SKYWARDS REGENCY
RG-MH-93857 · RERA P51700014068 · Last updated on MahaRERA portal: 28 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 66 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SKYWARDS REGENCY is a Residential / Group Housing project by SKYWARDS VISION DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700014068 on 7 Nov 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 66 months from the original filing. 8 complaints are on record with the regulator.
At a glance
Project
- NameSKYWARDS REGENCY
- TypeResidential / Group Housing
- Location
- Mira-Bhayandar (M Corp.)
- Thane
- 401104
- Pincode401104
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700014068
- ReraGenie IDRG-MH-93857
Builder
- NameSKYWARDS VISION DEVELOPERS
- Entity typePartnership
- PartnersKALPESH AMRUTLAL RAJPARA, KALPANA PANDHARINATH PATIL, PANDHARINATH SITARAM PATIL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Nov 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2020)
- Buildings2 building records
- Documents filed71 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SKYWARDS REGENCY A WING | NA | 38 | 0 | 0 | 0 | 0 |
| SKYWARDS REGENCY B WING | NA | 50 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 28 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 60%.
SKYWARDS REGENCY A WING51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SKYWARDS REGENCY B WING38%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed59
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SKYWARDS REGENCY A WING | 23 | 23 |
| SKYWARDS REGENCY B WING | 36 | 36 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ULHAS GOPINATH PRADHAN |
| Partner | Role in project |
|---|---|
| SKYWARDS VISION DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSurvey No 119 Hissa No 1 Part Bifurcation for TRL application is under process
Reason as filed by the promoterThe completion date for the said project was 30/06/2020. But due to the pandemic which is commenced by March 2020, we were unable to complete the project and yet even after the lockdown has been at eased there are difficulties to cope with the labours and the material frequency. The project is completed upto 10th floor and maximum interior work has also been completed. We say that the project is 80% completed from our end. We have sold only upto 30% of the project including the shops and the flats. We request you to grant us an extension upto 31st December, 2021. We have full faith we will com
Reason as filed by the promoterTHE BUILDING IS PARTLY COMPLETED ONLY THE UPPER FLOORS ARE PENDING.
Reason as filed by the promoterThe project is delayed due to pending approvals from Concerned Authorities
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000171598 | Phalcomm Infra Solutions Pvt Ltd | Skywards Vision Developers. | 19/11/2019 |
| CC006000000196405 | JAAN MOHAMMED | Kalpesh a rajpara | 29/04/2021 |
| CC006000000302958 | Yogesh Pandurang Rane | Kalpesh.A.Rajpara | 07/10/2022 |
| CC006000000429405 | Priyanka Pandit Khare | Skywards Vision Developer | 24/02/2024 |
| CC006000000429426 | Rohan Savlaram Kawle | Skywards Vision Developer | 27/02/2024 |
| CC006000000429389 | Rashmi Omprakash Vishwakarma | Skywards Vision Developer | 24/02/2024 |
| CC006000000429403 | Vinod Kateshwar Nayak | Skywards Vision Developer | 24/02/2024 |
| CC006000000429430 | ABDUL KADIR KHAN | Skywards Vision Developer | 27/02/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Nov 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Nov 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed71
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 architect certificate (1).pdf | 28 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Doc_6738.pdf | 28 Mar 2025 |
| Certificates of CA (Form 3)File: Skywards Form 3 .pdf | 21 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A 19-20.pdf | 21 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A 22-23.pdf | 21 Mar 2025 |
| Declaration in FORM BFile: Form B Declaration.pdf | 20 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate A B dated 03-01-2025.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate A B dated 29-06-2024.pdf | 20 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate A B dated 30-09-2024.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A engineer certificate for quality assurance.pdf | 20 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: engineer certificate A B dated 29-06-2024.pdf | 20 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 29-06-2024.pdf | 12 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30-09-2024.pdf | 12 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 03-01-25.pdf | 12 Mar 2025 |
| Certificates of CA (Form 3)File: form 3 year 23-24.pdf | 12 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory.pdf | 12 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 14 Jan 2025 |
