Home / Browse projects / Pune, Maharashtra / Siyona Phase - II

Registered No litigation declared Residential / Group Housing project

Siyona Phase - II

By PETHKAR PROJECTS

RG-MH-04723 · RERA P52100020135 · Last updated on MahaRERA portal: 21 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedmoved 27 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 70%
192 of 376Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 232 documents Report an error

Siyona Phase - II is a Residential / Group Housing project by PETHKAR PROJECTS in Pune, Maharashtra, registered with MahaRERA as P52100020135 on 29 Mar 2019. Possession is promised by 30 Mar 2029. The completion date has moved by 27 months from the original filing. 184 of the 376 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameSiyona Phase - II
  • TypeResidential / Group Housing
  • Location
    • OFF MUMBAI BANGLURU BYPASS
    • PUNAWALE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020135
  • ReraGenie IDRG-MH-04723

Builder

  • NamePETHKAR PROJECTS
  • Entity typePartnership
  • PartnersCHANDRAKANT SHANKARRAO PETHKAR, SACHIN CHANDRAKANT PETHKAR, ABHIJIT CHANDRAKANT PETHKAR
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2019First promiseDec 2026Revised toMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Mar 2019
  • Promised completion30 Mar 2029
  • Revised completionRevised to 30 Mar 2029 (originally 30 Dec 2026)
  • Buildings2 building records
  • Documents filed232 files

Current status

49%184 of 376 units booked
60.9%Work done, per cost certificate

Figures as on 21 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DNA26241880188
ENA26241880188

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 70%.

D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E31%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed428

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots428
Closed/Covered189
Open Space239
BuildingClosed/CoveredOpen SpaceTotal
D87149236
E10290192

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,651 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2026
LandownerVillageDistrict
BABULAL BHURMAL OSWALPune (M Corp.)Pune
YASHWANT BABULAL OSWALPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION, PIMPRI
Permissible FSI26282.44
Proposed, not sanctioned11,396 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGUJRAT COLONY,PAUD ROAD,KOTHRUD,PUNE - 411038
Estimated costRs 162.00 cr
Cost incurredRs 98.70 cr
Work done60.93%
BuildingWingEstimatedIncurred
DNARs 80.00 crRs 79.17 cr
ENARs 80.00 crRs 19.53 cr
-NARs 2.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK a Architecture
EngineerMANDAR MADHUKAR LAPATE MADHUKAR LAPATE
Chartered AccountantAMBAR NAIK & ASSOCIATES
Chartered AccountantNitin B Inamdar
PartnerRole in project
PETHKAR PROJECTS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11062621310Dec 2026 → Mar 2029

Reason as filed by the promoterConstruction of the Building D has been completed. Construction of the Building E is under process. We want extension till 30/03/2029 to complete the construction of the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Dec 2022

Documents filed232

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 232 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf21 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf21 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf21 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf24 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf24 Jun 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE APRIL 2026.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf11 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf11 Jun 2026
Withdrawal Update Form 3File: FORM 3 - APRIL 2026 fINAL.pdf11 Jun 2026
Form 1File: FORM 1 Final.pdf8 Jun 2026
Form 2File: FORM 2 30-06-2019.pdf8 Jun 2026
Form 3File: FORM 3.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf8 Jun 2026
Form 1File: FORM 1 Final.pdf8 Jun 2026
Form 2File: FORM 2 30-09-2019.pdf8 Jun 2026
Form 3File: FORM 3.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf8 Jun 2026
Form 1File: FORM 1 Final.pdf8 Jun 2026
Form 2File: FORM 2 30-06-2019.pdf8 Jun 2026
Form 3File: FORM 3.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf8 Jun 2026
Form 1File: FORM 1.pdf6 Jun 2026
Form 2File: FORM 2 30-06-2025.pdf6 Jun 2026
Form 3File: FORM 3 (1).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: JUNE 2025.pdf6 Jun 2026
Form 1File: FORM 1.pdf6 Jun 2026
Form 2File: FORM 2 30-09-2025.pdf6 Jun 2026
Form 3File: FORM 3 (2).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1.pdf6 Jun 2026
Form 2File: FORM 2 31-12-2025.pdf6 Jun 2026
Form 3File: FORM 3 (3).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (1).pdf6 Jun 2026
Form 2File: FORM 2 31-03-2021.pdf6 Jun 2026
Form 3File: FORM 3 (1).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (2).pdf6 Jun 2026
Form 2File: FORM 2 31-06-2021.pdf6 Jun 2026
Form 3File: FORM 3 (2).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: Form 1.pdf6 Jun 2026
Form 2File: FORM 2.pdf6 Jun 2026
Form 3File: FORM 3.pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (3).pdf6 Jun 2026
Form 2File: form 2.pdf6 Jun 2026
Form 3File: FORM 3 (3).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (4).pdf6 Jun 2026
Form 2File: FORM 2 31-12-2021.pdf6 Jun 2026
Form 3File: FORM 3 (4).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (1) (1).pdf6 Jun 2026
Form 2File: FORM 2 30-03-2020.pdf6 Jun 2026
Form 3File: FORM 3 (1).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 Finsl.pdf6 Jun 2026
Form 2File: FORM 2 30-06-2020.pdf6 Jun 2026
Form 3File: FORM 3 (2).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 final.pdf6 Jun 2026
Form 2File: FORM 2 30-09-2022.pdf6 Jun 2026
Form 3File: FORM 3 (3).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf6 Jun 2026
Form 1File: FORM 1 (4).pdf6 Jun 2026
Form 2File: FORM 2 31-12-2022.pdf6 Jun 2026
Form 3File: FORM 3 (4).pdf6 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf6 Jun 2026
Form 1File: FORM 1 (4).pdf28 May 2026
Form 2File: FORM 2 30-03-2022.pdf28 May 2026
Form 3File: FORM 3.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf28 May 2026
Form 1File: FORM 1 (1).pdf28 May 2026
Form 2File: FORM 2 30-06-2022.pdf28 May 2026
Form 3File: FORM 3.pdf28 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY.pdf28 May 2026
Form 1File: FORM 1 (2).pdf28 May 2026
Form 2File: FORM 2 30-09-2022.pdf28 May 2026
Form 3File: FORM 3.pdf28 May 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Siyona Phase - IOff Mumbai Bangaluru Highway Punawale PCMC Pune - 411033324CompletedDec 2018Dec 2018

How this compares with Pune

49%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 27 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Siyona Phase - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNAWALE13,700+ in Pune

2 kmSiyona Phase - IICompleted 88Lapsed / revoked 32Other 112Dot size: filed unitsN

Filed coordinates, straight-line distance. 232 registered projects within 2 km.

Builder: PETHKAR PROJECTS

PETHKAR PROJECTS has 2 registrations on MahaRERA, including Siyona Phase - I and Siyona Phase - II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Siyona Phase - II is delayed beyond 30 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Siyona Phase - II?

The registered promoter entity is PETHKAR PROJECTS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Siyona Phase - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Siyona Phase - II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Siyona Phase - II?

The professionals named in the filing: Architect: VK a Architecture; Engineer: MANDAR MADHUKAR LAPATE MADHUKAR LAPATE; Chartered Accountant: AMBAR NAIK & ASSOCIATES; Chartered Accountant: Nitin B Inamdar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Siyona Phase - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Siyona Phase - II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Siyona Phase - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.