Home / Browse projects / Raigarh, Maharashtra / Sky Natraj

Registered No litigation declared Mixed project

Sky Natraj

By Natraj Buildcon

RG-MH-95863 · RERA P52000047649 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
7 of 9Construction stages donefurthest along: Installation of Lifts, 83%
39 of 59Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

Sky Natraj is a Mixed project by Natraj Buildcon in Raigarh, Maharashtra, registered with MahaRERA as P52000047649 on 14 Nov 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 20 of the 59 units on this registration are recorded sold or booked, and 7 of 9 construction stages are filed complete.

At a glance

Project

  • NameSky Natraj
  • TypeMixed
  • Location
    • Sector - 50
    • Dronagiri
    • Bokadvira
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000047649
  • ReraGenie IDRG-MH-95863

Builder

  • NameNatraj Buildcon
  • Entity typePartnership
  • GSTIN27AAJFN0028Q1ZX
  • PartnersMahesh Ananda Kherpatel, Premji Pancha Patel, Mavji Ganesha Patel

Key dates

this monthRegisteredNov 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Nov 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed121 files

Current status

34%20 of 59 units booked
62.2%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sky NatrajNA8851859

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 9 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 83%.

Sky Natraj: 96% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.83%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNo80%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed80

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots80
Closed/Covered80

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,099 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on12 Feb 2026

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI3743.52
Proposed, not sanctioned3,714 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 19-22, Plot No 1-1 1-2, Daffodil Chs, Nr Gaondevi Temple, Sector-14, Vashi-400705
Estimated costRs 10.28 cr
Cost incurredRs 6.39 cr
Work done62.18%
BuildingWingEstimatedIncurred
Sky NatrajNARs 8.97 crRs 6.39 cr
-NARs 1.30 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel Architects
EngineerS R Consultant
EngineerSC Engineers & Consultants
Chartered AccountantCA Rutuja Narsingh and Associates
Chartered AccountantR D Patel & Co
Chartered AccountantPatel Senghani & Parvadiya
Chartered AccountantJ P Senghani & Associates
PartnerRole in project
Natraj Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23022619973Dec 2025 → Dec 2026

