Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
293 of 293Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

SKORA ML GOLDEN PALMS is a Others project by SKORA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700080052 on 22 Apr 2025. Possession is promised by 31 Dec 2030. 0 of the 293 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameSKORA ML GOLDEN PALMS
  • TypeOthers
  • Location
    • AT VILLAGE TEMGHAR
    • BHIWANDI
    • Bhiwandi (M Corp.)
    • Thane
    • 421302
  • Pincode421302
  • RERA no.P51700080052
  • ReraGenie IDRG-MH-31717

Builder

  • NameSKORA DEVELOPERS
  • Entity typePartnership
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2025PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Apr 2025
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Current status

0%0 of 293 units booked
10.0%Work done, per cost certificate

Figures as on 11 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PLOT B BUILDING NO 1NA202024944293

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

PLOT B BUILDING NO 1: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed162

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots162
Closed/Covered36
Open Space126

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,321 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Sep 2026
LandownerVillageDistrict
KEJAL ENTERPRISES PROPRIETOR SANJAY LAXMAN MHATREBhiwandi (M Corp.)Thane

Approvals and building plan

Sanctioning authorityBHIWANDI NIZAMPUR CITY MUNICIPAL CORPORATION
Permissible FSI18579.52
Proposed, not sanctioned18,163 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD FLR SHOP NO 4 5 MASTER PLAZA COMMERCIAL COMPLEX NR MUM NASIK HIGHWAY BHIWANDI MAHARASHTRA 421302
Estimated costRs 49.19 cr
Cost incurredRs 4.92 cr
Work done10.0%
BuildingWingEstimatedIncurred
PLOT B BUILDING NO 1NARs 49.19 crRs 4.92 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAVRACHANA ARCHITECT AND INTERIOR DESIGNER
EngineerR KAY CONSULTANTS
EngineerMANDHADI VENKAT RAMANA REDDY
Chartered AccountantNITIN B DHAVAN & CO
PartnerRole in project
SKORA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 GOLDEN PALM JUNE 26 signed.pdf11 Sep 2026
Withdrawal Update Form 2File: FORM 2 ML PALM signed.pdf11 Sep 2026
Withdrawal Update Form 3File: SKORA FORM 3 GOLDEN PALMSJUNE 2026 signed_11zon (1).pdf11 Sep 2026
Form 2A (FY 2025-2026)File: ML GOLDEN PALM 2A CERTIFICATE (1).pdf11 Sep 2026
Form 1File: FORM 1 GOLDEN PALM JUNE 26 signed.pdf25 Jul 2026
Form 2File: FORM 2 ML PALM signed.pdf25 Jul 2026
Form 3File: SKORA FORM 3 GOLDEN PALMSJUNE 2026 signed_11zon.pdf25 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DISLOSURE GOLDEN JUNE.pdf25 Jul 2026
Form 1File: palms PHASE 2_SCHOOL RESERVATION_form 1 (architect certificate)_30 MARCH 2026.pdf29 Apr 2026
Form 2File: palm sns form 2.pdf29 Apr 2026
Form 3File: form3 SKORA GOLDEN PALMS_11zon.pdf29 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DISLOSURE GOLDEN JUNE.pdf29 Apr 2026
Form 1File: form 1 golden palm dec 25.pdf14 Feb 2026
Form 2File: from 2 skora golden palms dec 25.pdf14 Feb 2026
Form 3File: SKORA PALMS DEC 25 FORM 3_11zon.pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DICLOSURE.pdf14 Feb 2026
Form 1File: ML GOLDEN FORM 1.pdf29 Nov 2025
Form 2File: ML GOLDEN FORM 2.pdf29 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DICLOSURE.pdf29 Nov 2025
Form 3File: FORM 3 SEPT 25 SKORA ML VISTA_11zon.pdf29 Nov 2025
Form 1File: FORM 1-SKORA ML GOLDEN PALMS 30 june 2025.pdf18 Jul 2025
Form 2File: FORM 2 -SKORA ML GOLDEN PALMS 30 june 2025.pdf18 Jul 2025
Form 3File: form 3 skora ML GOLDEN PALMS june 25 SIGNED AND UDIN_11zon.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD DISLOSURE GOLDEN JUNE.pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SKORA GOLDEN PALMS REVISED UNIT OFFICE.pdf16 Apr 2025
Other - TechnicalFile: LAND VALUE ZERO.pdf16 Apr 2025
Copy of the legal title reportFile: TITLE CHANGES DONE.pdf4 Apr 2025
Declaration in FORM BFile: form b skora golden palm add address.pdf4 Apr 2025
Layout approvalFile: shuddhi patra vista.pdf29 Mar 2025
