ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / SILVER OAK PHASE 1

Completed No litigation declared Others project

SILVER OAK PHASE 1

By BHASKAR RAMGONDA PATIL

RG-MH-09516 · RERA P53000001256 · Last updated on MahaRERA portal: 24 Nov 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
28 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SILVER OAK PHASE 1 is a Others project by BHASKAR RAMGONDA PATIL in Kolhapur, Maharashtra, registered with MahaRERA as P53000001256 on 27 Jul 2017. The registration is recorded completed; possession was promised by 27 Jun 2023.

At a glance

Project

  • NameSILVER OAK PHASE 1
  • TypeOthers
  • Location
    • Gadhinglaj
    • Kolhapur
    • 416502
  • Pincode416502
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000001256
  • ReraGenie IDRG-MH-09516

Builder

  • NameBHASKAR RAMGONDA PATIL
  • Entity typeIndividual
  • GSTIN27AHEPP3591Q1ZJ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredJul 2017PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion27 Jun 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARVATI COMPLEXNA70000
SILVER BUILDING NO2NA60000
SILVER OAK BUILDING NO3NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

PARVATI COMPLEX82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SILVER BUILDING NO282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SILVER OAK BUILDING NO391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes5%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered3
Open Space5
BuildingClosed/CoveredOpen SpaceTotal
PARVATI COMPLEX156
SILVER BUILDING NO2101
SILVER OAK BUILDING NO3101

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,808 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
ARUN LAXMAN TELANGGadhinglajKolhapur
VIJAY BABURAO TELANGGadhinglajKolhapur
VISHWANATH VIRBHADRAPPA PATTANSHETTIGadhinglajKolhapur

Approvals and building plan

Permissible FSI6058.71
Proposed, not sanctioned4,013 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTILAK PATH

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAHAS ARVIND PATIL
EngineerSUNIL ANNASAHEB DESAI
PartnerRole in project
BHASKAR RAMGONDA PATIL-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA SILVER OAK PHAE 1 C A 5 CERTIFICATE.pdf24 Nov 2021
Certificates of Architect (Form 4)File: Ar form 4 phase 1 Certificate.pdf17 Sep 2021
Building plan approvalFile: silver oak No 1 Complition Plan.pdf6 Apr 2021
Building plan approvalFile: Silver Oak 02 Plan.pdf6 Apr 2021
Building Plan Approval (IOD)File: silver oak No 1 Complition Plan.pdf6 Apr 2021
Building Plan Approval (IOD)File: Silver Oak 02 Plan.pdf6 Apr 2021
OtherFile: Silver Oak 01 Complition Certificate.pdf6 Apr 2021
OtherFile: Complition Certificate So 02.pdf6 Apr 2021
Form 2AFile: Silver Oak 02.pdf17 Jun 2019
Form 2AFile: SILVEROAK3.pdf17 Jun 2019
Certificates of Architect (Form 4)File: Sahas Patil Certificate 01 (1).pdf17 Jun 2019
Certificates of Architect (Form 4)File: Sahas Patil Certificate 01 (2).pdf17 Jun 2019
Certificates of Architect (Form 4)File: Certificate.pdf1 Feb 2019
Certificates of CA (Form 5)File: Account Statement.pdf31 Jan 2019
OtherFile: Ghoshanapatra.pdf29 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: silver oak.pdf31 Oct 2018
OtherFile: silver oak.pdf31 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: silver Oak.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sahas Patil.pdf30 Oct 2017
Details of encumbrancesFile: Morgage index 2nd project.pdf27 Oct 2017
Layout approvalFile: Layout Congcation.pdf24 Jul 2017
Details of encumbrancesFile: Loan Letter.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Congcation.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Building Parawana.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahas Patil.pdf24 Jul 2017
Certificates of CA (Form 3)File: Shelake Sir.pdf24 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg certi.pdf22 Jul 2017
Building plan approvalFile: parvati.pdf17 Jul 2017
Building plan approvalFile: Silver Oak.pdf17 Jul 2017
Building plan approvalFile: Silver.pdf17 Jul 2017
PAN CardFile: Pan Card.pdf17 Jul 2017
Copy of the legal title reportFile: Serach Report.pdf17 Jul 2017
Building Plan Approval (IOD)File: parvati.pdf17 Jul 2017
Building Plan Approval (IOD)File: Silver Oak.pdf17 Jul 2017
Building Plan Approval (IOD)File: Silver.pdf17 Jul 2017
Declaration in FORM BFile: Doc3.pdf17 Jul 2017
Proforma of Allotment letterFile: Turate.pdf17 Jul 2017

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
OM DATTA SHANTIAYODHYANAGAR1CompletedApr 2017Apr 2017
RAGHURAJ RESIDENCYSANKESHWAR ROAD1CompletedJan 2017Dec 2016
OMKAR PRIDE 1AMBARI GALLI GADHINGLAJ1CompletedJan 2017Dec 2016
ABHISHEK PLAZASAI MANDIR ROAD1CompletedJan 2017Late, Feb 2017
OM ABHISHEK RESIDENCYANAND COLONY1CompletedNov 2015Late, Dec 2015

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is completed

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep SILVER OAK PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gadhinglaj880+ in Kolhapur

2 kmSILVER OAK PHASE 1Completed 13Lapsed / revoked 6Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: BHASKAR RAMGONDA PATIL

BHASKAR RAMGONDA PATIL has 6 registrations on MahaRERA, including SILVER OAK PHASE 1 and KIRAN HEIGHTS. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if SILVER OAK PHASE 1 is delayed beyond 27 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SILVER OAK PHASE 1?

The registered promoter entity is BHASKAR RAMGONDA PATIL, an individual as per the filing. Its GSTIN 27AHEPP3591Q1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SILVER OAK PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SILVER OAK PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SILVER OAK PHASE 1?

The professionals named in the filing: Architect: SAHAS ARVIND PATIL; Engineer: SUNIL ANNASAHEB DESAI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SILVER OAK PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SILVER OAK PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SILVER OAK PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.