Reason as filed by the promoterWe had recieved revised sanction CC from the Authority to develope a G+7 building instead of G+3 building as per previous CC. We have already completed 90% of the work, only minor finishing work is pending for which we are seeking extention.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: NB Form1 Jun26.pdf16 Jul 2026
Withdrawal Update Form 2File: NB Form 2 Jun26.pdf16 Jul 2026
Withdrawal Update Form 3File: NB Form3 Jun26.pdf16 Jul 2026
Withdrawal Update Form 1File: NB Form1 Mar26.pdf20 Apr 2026
Withdrawal Update Form 2File: NB Form2 Mar26.pdf20 Apr 2026
Withdrawal Update Form 3File: NB Form 3 Mar26.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: NB Form2A Mar26.pdf2 Apr 2026
Building plan approvalFile: 5-CC Revised Plan.pdf20 Mar 2026
Declaration and undertaking (Annexure A)File: NB AnnextureA.pdf20 Mar 2026
Withdrawal Update Form 1File: NB Form 1 Sep 24.pdf18 Mar 2026
Withdrawal Update Form 2File: NB Form 2 Sep24.pdf18 Mar 2026
Withdrawal Update Form 3File: NB Form 3 Sep24.pdf18 Mar 2026
Form 1File: NB Form 1 Dec22.pdf9 Mar 2026
Form 2File: NB Form 2 Dec22.pdf9 Mar 2026
Form 3File: NB Form 3 Dec22.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Dec22.pdf9 Mar 2026
Form 1File: NB Form 1 Mar23.pdf9 Mar 2026
Form 2File: NB Form 2 Mar23.pdf9 Mar 2026
Form 3File: NB Form 3 Mar23.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Mar23.pdf9 Mar 2026
Form 1File: NB form 1 Jun23.pdf9 Mar 2026
Form 2File: NB Form 2 Jun23.pdf9 Mar 2026
Form 3File: NB form 3 Jun23.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Jun23.pdf9 Mar 2026
Form 1File: NB Form 1 Sep23.pdf9 Mar 2026
Form 2File: NB Form 2 Sep23.pdf9 Mar 2026
Form 3File: NB Form 3 Sep23.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Sep23.pdf9 Mar 2026
Form 1File: NB Form 1 Dec23.pdf9 Mar 2026
Form 2File: NB Form 2 Dec23.pdf9 Mar 2026
Form 3File: NB Form 3 Dec23.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Dec 23.pdf9 Mar 2026
Form 1File: NB Form 1 Mar 24.pdf9 Mar 2026
Form 2File: NB Form 2 Mar24.pdf9 Mar 2026
Form 3File: NB Form 3 Mar24.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Mar24.pdf9 Mar 2026
Form 1File: NB Form 1 Jun24.pdf9 Mar 2026
Form 2File: NB Form 2 Jun24.pdf9 Mar 2026
Form 3File: NB Form 3 Jun24.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Jun24.pdf9 Mar 2026
Form 1File: 5-50-DRONAGIRI RERA (2024 DECEMBER ) (1).pdf9 Mar 2026
Form 2File: NB Form 2 Dec24.pdf9 Mar 2026
Form 3File: NB Form 3 Dec24.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Dec24.pdf9 Mar 2026
Form 1File: 5-50-DRONAGIRI RERA (2025 MARCH) (1).pdf9 Mar 2026
Form 2File: NB Form 2 Mar25.pdf9 Mar 2026
Form 3File: NB Form 3 Mar25.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: NB Inv Mar25.pdf9 Mar 2026
Withdrawal Update Form 1File: NB Form 1 Jun24.pdf9 Mar 2026
Withdrawal Update Form 1File: NB Form 1 Sep 24.pdf9 Mar 2026
Withdrawal Update Form 2File: NB Form 2 Jun24.pdf9 Mar 2026
Withdrawal Update Form 2File: NB Form 2 Sep24.pdf9 Mar 2026
Withdrawal Update Form 3File: NB Form 3 Jun24.pdf9 Mar 2026
Withdrawal Update Form 3File: NB Form 3 Sep24.pdf9 Mar 2026
Form 2A (FY 2022-2023)File: NB Form 2 Mar23.pdf9 Mar 2026
Form 2A (FY 2023-2024)File: NB Form 2A 23-24.pdf9 Mar 2026
Form 2A (FY 2024-2025)File: NB Form 2A 24-25.pdf9 Mar 2026
Form 5 (FY 2022-2023)File: NB Form 5 22-23.pdf9 Mar 2026
Form 5 (FY 2023-2024)File: NB Form 5 23-24.pdf9 Mar 2026
Form 5 (FY 2024-2025)File: NB Form 5 24-25.pdf9 Mar 2026
Withdrawal Update Form 1File: 5-50-DRONAGIRI RERA (2025 JUNE).pdf16 Feb 2026
Withdrawal Update Form 1File: 5-50-DRONAGIRI RERA (2025 SEPTEMBER).pdf16 Feb 2026
Withdrawal Update Form 1File: 5-50-DRONAGIRI RERA (2025 DECEMBER).pdf16 Feb 2026
Withdrawal Update Form 2File: dad0c0e1-cac2-4045-82ff-c57875bec4ed.pdf16 Feb 2026
Withdrawal Update Form 2File: NB Form 2 Sep25.pdf16 Feb 2026
Withdrawal Update Form 2File: NB Form 2 Dec25.pdf16 Feb 2026
Withdrawal Update Form 3File: b358b664-22a9-42ff-a35d-1da4b1364845.pdf16 Feb 2026
Withdrawal Update Form 3File: b358b664-22a9-42ff-a35d-1da4b1364845.pdf16 Feb 2026
Withdrawal Update Form 3File: NB f3 Dec25.pdf16 Feb 2026
Other - TechnicalFile: NB Consent.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NB Form1 Jun23.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NB Form1 Jun24.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NB Form1 Sep24.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NB Form3 Jun23.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NB Form3 Jun24.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NB Form3 Mar23.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NB Form3 Sep23.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NB Form3 Sep24.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NB Form 2 Jun23.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NB Form 2 Jun24.pdf27 Jan 2025

How this compares with Raigarh

34%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sky Natraj on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dronagiri5,900+ in Raigarh

2 kmSky NatrajCompleted 60Lapsed / revoked 22Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 125 registered projects within 2 km.

Builder: Natraj Buildcon

Natraj Buildcon has 1 registration on MahaRERA, including Sky Natraj. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Sky Natraj is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sky Natraj?

The registered promoter entity is Natraj Buildcon, a partnership as per the filing. Its GSTIN 27AAJFN0028Q1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sky Natraj?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sky Natraj?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sky Natraj?

The professionals named in the filing: Architect: Atul Patel Architects; Engineer: S R Consultant; Engineer: SC Engineers & Consultants; Chartered Accountant: CA Rutuja Narsingh and Associates; Chartered Accountant: R D Patel & Co; Chartered Accountant: Patel Senghani & Parvadiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sky Natraj?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sky Natraj. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sky Natraj to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.