Home / Browse projects / Thane, Maharashtra / ANA Avant Garde Phase 1

Completed No litigation declared Residential / Group Housing project

ANA Avant Garde Phase 1

By STEELFAB ENGINEERING CORPORATION

RG-MH-20899 · RERA P51700001388 · Last updated on MahaRERA portal: 4 Feb 2020

Source: official MahaRERA filing

Red flags

  • 23 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Internal walls, 98%
23Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

ANA Avant Garde Phase 1 is a Residential / Group Housing project by STEELFAB ENGINEERING CORPORATION in Thane, Maharashtra, registered with MahaRERA as P51700001388 on 27 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 23 complaints are on record with the regulator.

At a glance

Project

  • NameANA Avant Garde Phase 1
  • TypeResidential / Group Housing
  • Location
    • Western Express Highway
    • Kashimira Junction
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401104
  • Pincode401104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001388
  • ReraGenie IDRG-MH-20899

Builder

  • NameSTEELFAB ENGINEERING CORPORATION
  • Entity typePartnership
  • PartnerJignesh Pramod Shah

Key dates

this monthRegisteredJul 2017First promiseDec 2018Revised toDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing E and Wing FNA270000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

Wing E and Wing F: 97% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 4 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area713 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10799.06
Proposed, not sanctioned10,567 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch36, Crystal Building, Kemps Corner, Altamount Road, Mumbai, 400026

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTATA Consulting Engineers Limited
EngineerTATA Consulting Engineers Limited
PartnerRole in project
STEELFAB ENGINEERING CORPORATION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001034Dec 2018 → Dec 2019

Reason as filed by the promoterOccupancy Certificate is under Process, awaiting OC to receive

Complaints filed with MahaRERA23

Case no.ComplainantRespondentFiled
CC006000000001405Vidya Laxman ShettySteelFab Engineering Corporation22/10/2017
CC006000000056577RANJANA SINGHCHIRAG PRAMOD SHAH15/10/2018
CC006000000056759PRASHANT SAWANTSteel Fab Engineering Corporation29/10/2018
CC006000000057550Yogisha LadSai Estate Consultants Private Limited04/01/2019
CC006000000057578DIVYA CHHEDAsteelfab engineering ltd10/01/2019
CC006000000057682Abhishek jainSteelfab coorporation18/01/2019
CC006000000079024Steelfab Engineering CorporationVijay Dev Salian24/04/2019
CC006000000078236Suryakant SoparkarSteelfab Engineering Corporation24/02/2019
CC006000000078771Sachin Prem Chand SachdevaMr. Chirag Shah06/04/2019
CC006000000078913Vikramjeet Pal and Shushila PalM/s Steelfab Engineering Corporation16/04/2019
CC006000000079298Harshvardhan SinhaSteelfab Eng Corporation14/05/2019
CC006000000100479Vicky WadhwaniSteelfab Engineering Corporation19/08/2019
CC006000000100560Vicky WadhwaniSteelfab Engineering Corporation19/08/2019
CC006000000100561Bhagwan Wadhwanisteefab engineering corporation19/08/2019
CC006000000100562Amit WadhwaniSteelfab Engineering Corporation19/08/2019
CC006000000100563Amit WadhwaniSteelfab Engineering Corporation19/08/2019
CC006000000100565Milton MascarehnasSteelfab Engineering Corporation21/08/2019
CC006000000161426Bhupinder Kaur Sahni and Jaslyn Kaur SahniSteelfab Engineering Corporation13/12/2019
CC006000000193194Mariyam Imtiyaz Patel and Imad Imtiyaz PatelM/s Steelfeb Engineering Corporation06/05/2020
CC006000000196363Basantee BiswalANA Reality ([email protected])16/03/2021
CC006000000221002Samruddhi Ankit ShahM/S. ANA Realty08/05/2022
CC12500030STEELFAB ENGINEERING CORPORATIONMs Chandrika Raju Nair (Allotee)03/01/2025
CC12500066STEELFAB ENGINEERING CORPORATIONSunil Rout (Respondent)08/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Jan 2020

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate (Form 5) Annual Audit Report.pdf4 Feb 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MBMC 22 Story OC As-Build Plan - 1 to 5 Floor Plan Dtd 17-1-20_001.pdf20 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MBMC 22 Story OC As-Build Plan - 6 to 22 Floor Plan Dtd 17-1-20_001.pdf20 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MBMC 22 Story OC As-Build Plan - Layout Plan Dtd 17-1-20_001.pdf20 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MBMC 22 Story OC As-Build Plan - Section Plan Dtd 17-1-20_001.pdf20 Jan 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate Letter ANA Avant Garde Phase 1.pdf18 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: TCE Building Completion Certificate.pdf27 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: TCE Building Completion Certificate.pdf27 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TCE Architect Certificate Building Completion Dtd 11-5-18.pdf26 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Basavraj -Architect Tej Consultant Building Completion Letter.pdf26 Dec 2019
OtherFile: Basavraj -Architect Tej Consultant Building Completion Letter.pdf26 Dec 2019
OtherFile: TCE Architect Certificate Building Completion Dtd 11-5-18.pdf26 Dec 2019
OtherFile: OC Aplication Submission Confirmation Dtd 13-11-19.pdf26 Dec 2019
OtherFile: MBMC Stop Work Cancellation Order Scan Copy Dtd 21-9-19.pdf24 Oct 2019
OtherFile: MBMC Stop Work Cancellation Order Scan Copy Dtd 21-9-19.pdf24 Oct 2019
OtherFile: MBMC Stop Work Cancellation Order Scan Copy Dtd 21-9-19.pdf24 Oct 2019
OtherFile: ANA Reply to MBMC for Amenity Plot Development Notice Dtd 16-11-18.pdf17 Apr 2019
OtherFile: MBMC Stop Work Notice Dtd 14-12-18.pdf17 Apr 2019
OtherFile: ANA Repeated Request to MBMC Commissioner to remove Stop work notice Ltr Dtd 19-2-19 Ackno17 Apr 2019
OtherFile: MBMC PWD Confirmation about Amenity Plot Dev will be carried out by them Dtd 7-2-19.pdf17 Apr 2019
OtherFile: Sai Termination Letter Dated 08-02-2019 Lower V1.pdf11 Apr 2019
Certificates of CA (Form 5)File: Form 5 By CA Nirav Shah Dtd 31-1-19.pdf8 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architetcs Certificate Form 1 Dtd 30-9-18.pdf21 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2 Dtd 30-9-18.pdf21 Dec 2018
Certificates of CA (Form 3)File: CA Certificate Form 3 Dtd 30-9-18 Low Resolution.pdf21 Dec 2018
OtherFile: OC Application Dtd 15-11-18.pdf21 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Form 1 Dtd 31-3-18.pdf11 Jun 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2 Dtd 31-3-18.pdf11 Jun 2018
Certificates of CA (Form 3)File: CA Certificate Form 3 Dtd 31-3-18 Low Resolution.pdf11 Jun 2018
Proforma of Allotment letterFile: Final ANA RERA Agreement - Version - IIIIV - 1-Apr-18 Blank for RERA Upload V2.pdf7 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate TCE Form 1 Dtd 31-12-17.pdf15 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certifiate TCE Form 2 Dtd 31-12-17.pdf15 Feb 2018
Certificates of CA (Form 3)File: CA Certificate Form 3 Dtd 31-12-17 Small File Size.pdf15 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate TCE Form 1 Dtd 30-9-17.pdf18 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certifiate TCE Form 2 Dtd 30-9-17.pdf18 Oct 2017
Certificates of CA (Form 3)File: CA Certificate Form 3 Dtd 30-9-17 Small Size.pdf18 Oct 2017
Proforma of Allotment letterFile: ANA Avant Garde P1 Agreement.pdf7 Sep 2017
Building plan approvalFile: MBMC 22 Story Approved Plan - Layout Plan Dtd 27-5-16.pdf25 Jul 2017
Layout approvalFile: MBMC 22 Story Approved Plan - Floor Plan Dtd 27-5-16.pdf25 Jul 2017
PAN CardFile: Pan Card - Steelfab Engineering Corporation.pdf25 Jul 2017
Copy of the legal title reportFile: Mulla Title Certificate Dated 9-2-15 for Upload.pdf25 Jul 2017
Details of encumbrancesFile: Details of encumbrances Table.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: MBMC 22 Story Approved Plan - Floor Plan Dtd 27-5-16.pdf25 Jul 2017
Building Plan Approval (IOD)File: MBMC 22 Story Approved Plan - Layout Plan Dtd 27-5-16.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: MBMC CC Copy 22 Story Dtd 27-5-16 for Upload1.pdf25 Jul 2017
Declaration in FORM BFile: Declaration in FORM B Rule 3(6).pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final 25-7-17 Architect Certificate - Form 1.pdf25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Final 25-7-17 Engineers Certificate - Form 2 for Steelfab Engg Corpn by TCE For Upload.pdf25 Jul 2017
Certificates of CA (Form 3)File: Final Dtd 25-7-17 CA Certificate - Form 3 for Steelfab Engg Corpn by CA for Upload.pdf25 Jul 2017
Proforma of Allotment letterFile: Proforma of the Allotment letter and Agreement for Sale - Steelfab Engg Corpn.pdf25 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANA Avant Garde Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kashimira Junction7,600+ in Thane

2 kmANA Avant Garde Phase 1Completed 43Lapsed / revoked 23Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 129 registered projects within 2 km.

Builder: STEELFAB ENGINEERING CORPORATION

STEELFAB ENGINEERING CORPORATION has 1 registration on MahaRERA, including ANA Avant Garde Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ANA Avant Garde Phase 1 is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANA Avant Garde Phase 1?

The registered promoter entity is STEELFAB ENGINEERING CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANA Avant Garde Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANA Avant Garde Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANA Avant Garde Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANA Avant Garde Phase 1?

The professionals named in the filing: Architect: TATA Consulting Engineers Limited; Engineer: TATA Consulting Engineers Limited. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANA Avant Garde Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANA Avant Garde Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANA Avant Garde Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.