Home / Browse projects / Pune, Maharashtra / Silverstone Lonaville

Registered No litigation declared Others project

Silverstone Lonaville

By Silverstone Homemakers Pvt. Ltd

RG-MH-19885 · RERA P52100007543 · Last updated on MahaRERA portal: 20 Mar 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 53 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 53 months from the original
146 of 451Construction stages doneacross 41 buildings; furthest along: Basement (if any), 85%
31 of 41Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

Silverstone Lonaville is a Others project by Silverstone Homemakers Pvt. Ltd in Pune, Maharashtra, registered with MahaRERA as P52100007543 on 17 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 53 months from the original filing. 10 of the 41 units on this registration are recorded sold or booked, and 146 of 451 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSilverstone Lonaville
  • TypeOthers
  • Location
    • Varsoli
    • Mawal
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007543
  • ReraGenie IDRG-MH-19885

Builder

  • NameSilverstone Homemakers Pvt. Ltd
  • Entity typeCompany
  • DirectorsBhavesh Kantilal Patel, Bharat Kantilal Patel
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseJul 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Jul 2023)
  • Buildings41 building records
  • Documents filed108 files

Current status

24%10 of 41 units booked

Figures as on 20 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VILLA NO 01NA42101
VILLA NO 02NA22101
VILLA NO 03NA22101
VILLA NO 04NA42101
VILLA NO 05NA42101
VILLA NO 06NA42101
VILLA NO 07NA22101
VILLA NO 08NA42101
VILLA NO 09NA42101
VILLA NO 10NA22101
VILLA NO 11NA22101
VILLA NO 12NA42101
VILLA NO 13NA42101
VILLA NO 14NA22101
VILLA NO 15NA22101
VILLA NO 16NA42101
VILLA NO 17NA42101
VILLA NO 18NA22101
VILLA NO 19NA22101
VILLA NO 20NA42101
VILLA NO 21NA42101
VILLA NO 22NA22101
VILLA NO 23NA22101
VILLA NO 24NA42101
VILLA NO 25NA42101
VILLA NO 26NA22101
VILLA NO 27NA22101
VILLA NO 28NA42101
VILLA NO 32NA42101
VILLA NO 33NA32101
VILLA NO 35NA32101
VILLA NO 36NA32101
VILLA NO 37NA42101
VILLA NO 34NA32101
VILLA NO 38NA42101
VILLA NO 39NA42101
VILLA NO 40NA42101
VILLA NO 41NA42101
VILLA NO 42NA22101
VILLA NO 43NA22101
VILLA NO 50NA42101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 20 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 41 buildings; the table lists the first 20.

146 of 451 construction stages are filed complete across 41 buildings. The stage furthest along is Basement (if any), at 85%.

VILLA NO 0144%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor82%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0255%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0355%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0455%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0518%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 069%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 079%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0818%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 0925%
ActivityProgress
Excavation100%
Basement (if any)85%
Podiums (if any)0%
Plinth85%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1025%
ActivityProgress
Excavation100%
Basement (if any)85%
Podiums (if any)0%
Plinth85%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1150%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1250%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 130%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 140%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 160%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1755%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1816%
ActivityProgress
Excavation100%
Basement (if any)40%
Podiums (if any)0%
Plinth40%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1918%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 2018%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes47%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered4
Open Space31
BuildingClosed/CoveredOpen SpaceTotal
VILLA NO 01011
VILLA NO 02011
VILLA NO 03011
VILLA NO 04011
VILLA NO 05011
VILLA NO 06011
VILLA NO 07011
VILLA NO 08011
VILLA NO 09011
VILLA NO 10011
VILLA NO 11011
VILLA NO 12011
VILLA NO 13011
VILLA NO 14011
VILLA NO 15011
VILLA NO 16011
VILLA NO 17011
VILLA NO 18011
VILLA NO 19011
VILLA NO 20011
VILLA NO 21011
VILLA NO 22011
VILLA NO 23011
VILLA NO 24011
VILLA NO 25011
VILLA NO 26011
VILLA NO 27011
VILLA NO 28011
VILLA NO 33101
VILLA NO 35101
VILLA NO 36101
VILLA NO 34101
VILLA NO 42011
VILLA NO 43011
VILLA NO 50011

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,640 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
LAKHANI PANACHEKhargharRaigarh

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority, Pune
Permissible FSI5689.35
Proposed, not sanctioned5,689 sq m
Buildings approved41
Buildings sanctioned41

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Shubham Palace Main Road Sector 15 Kopar Khairane Navi Mumbai 400709

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARAKH ASSOCIATES ARCHITECTS AND INTERIOR DESIGNERS
ArchitectM/S. HITEN SETHI ARCHITECTS
ArchitectPB Associates
EngineerMAHIMTURA CONSULTANTS PVT LTD.
EngineerS K Consultants & Engineers
Chartered AccountantN B Sayed & Associates
PartnerRole in project
Silverstone Homemakers Pvt. Ltd-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013809Jul 2023 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 52.38% allottees for purpose of extension of RERA registration period of the said project.

EA20032620301Jul 2023 → Dec 2027

Reason as filed by the promoterWe, Silverstone Homemakers Pvt. Ltd, the promoter of the project Silverstone Lonaville (Registration No. P52100007543) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely apologize for the delay in the completion of the Project. The delay was primarily caused by limited financial resources, which affected the timely procurement of materials and the continuation of planned activities. We are in the process of securing the required finances and are confident that we will complete the remaining work within the stipulated timeframe. Gi

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000075197Mr. Paresh Keshavji Karwa & Mr. Pankaj Keshavji KarwaM/s Lakhani Builders Private Limited11/02/2021
CC005000000075199Mr. Rasik Surji Karwa & Mr. Ashok Surji KarwaM/s Lakhani Builders Private Limited11/02/2021
CC005000000075202Mr. Meghji Moraji Karwa & Mrs. Shakuntala Meghji KarwaM/s Lakhani Builders Private Limited11/02/2021
CC12504431Sudhir AgrawalSilverstone Homemakers Pvt. Ltd12/12/2025
CC12504501lakhani buildersSilverstone Homemakers Pvt. Ltd16/12/2025
CC12604423Amit Jain HUFSilverstone Homemakers Pvt. Ltd16/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Dec 2025_rotated_11zon.pdf20 Mar 2026
Withdrawal Update Form 1File: Form 1 Dec 2025_rotated_11zon.pdf20 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf20 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf20 Mar 2026
Withdrawal Update Form 3File: Form 3 Dec A.pdf20 Mar 2026
Withdrawal Update Form 3File: Form 3 Dec A.pdf20 Mar 2026
Form 1File: Form 1 June 2025.pdf31 Oct 2025
Form 2File: Form 2 - Silverstone lonaville as on June 2025.pdf31 Oct 2025
Form 3File: Form 3 of Silverstone lonaville as on 30-06-2025.pdf31 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - June 2025 (Silverstone Lonaville).pdf31 Oct 2025
Certificates of CA (Form 3)File: Form 3 Jun.pdf29 Jul 2023
Disclosure of sold/ booked inventoryFile: Circular 29 24072023.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: organized (18)_compressed.pdf20 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: organized (11)_compressed.pdf20 Jul 2023
Certificates of CA (Form 3)File: organized (11)_compressed.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Silverstone Lonaville as on 30-06-2023 (1)_compressed.pdf10 Jul 2023
Declaration about Commencement CertificateFile: Format - D 2 1.pdf30 May 2023
Declaration about Commencement CertificateFile: Format - D 3 2.pdf30 May 2023
Declaration about Commencement CertificateFile: Format - D 1 3.pdf30 May 2023
Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-2020.pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-2021.pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-2022.pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A -P52100007543.pdf27 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5 7543 FY2018 19.pdf14 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Lakhani Panache Form5_Rera_7543_FY2019_20.pdf14 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Lakhani Panache Form5_Rera_7543_FY2020_21.pdf14 Oct 2021
Certificates of CA (Form 3)File: CA 30 06 21.pdf23 Sep 2021
Certificates of CA (Form 3)File: Plot 1 to 14_Sept-20 Panache_Signed_compressed.pdf4 Jul 2021
Certificates of CA (Form 3)File: Plot 1 to 14_Dec-20 Panache_Signed_compressed.pdf4 Jul 2021
Certificates of CA (Form 3)File: Panache CA certifivate June 20.pdf14 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf9 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf9 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf9 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf24 Dec 2018
Certificates of CA (Form 3)File: CA Certificate.pdf24 Dec 2018
Certificates of CA (Form 5)File: Form 5.pdf24 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf1 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Certificate.pdf1 Aug 2018
Certificates of CA (Form 3)File: CA Certificate.pdf1 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate.pdf2 May 2018
Certificates of CA (Form 3)File: CA Certificate.pdf2 May 2018
Building plan approvalFile: 15.pdf9 Mar 2018
Building Plan Approval (IOD)File: 15.pdf9 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Plot No 15.pdf9 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf9 Mar 2018
Certificates of CA (Form 3)File: CA Certificate.pdf9 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf1 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Project Engineer Cerificate - PANACHE.pdf1 Nov 2017
Certificates of CA (Form 3)File: CA Certificate.pdf1 Nov 2017
Layout approvalFile: PANACHE LAYOUT.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 03A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 03B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 04A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 4B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 05A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 5B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 6A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 6B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 07A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 07 B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 09.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 10.pdf29 Jul 2017
Building plan approvalFile: PLOT 11A B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 14.pdf29 Jul 2017
Building plan approvalFile: PLOT 01A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 1B.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 2A.pdf29 Jul 2017
Building plan approvalFile: PLOT NO 2B.pdf29 Jul 2017
PAN CardFile: LBPL Pan Card.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Jul 2017
Details of encumbrancesFile: Title Certificate.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: PANACHE LAYOUT.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLOT 01A.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLOT NO 1B.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLOT NO 2A.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLOT NO 2B.pdf29 Jul 2017
Building Plan Approval (IOD)File: PLOT NO 03A.pdf29 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
LAKHANI WHITE CASTLEPLOT NO 31 SEC 18 ULWE NAVI MUMBAI71CompletedFeb 2015Late, Feb 2015
LAKHANI BLUE WAVESPLOT NO 161 SEC 09 ULWE NAVI MUMBAI54CompletedJan 2014Late, Jan 2014

How this compares with Pune

24%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 53 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Silverstone Lonaville on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Varsoli13,700+ in Pune

2 kmSilverstone LonavilleCompleted 12Lapsed / revoked 6Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Silverstone Homemakers Pvt. Ltd

Silverstone Homemakers Pvt. Ltd has 1 registration on MahaRERA, including Silverstone Lonaville. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Silverstone Lonaville is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Silverstone Lonaville?

The registered promoter entity is Silverstone Homemakers Pvt. Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Silverstone Lonaville?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Silverstone Lonaville?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Silverstone Lonaville?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Silverstone Lonaville?

The professionals named in the filing: Architect: PARAKH ASSOCIATES ARCHITECTS AND INTERIOR DESIGNERS; Architect: M/S. HITEN SETHI ARCHITECTS; Architect: PB Associates; Engineer: MAHIMTURA CONSULTANTS PVT LTD.; Engineer: S K Consultants & Engineers; Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Silverstone Lonaville?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Silverstone Lonaville. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Silverstone Lonaville to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.