Copy of Layout Approval (in case of layout)File: shuddhi patra vista.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SKORA GOLDEN PALMS SIGNED.pdf29 Mar 2025
Other - TechnicalFile: shuddhi patra vista.pdf29 Mar 2025
Layout approvalFile: LAYOUT MARKED B_11zon.pdf28 Mar 2025
Details of encumbrances concerned to FinanceFile: LEGAL LITIGATION GOLDEN PALMS.pdf28 Mar 2025
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCES TO FINANCE GOLDEN PALMS.pdf28 Mar 2025
Copy of Layout Approval (in case of layout)File: LAYOUT MARKED B_11zon.pdf28 Mar 2025
Proforma of Allotment letterFile: ALLOTMENT LETYTER SKORA GOLDEN PALMS.pdf28 Mar 2025
Declaration about Commencement CertificateFile: FORMAT D GOLDEN PALMS.pdf28 Mar 2025
CERSAI detailsFile: CERSAI DECLARATION SKORA GOLDEN PALMS.pdf28 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A GOLDEN PALMS.pdf28 Mar 2025
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCES TO FINANCE GOLDEN PALMS.pdf28 Mar 2025
Details of encumbrances concerned to LegalFile: LEGAL LITIGATION GOLDEN PALMS.pdf28 Mar 2025
Proforma of Agreement for saleFile: DRAFT AGREEMENT PLOT B GOLDEN PALMS.pdf28 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B SKORA GOLDEN PALMS.pdf28 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF SECURED AND UNSECURED.pdf28 Mar 2025
Building plan approvalFile: PLOT AREA CALCULATION SHEET 2.pdf25 Mar 2025
Building plan approvalFile: PLOT B BLDG 1 SHEET 6.pdf25 Mar 2025
Building plan approvalFile: PLOT B BLDG 1 SHEET 7.pdf25 Mar 2025
Building plan approvalFile: PLOT B--BLDG 1 SHEET 8.pdf25 Mar 2025
Building plan approvalFile: PLOT B- BLDG NO 1.pdf25 Mar 2025
PAN CardFile: PAN UPLOAD.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf25 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC- BNCMC.PDF25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLOT AREA CALCULATION SHEET 2.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLOT B BLDG 1 SHEET 6.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLOT B BLDG 1 SHEET 7.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLOT B--BLDG 1 SHEET 8.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: PLOT B- BLDG NO 1.pdf25 Mar 2025
Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT.pdf25 Mar 2025
Other - TechnicalFile: CC COMMENT VISTA AND DIAMOND.pdf25 Mar 2025
Other - TechnicalFile: one plot one project.pdf25 Mar 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION AGREEMENT.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOAUSRE OF VIJAY KUMAR - VISTA.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest J MURLIDHAR REDDY.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest PATIL SIVANNA GAUDA.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest RATHNAPPA XAVIER.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest SHIVAM KATIRA.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interestLATA VIJAY PITTA.pdf25 Mar 2025

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SKORA ML GOLDEN PALMS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHIWANDI7,600+ in Thane

Builder: SKORA DEVELOPERS

SKORA DEVELOPERS has 2 registrations on MahaRERA, including SKORA ML GOLDEN PALMS and SKORA ML VISTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SKORA ML GOLDEN PALMS is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SKORA ML GOLDEN PALMS?

The registered promoter entity is SKORA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SKORA ML GOLDEN PALMS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SKORA ML GOLDEN PALMS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SKORA ML GOLDEN PALMS?

The professionals named in the filing: Architect: NAVRACHANA ARCHITECT AND INTERIOR DESIGNER; Engineer: R KAY CONSULTANTS; Engineer: MANDHADI VENKAT RAMANA REDDY; Chartered Accountant: NITIN B DHAVAN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKORA ML GOLDEN PALMS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKORA ML GOLDEN PALMS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKORA ML GOLDEN PALMS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.