Home / Browse projects / Udupi, Karnataka / SKY CITY BLOCK-1
SKY CITY BLOCK-1
By Skyway Infra
RG-KA-12586 · RERA PRM/KA/RERA/1273/318/PR/200624/003459 · Last updated on RERA Karnataka portal: 6 Jun 2020
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SKY CITY BLOCK-1 is a Residential/Group Housing project by Skyway Infra in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/200624/003459 on 24 Jun 2020. Possession is promised by 31 Dec 2024. The completion date has moved by 9 months from the original filing. 0 of the 84 units on this registration are recorded sold or booked, and 0 of 19 construction stages are filed complete.
At a glance
Project
- NameSKY CITY BLOCK-1
- TypeResidential/Group Housing
- Location
- Udupi
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1273/318/PR/200624/003459
- ReraGenie IDRG-KA-12586
Builder
- NameSkyway Infra
- Entity typePartnership Firm
- Authorized SignatorySAYED AKBAR ALI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Jun 2020
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 31 Mar 2024)
- Buildings1 building record
- Documents filed55 files
Current status
Figures as on 6 Jun 2020, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SKY CITY-BLOCK 1 | - | - | - | 84 | 0 | 84 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 6 Jun 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 19 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 6 Jun 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR.GEORGE T.V |
| Engineer | MR.GEORGE T.V |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed55
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/200624/003459 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| SANCTION LETTER FROM TOWN PANCHAYATHFile: Town Licence- For query.jpg | 6 Jun 2020 |
| CLARIFICATIONFile: EXPLANATION.pdf | 18 Feb 2020 |
| planFile: plan (2).pdf | 25 Jan 2020 |
| original planFile: building plan.pdf | 7 Jan 2020 |
| building licenseFile: building lic.jpg | 27 Dec 2019 |
| noc from waterFile: NOC from Local Water Supply & Power.pdf | 27 Dec 2019 |
| ecFile: ec.pdf | 27 Dec 2019 |
| building plotFile: plan.pdf | 27 Dec 2019 |
| CertificateFile: COMBINE.pdf | - |
| commencement certificate | - |
| building plan | - |
| SINGLE LAYOUT | - |
| Draft sale deed | - |
| Agreeement to sale1 | - |
| SALEDEEDNRTC | - |
| building plan | - |
| not applicalbe | - |
| Allotment Letter | - |
| Brochure | - |
| NOC from Local Water Supply & Power | - |
| project spec | - |
| ec | - |
| affadavit | - |
| not applicalbe | - |
| khata | - |
| not applicalbe | - |
| conversion1 | - |
| NOC (3) | - |
| NOC from Airport Authority of India | - |
| noc from seiaa | - |
| Balance Sheet 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Balance Sheet 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Balance Sheet 2016 - 2017File: financial documents not applicalbe.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: financial documents not applicalbe.pdf | - |
| Director's Report 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Director's Report 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Director's Report 2016 - 2017File: financial documents not applicalbe.pdf | - |
| Cash Flow Statement 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Cash Flow Statement 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Auditor's Report 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Auditor's Report 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Auditor's Report 2016 - 2017File: financial documents not applicalbe.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: financial documents not applicalbe.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: financial documents not applicalbe.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: financial documents not applicalbe.pdf | - |
| form b (1) | - |
| Prospectus/BrochureFile: Brochure.pdf | - |
| Advertisement Copy 1File: Advertisement-NA.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1273_318_PR_200624_003459.xlsx | - |
| Occupancy CertificateFile: Occupancy certificate by Gram panchayat.pdf | - |
| Completion certificate issued by the competent authorityFile: Completion Affidavit.pdf | - |
| Registered Agreement of SaleFile: Agreement of Sale.pdf | - |
| Registered conveyance deed for an individual unitFile: Agreement of Sale.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep SKY CITY BLOCK-1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: Skyway Infra
Skyway Infra has 1 registration on RERA Karnataka, including SKY CITY BLOCK-1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if SKY CITY BLOCK-1 is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SKY CITY BLOCK-1?
The registered promoter entity is Skyway Infra, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SKY CITY BLOCK-1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SKY CITY BLOCK-1?
The professionals named in the filing: Architect: MR.GEORGE T.V; Engineer: MR.GEORGE T.V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKY CITY BLOCK-1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback