31-12-2025. Thanking You,

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FORM 5_FY 24-25.pdf29 Oct 2025
Certificates of CA (Form 3)File: FORM 3_SH_DEC 2023-SIGNED.pdf12 Apr 2025
Certificates of CA (Form 3)File: FORM 3_SH_MAR 2024-SIGNED.pdf12 Apr 2025
Certificates of CA (Form 3)File: FORM 3_SH_JUNE 2024-SIGNED.pdf12 Apr 2025
Certificates of CA (Form 3)File: FORM3_SH_SEP 2024-SIGNED.pdf12 Apr 2025
Certificates of CA (Form 3)File: FORM3_SH_DEC 2024-SIGNED.pdf12 Apr 2025
Certificates of CA (Form 3)File: FORM 3_SH_MAR 2025-SIGNED.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD AS ON 31 03 2025.pdf12 Apr 2025
Other - TechnicalFile: FORM 2A 2025.pdf12 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2024.pdf12 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2025.pdf12 Apr 2025
Declaration in FORM BFile: 5 AFFIDAVIT FORM B.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 SELF DECLARATION FOR NO QPR WITH COMPLETION LETTER.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SIGNED_MAR 25.pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_MAR25 SIGNED.pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 SELF DECLARATION FOR NO QPR WITH COMPLETION LETTER.pdf11 Apr 2025
Other - FinanceFile: 4 JUSTIFICATION WITH COMPLETION LETTER.pdf11 Apr 2025
Other - FinanceFile: 3 PERT CPM_STATUS OF WORK.pdf11 Apr 2025
Other - FinanceFile: ARCHITECT COMPLETION LETTER_SMRITI DEVELOPERS.pdf11 Apr 2025
Other - TechnicalFile: ARCHITECT COMPLETION LETTER_SMRITI DEVELOPERS.pdf11 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Report On Statement Of Account_FORM-5.pdf11 Apr 2025
Layout approvalFile: PLAN-REVISED_1.pdf10 Feb 2024
Layout approvalFile: PLAN-REVISED_2.pdf10 Feb 2024
Layout approvalFile: PLAN-REVISED_3.pdf10 Feb 2024
Layout approvalFile: PLAN-REVISED_4.pdf10 Feb 2024
Layout approvalFile: PLAN-REVISED_5.pdf10 Feb 2024
Building plan approvalFile: PLAN-REVISED_1.pdf10 Feb 2024
Building plan approvalFile: PLAN-REVISED_2.pdf10 Feb 2024
Building plan approvalFile: PLAN-REVISED_3.pdf10 Feb 2024
Building plan approvalFile: PLAN-REVISED_4.pdf10 Feb 2024
Building plan approvalFile: PLAN-REVISED_5.pdf10 Feb 2024
Copy of Layout Approval (in case of layout)File: PLAN-REVISED_1.pdf10 Feb 2024
Copy of Layout Approval (in case of layout)File: PLAN-REVISED_2.pdf10 Feb 2024
Copy of Layout Approval (in case of layout)File: PLAN-REVISED_3.pdf10 Feb 2024
Copy of Layout Approval (in case of layout)File: PLAN-REVISED_4.pdf10 Feb 2024
Copy of Layout Approval (in case of layout)File: PLAN-REVISED_5.pdf10 Feb 2024
Building Plan Approval (IOD)File: PLAN-REVISED_1.pdf10 Feb 2024
Building Plan Approval (IOD)File: PLAN-REVISED_2.pdf10 Feb 2024
Building Plan Approval (IOD)File: PLAN-REVISED_3.pdf10 Feb 2024
Building Plan Approval (IOD)File: PLAN-REVISED_4.pdf10 Feb 2024
Building Plan Approval (IOD)File: PLAN-REVISED_5.pdf10 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD HL 31 12 2023.pdf7 Feb 2024
Certificates of CA (Form 3)File: FORM 3 SIGNED UPTO 31 03 23-SMRITI DEV.pdf7 Feb 2024
Certificates of CA (Form 3)File: FORM 3 SIGNED (APR TO JUNE 23)-SMRITI.pdf7 Feb 2024
Certificates of CA (Form 3)File: FORM 3 SIGNED (JUL TO SEP 23)-SMRITI.pdf7 Feb 2024
CERSAI detailsFile: CERSAI DECLARATION WITH REPORT.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEX A- PRAMOD CHAT.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEX A -ANAND SINGH.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEX A - SANJAY C.pdf31 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEX A - RAMESHKUMAR Y.pdf31 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION -ANNEX A.pdf31 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ARCHITECT CERT SIGNED DEC 23.pdf9 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTIFICATE SIGNED DEC 23 SIGNED.pdf9 Jan 2024
Declaration in FORM BFile: FORM B REVISED.pdf2 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 2020.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A - 2021.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A - 2022.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A - 2023.pdf2 Jan 2024
Disclosure of sold/ booked inventoryFile: sold unsold flat details revised.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2023 SIGNED.pdf24 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 SMRITI DEVELOPERS_opt.pdf25 Mar 2023
Other - LegalFile: DEVELOPMENT AGREEMENT REVISED_1.pdf20 Jan 2023
Other - LegalFile: DEVELOPMENT AGREEMENT REVISED_2_opt.pdf20 Jan 2023
Other - LegalFile: DEVELOPMENT AGREEMENT REVISED_3.pdf20 Jan 2023
Other - LegalFile: DEVELOPMENT AGREEMENT REVISED_4.pdf20 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021_opt.pdf25 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 SIGNED.pdf18 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 SMRITI DEV 2019.PDF30 Nov 2019
Certificates of CA (Form 5)File: RERA FORM-5-SMRITI DEV.pdf29 Sep 2018
Building plan approvalFile: smruti cc.pdf31 Jul 2017
Layout approvalFile: LAYOUT PLAN (1).pdf31 Jul 2017
PAN CardFile: Smriti Developer - Pan card.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE (1).pdf31 Jul 2017
Details of encumbrancesFile: smruti developers LETTER.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN (1).pdf31 Jul 2017
Building Plan Approval (IOD)File: smruti cc.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: smruti cc.pdf31 Jul 2017
Declaration in FORM BFile: FORM B.pdf31 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SMRITI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIRAR3,200+ in Palghar

2 kmSMRITI HEIGHTSCompleted 78Lapsed / revoked 46Other 81Dot size: filed unitsN

Filed coordinates, straight-line distance. 205 registered projects within 2 km.

Builder: SMRITI DEVELOPER

SMRITI DEVELOPER has 1 registration on MahaRERA, including SMRITI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that SMRITI HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SMRITI HEIGHTS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SMRITI HEIGHTS?

The registered promoter entity is SMRITI DEVELOPER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SMRITI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SMRITI HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SMRITI HEIGHTS?

The professionals named in the filing: Architect: AJAY WADE; Engineer: MUKESH KUMAR; Chartered Accountant: HARESH MEHTA & ASSOCIATES; Chartered Accountant: STR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SMRITI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SMRITI HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SMRITI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.