SINI ENTERPRISES

By VINOD BALNATH PATIL

RG-MH-51005 · RERA P51700014766 · Last updated on MahaRERA portal: 6 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
2 of 11Construction stages donefurthest along: Stilt Floor, 67%
104 of 200Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

SINI ENTERPRISES is a Others project by VINOD BALNATH PATIL in Thane, Maharashtra, registered with MahaRERA as P51700014766 on 2 Jan 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 96 of the 200 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameSINI ENTERPRISES
  • TypeOthers
  • Location
    • kalher
    • Kalher (CT)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700014766
  • ReraGenie IDRG-MH-51005

Builder

  • NameVINOD BALNATH PATIL
  • Entity typeIndividual

Key dates

this monthRegisteredJan 2018First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Jan 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed48 files

Current status

48%96 of 200 units booked
79.3%Work done, per cost certificate

Figures as on 6 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SINI SQUARE BUILDING TYPE A WING A WING B ,BUILDINGTYPE BNA383818416200

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 67%.

SINI SQUARE BUILDING TYPE A WING A WING B ,BUILDINGTYPE B: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor67%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises67%
Sanitary Fittings within the flats / premises67%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks67%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.67%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.67%

Progress on shared amenities15

As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes30%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed218

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots218
Closed/Covered132
Open Space86

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,455 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Oct 2025
LandownerVillageDistrict
PANDURANG GANPAT MADHAVIRahanal (CT)Thane

Approvals and building plan

Sanctioning authorityMUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY
Permissible FSI7015.85
Proposed, not sanctioned6,048 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGB-149, HIGH STREET MALL,KAPURBAWDI JUNCTION ,THANE WEST 400607
Estimated costRs 40.84 cr
Cost incurredRs 32.39 cr
Work done79.3%
BuildingWingEstimatedIncurred
SINI SQUARE BUILDING TYPE A WING A WING B ,BUILDINGTYPE BNARs 33.94 crRs 28.97 cr
-NARs 6.91 crRs 3.42 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDURRAJ KAMANKAR
Architectk.k and associates
EngineerDURAJ KAMANKAR
EngineerK.K AND ASSOCIATES
Chartered AccountantSAMPAT BALDIA
Chartered AccountantDHIRAJ S PAREEK & CO
PartnerRole in project
VINOD BALNATH PATIL-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011438Dec 2023 → Dec 2024

Reason as filed by the promoterWITH RESPECT TO DELAY OF THE COMPLETION OF PROJECT WE HEREBY STATE THAT DUE TO COVID19 SEVERAL GOVERNMENT RESTRICTION IT WAS NOT POSSIBLE TO CARRYING OUT CONSTRUCTION WORK

EA28102518182Dec 2023 → Dec 2026

Reason as filed by the promoter1. Court Case in Bhiwandi Court (Civil Suit No. 52/2024): A legal dispute related to the project is currently under litigation in the Bhiwandi Court, from 05/03/2024 which has caused unforeseen delays in the completion of the project. 2. Consent from Allottees as per Section 7(3) As per the regulations stated under Section 7(3) & Circular 28A/2021, we are in the process of obtaining consent from the allottees of the sold units. This process is ongoing, and due to certain logistical and legal formalities, We will be applying for an extension of the project as soon as possible. We are in the fin

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Dec 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Apr 2022

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5-(24-25).pdf6 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf4 Jul 2026
Withdrawal Update Form 1File: Architect Certificates 0101.pdf1 Jul 2026
Withdrawal Update Form 1File: Architect Certificates.pdf1 Jul 2026
Withdrawal Update Form 2File: Engineer Certificate 0101.pdf1 Jul 2026
Withdrawal Update Form 2File: Engineer Certificates.pdf1 Jul 2026
Withdrawal Update Form 3File: Form 3- For Q3.pdf1 Jul 2026
Withdrawal Update Form 3File: Form 3- For Q4.pdf1 Jul 2026
Withdrawal Update Form 1File: form 1.pdf10 Jun 2026
Withdrawal Update Form 2File: form 2.pdf10 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf10 Jun 2026
Withdrawal Update Form 1File: form 1.pdf9 Jun 2026
Withdrawal Update Form 2File: form 2.pdf9 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf9 Jun 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf19 Feb 2025
Certificates of CA (Form 3)File: CA.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf19 Feb 2025
Disclosure of sold/ booked inventoryFile: Inventory List of Sin_compressed (1).pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificates 2A.pdf19 Feb 2025
Declaration about Commencement CertificateFile: Sini square declaration about cc.pdf16 Apr 2022
Declaration in FORM BFile: affidavit cum declaration page1.pdf16 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate ed.pdf16 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate essed.pdf16 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate (1)_compressed (1).pdf16 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate (1)_compressed (1).pdf16 Apr 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD LIST_compressed (1).pdf16 Apr 2022
Certificates of CA (Form 3)File: FORM3-1-5_compressed.pdf16 Apr 2022
Certificates of CA (Form 3)File: FORM3-6-7.pdf16 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM5_compressed (4).pdf16 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM5_compressed (4).pdf16 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM5_compressed (3).pdf16 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM5_compressed (3).pdf16 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2021-1-5.pdf16 Apr 2022
Building plan approvalFile: 33_0001-1.pdf27 Dec 2017
Layout approvalFile: PLAN.pdf27 Dec 2017
Copy of Layout Approval (in case of layout)File: PLAN.pdf27 Dec 2017
Building Plan Approval (IOD)File: 33_0001-1.pdf27 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE_Compressed.pdf27 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE_Compressed.pdf27 Dec 2017
Certificates of CA (Form 3)File: VINOD CA CERTIFICATE_Compressed.pdf27 Dec 2017
Details of encumbrancesFile: images.pdf20 Dec 2017
Declaration in FORM BFile: VINOD PATIL DECLARATION.pdf20 Dec 2017
Proforma of Allotment letterFile: Flat-Draft-Rera (2).pdf20 Dec 2017
Building plan approvalFile: PLAN.pdf29 Nov 2017
Building Plan Approval (IOD)File: PLAN.pdf29 Nov 2017
PAN CardFile: PAN CARD.pdf27 Nov 2017
Copy of the legal title reportFile: images (3).pdf27 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf27 Nov 2017

How this compares with Thane

48%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SINI ENTERPRISES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kalher7,600+ in Thane

2 kmSINI ENTERPRISESCompleted 1Lapsed / revoked 7Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 29 registered projects within 2 km.

Builder: VINOD BALNATH PATIL

VINOD BALNATH PATIL has 1 registration on MahaRERA, including SINI ENTERPRISES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SINI ENTERPRISES is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SINI ENTERPRISES?

The registered promoter entity is VINOD BALNATH PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SINI ENTERPRISES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SINI ENTERPRISES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SINI ENTERPRISES?

The professionals named in the filing: Architect: DURRAJ KAMANKAR; Architect: k.k and associates; Engineer: DURAJ KAMANKAR; Engineer: K.K AND ASSOCIATES; Chartered Accountant: SAMPAT BALDIA; Chartered Accountant: DHIRAJ S PAREEK & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SINI ENTERPRISES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SINI ENTERPRISES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SINI ENTERPRISES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.