Home / Browse projects / Raigarh, Maharashtra / SKY COPPER
SKY COPPER
RG-MH-87589 · RERA P52000017618 · Last updated on MahaRERA portal: 23 Jul 2024
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SKY COPPER is a Others project by SHREY INFRA PROJECT in Raigarh, Maharashtra, registered with MahaRERA as P52000017618 on 29 Aug 2018. The registration is recorded completed; possession was promised by 15 Aug 2023.
At a glance
Project
- NameSKY COPPER
- TypeOthers
- Location
- PLOT NO 118 SECTOR 50
- DRONAGIRI
- Bokadvira
- Uran
- Raigarh
- 400702
- Pincode400702
- RERA no.P52000017618
- ReraGenie IDRG-MH-87589
Builder
- NameSHREY INFRA PROJECT
- Entity typePartnership
- PartnersSANGITA M HIRANI, VIJAY J CHOVATIYA
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Aug 2018
- Promised completion15 Aug 2023
- Revised completionNone
- Buildings1 building record
- Documents filed65 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SKY COPPER | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SKY COPPER: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PANDURANG PARSHURAM GHARAT | Bokadvira | Raigarh |
| MOHAN PARSHURAM GHARAT | Bokadvira | Raigarh |
| ANANT PARSHURAM GHARAT | Bokadvira | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ATUL PATEL ARCHITECTS |
| Engineer | B S SUKTHANKAR & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHREY INFRA PROJECT | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to financial problem and unavailability of some raw materials grant us extension of 12 month we area almost complete project more than 90%
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Aug 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Jul 2024
Documents filed65
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - SKY COPPER P-118-50.pdf | 23 Jul 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form -4 - Architect - Plot - 118.pdf | 23 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1 plot - 118.pdf | 24 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P-118 - 31-03-2024.pdf | 24 Apr 2024 |
| Declaration about Commencement CertificateFile: CC DECLARATION FORMAT D -.pdf | 5 Dec 2023 |
| Declaration in FORM BFile: FORB -B -SKY COPPER .pdf | 5 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sky Copper_Form-5_FY2022-23_Signed.pdf | 30 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1- ARCHITECT.pdf | 25 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - SKY COPPER - ENG CERTIFICATE_compressed.pdf | 25 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM - 2A -ENGR.pdf | 25 Nov 2023 |
| Certificates of CA (Form 3)File: FORM 3 - SKY COPPER.pdf | 25 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P-118-50 30-09-2023.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P-118 SKY COPPER - 30-06-2023.pdf | 9 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 118 FORM 2A 9.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Sky Copper_Form-5_FY2018-19_Signed_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 SKY COPPER 2021-22_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sky Copper_Form-5_FY2019-20_Signed_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 SKY COPPER 2019-20_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sky Copper_Form-5_FY2020-21_Signed_New_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 SKY COPPER 2020-21_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sky Copper_Form-5_FY2021-22_Signed_compressed.pdf | 19 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 SKY COPPER 2021-22_compressed.pdf | 19 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 118 FORM 2A 9.pdf | 12 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 P-118 ARCHITECT CERT 31-12-2022.pdf | 9 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKY COPPER FORM 2.pdf | 9 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P- 118 SKY COPPER - 30-09-2022.pdf | 9 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P-118-50 - 31-12-2022.pdf | 9 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCHITECT CERT 30-06-2022_compressed.pdf | 19 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 30-06-2022_compressed.pdf | 19 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - PLOT 118 SKY COPPER - 30-06-2022.pdf | 19 Jul 2022 |
| Certificates of CA (Form 3)File: Shrey Infra Project Form 3 30062022 (1)_compressed_compressed.pdf | 19 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: SALES INVENTORY FOR RERA - P-118 - 31-03-2022 COMPRESSED.pdf | 24 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: P-118-50 RERA SOLD INVENTORY 31-12-21.pdf | 21 Jan 2022 |
| Form 2AFile: 118 FORM 2A 2.pdf | 17 Jul 2021 |
| Form 2AFile: 118 FORM 2A 3.pdf | 17 Jul 2021 |
| Form 2AFile: 118 FORM 2A 4.pdf | 17 Jul 2021 |
| Form 2AFile: 118 FORM 2A 5.pdf | 17 Jul 2021 |
| Form 2AFile: 118 FORM 2A 6.pdf | 17 Jul 2021 |
| Form 2AFile: 118 FORM 2A 7.pdf | 17 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ATUL PATEL - FORM 1 CERTIFICATE RERA UPDATE P-118.pdf | 15 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: P-118-50 RERA SOLD UNSOLD INVENTORY_compressed.pdf | 11 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA ARCHIOTECT FROM 1 _compressed.pdf | 25 Jul 2019 |
| Form 2AFile: 118 FORM 2A.pdf | 7 Jun 2019 |
| Building plan approvalFile: 2.pdf | 20 Aug 2018 |
| Building plan approvalFile: 3.pdf | 20 Aug 2018 |
| Building plan approvalFile: 4.pdf | 20 Aug 2018 |
| Building plan approvalFile: 5.pdf | 20 Aug 2018 |
| Building plan approvalFile: 6.pdf | 20 Aug 2018 |
| Building plan approvalFile: 1.pdf | 20 Aug 2018 |
| Layout approvalFile: 1.pdf | 20 Aug 2018 |
| PAN CardFile: SHREY INFRA PROJECT PAN CARD.pdf | 20 Aug 2018 |
| Copy of the legal title reportFile: TITLE SEARCH REPORT-ilovepdf-compressed.pdf | 20 Aug 2018 |
| Copy of the legal title reportFile: TITLE CLEARANCE CERTIFICATE-ilovepdf-compressed.pdf | 20 Aug 2018 |
| Details of encumbrancesFile: CERTIFICATE.pdf | 20 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 2.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 3.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 4.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 5.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 6.pdf | 20 Aug 2018 |
| Building Plan Approval (IOD)File: 1.pdf | 20 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: C C COPY.pdf | 20 Aug 2018 |
| Declaration in FORM BFile: FORM B DECLARATION .pdf | 20 Aug 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 20 Aug 2018 |
| Proforma of Allotment letterFile: PRINCIPAL AGREEMENT-ilovepdf-compressed (1).pdf | 20 Aug 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 65 filed documents as one ZIP, foldered, with a manifest
Keep SKY COPPER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DRONAGIRI5,900+ in Raigarh
VILLA ONE
Khodiyar Realtech LLP
Gami Bianca
LAL GEBI INFRA PRIVATE LIMITED
MAHAAVIR LABDHI PHASE 1
MAHAAVIR BUILDCON LLP
Siddhivinayak- Anaya
DIVYADRISHTI BUILDCON PRIVATE LIMITED
Horizon Landmark
GREENSCAPE KALPANA STRUCT CON
Grand Uran Central
Tycoons Altofin Realty
See every Raigarh project, with the district possession charts
Builder: SHREY INFRA PROJECT
SHREY INFRA PROJECT has 2 registrations on MahaRERA, including MISRI VILLA HEIGHT and SKY COPPER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SKY COPPER is delayed beyond 15 Aug 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SKY COPPER?
The registered promoter entity is SHREY INFRA PROJECT, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SKY COPPER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SKY COPPER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SKY COPPER?
The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Engineer: B S SUKTHANKAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKY COPPER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.