| Certificates of CA (Form 5)File: CA Form D.pdf | 14 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22-23 architect certificate.pdf | 4 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 23-24 architect certificate.pdf | 4 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form-2 (A).pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form-2 (B).pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form-2 (A).pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form-2(B).pdf | 3 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 year 22-23.pdf | 3 Jun 2024 |
| Certificates of CA (Form 5)File: form 5 year 22-23.pdf | 3 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 year 22-23.pdf | 3 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CamScan_05-04-2023_23-24-14_compressed.pdf | 6 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ilovepdf_merged_compressed.pdf | 5 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CamScan_05-04-2023_15-30-20-compressed.pdf | 5 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CamScan_29-03-2023_16-08-01.pdf | 29 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: CamScan_29-03-2023_17-06-12_compressed.pdf | 29 Mar 2023 |
| Certificates of CA (Form 3)File: 19-20 FORM-3 (1)_compressed.pdf | 29 Mar 2023 |
| Certificates of CA (Form 3)File: 20-21 FORM-3 (1)_compressed.pdf | 29 Mar 2023 |
| Certificates of CA (Form 3)File: Skywards Form 3_compressed.pdf | 29 Mar 2023 |
| Certificates of CA (Form 5)File: Skywards Form 5.pdf | 29 Mar 2023 |
| Certificates of CA (Form 5)File: 19-20 FORM-5.pdf | 29 Mar 2023 |
| Certificates of CA (Form 5)File: Skywards Form 5 (1).pdf | 29 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf | 28 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A_compressed.pdf | 2 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf | 2 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf | 2 Sep 2022 |
| CERSAI detailsFile: Cersai Declaration_compressed.pdf | 29 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20 FORM-5_compressed.pdf | 29 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21 FORM - 5_compressed.pdf | 29 Aug 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT CC.pdf | 25 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Rera.pdf | 24 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: comencement certificate issue by authority.pdf | 22 Jul 2019 |
| Certificates of CA (Form 5)File: C A CERTIFICATE FORM NO 5.pdf | 22 Jul 2019 |
| Building plan approvalFile: elevation plan.pdf | 3 Nov 2017 |
| Building plan approvalFile: Location, Floor, Site Plan by aproved authority.pdf | 3 Nov 2017 |
| Layout approvalFile: elevation plan.pdf | 3 Nov 2017 |
| Layout approvalFile: Location, Floor, Site Plan by aproved authority.pdf | 3 Nov 2017 |
| Layout approvalFile: location site plan.pdf | 3 Nov 2017 |
| Copy of Layout Approval (in case of layout)File: elevation plan.pdf | 3 Nov 2017 |
| Copy of Layout Approval (in case of layout)File: Location, Floor, Site Plan by aproved authority.pdf | 3 Nov 2017 |
| Copy of Layout Approval (in case of layout)File: location site plan.pdf | 3 Nov 2017 |
| Building Plan Approval (IOD)File: elevation plan.pdf | 3 Nov 2017 |
| Building Plan Approval (IOD)File: Location, Floor, Site Plan by aproved authority.pdf | 3 Nov 2017 |
| Declaration in FORM BFile: Form B - notarised.pdf | 3 Nov 2017 |
| PAN CardFile: PAN CARD OF FIRM AND PARTNERS.pdf | 8 Oct 2017 |
| Copy of the legal title reportFile: title report advocate 1 - 3.pdf | 8 Oct 2017 |
| Copy of the legal title reportFile: title report advocate 4 - 6.pdf | 8 Oct 2017 |
| Copy of the legal title reportFile: title report advocate 7 - 9.pdf | 8 Oct 2017 |
| Details of encumbrancesFile: Letter Head 2.pdf | 8 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT Pradhan 4-ok.pdf | 8 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dharmendra - engineer report.pdf | 8 Oct 2017 |
| Certificates of CA (Form 3)File: CA Form.pdf | 8 Oct 2017 |
| Proforma of Allotment letterFile: Skywards Vision Developers-DRAFT AGREEMENT.pdf | 8 Oct 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 71 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SKYWARDS REGENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane
Filed coordinates, straight-line distance. 294 registered projects within 2 km.
FOREST VISTA
KASHIMIRA CERAMIC PRODUCTS LLP
Meera Queen
Zubair Kamruddin Siddique
SAI ENCLAVE WING B
MEHTA REALTY
ANA Avant Garde Phase 1
STEELFAB ENGINEERING CORPORATION
DELTA GARDEN
Delta venture
DELTA VRINDAVAN
Delta venture
See every Thane project, with the district possession charts
Builder: SKYWARDS VISION DEVELOPERS
SKYWARDS VISION DEVELOPERS has 1 registration on MahaRERA, including SKYWARDS REGENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SKYWARDS REGENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SKYWARDS REGENCY is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SKYWARDS REGENCY?
The registered promoter entity is SKYWARDS VISION DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SKYWARDS REGENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SKYWARDS REGENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SKYWARDS REGENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SKYWARDS REGENCY?
The professionals named in the filing: Architect: ULHAS GOPINATH PRADHAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKYWARDS REGENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback