Home / Browse projects / Pune, Maharashtra / SILVER CRYSTAL

Registered No litigation declared Others project

SILVER CRYSTAL

By SILVER CRYSTAL

RG-MH-84035 · RERA P52100019161 · Last updated on MahaRERA portal: 21 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 41 months, 4 of them under MahaRERA's automatic 4-month extension
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2027Possession promisedmoved 41 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
70 of 118Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 183 documents Report an error

SILVER CRYSTAL is a Others project by SILVER CRYSTAL in Pune, Maharashtra, registered with MahaRERA as P52100019161 on 9 Jan 2019. Possession is promised by 14 May 2027. The completion date has moved by 41 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 48 of the 118 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameSILVER CRYSTAL
  • TypeOthers
  • Location
    • -
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • RERA no.P52100019161
  • ReraGenie IDRG-MH-84035

Builder

  • NameSILVER CRYSTAL
  • Entity typePartnership
  • PartnersKIRAN KISAN SAWANT, SOMNATH KANTILAL SASTE, HANUMANT PIRAJI JADHAV

Key dates

this monthRegisteredJan 2019First promiseDec 2023Revised toMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Jan 2019
  • Promised completion14 May 2027
  • Revised completionRevised to 14 May 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed183 files

Current status

41%48 of 118 units booked
104.6%Work done, per cost certificate

Figures as on 21 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SILVER CRYSTALNA15137741118

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

SILVER CRYSTAL: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 21 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed79

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots79
Closed/Covered61
Open Space18

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jun 2026
LandownerVillageDistrict
ASHOK VAMAN BARNEThergaonPune
JAYSING VAMAN BARNEThergaonPune
ARUN VAMAN BARNEThergaonPune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI4897.82
Proposed, not sanctioned2,398 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPIMPRI PUNE 411018
Estimated costRs 21.00 cr
Cost incurredRs 21.96 cr
Work done104.58%
BuildingWingEstimatedIncurred
SILVER CRYSTALNARs 18.00 crRs 13.76 cr
-NARs 3.00 crRs 8.20 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSIDDHARTH HARISHCHANDRAKAR
EngineerNILESH DIGHE
EngineerMAHADEV PARAJI ASWALE
Chartered AccountantNAVDEEP JINDAL
Chartered AccountantPrachi S Agarwal
Chartered AccountantSUSHANT SANJAY MAHEKAR
Chartered AccountantBogati & Co.
PartnerRole in project
SILVER CRYSTAL-

Extensions3

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jan 2027 → May 2027

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EXT52100017913Dec 2023 → Nov 2024

Reason as filed by the promoterDue To Covid 19

EA24072621859Dec 2023 → Jan 2027

Reason as filed by the promoterI was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 14 May 2027

Documents filed183

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 183 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf21 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf21 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf21 Oct 2026
Form 5 (FY 2025-2026)File: Silver Crystal (1) (1).pdf20 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2026
Form 2A (FY 2024-2025)File: F-2 A FY 24-25.pdf14 Oct 2026
Form 5 (FY 2024-2025)File: Silver Crystal (1) (1).pdf14 Oct 2026
Form 1File: FORM 01 MAR 25.pdf13 Oct 2026
Form 2File: Form 2 _mar 25.pdf13 Oct 2026
Form 3File: FORM 03 SILVER MAR 25.pdf13 Oct 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL MAR 25.pdf13 Oct 2026
Withdrawal Update Form 1File: FORM 01 JUN 25.pdf13 Oct 2026
Withdrawal Update Form 2File: Form 2 _Jun 25.pdf13 Oct 2026
Withdrawal Update Form 3File: FORM 03 SILVER JUNE 25.pdf13 Oct 2026
Form 2A (FY 2018-2019)File: F- 2 A Fy 18-19.pdf9 Oct 2026
Form 2A (FY 2019-2020)File: F- 2 A Fy 19-20.pdf9 Oct 2026
Form 2A (FY 2020-2021)File: F- 2 A Fy 20-21.pdf9 Oct 2026
Form 2A (FY 2021-2022)File: F- 2 A Fy 21-22.pdf9 Oct 2026
Form 2A (FY 2022-2023)File: F- 2 A Fy 22-23.pdf9 Oct 2026
Form 2A (FY 2023-2024)File: F-2 A FY 23-24.pdf9 Oct 2026
Form 2A (FY 2024-2025)File: F-2 A FY 24-25.pdf9 Oct 2026
Form 2A (FY 2025-2026)File: F-2 A FY 25-26.pdf9 Oct 2026
Form 5 (FY 2018-2019)File: FORM 05 2018-19.pdf10 Jul 2026
Form 5 (FY 2019-2020)File: FORM 05 2019-20.pdf10 Jul 2026
Form 5 (FY 2020-2021)File: FORM 05 2020-21.pdf10 Jul 2026
Form 5 (FY 2021-2022)File: FORM 05 2021-22.pdf10 Jul 2026
Form 5 (FY 2022-2023)File: FORM 05 2022-23.pdf10 Jul 2026
Form 5 (FY 2023-2024)File: FORM 05 2023-24.pdf10 Jul 2026
Form 1File: FORM 01 SEP 19.pdf9 Jul 2026
Form 2File: Form 2 Sep 19.pdf9 Jul 2026
Form 3File: FORM 03 SILVER SEPT 19.pdf9 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL SEP 19.pdf9 Jul 2026
Form 1File: FORM 01 DEC 19.pdf9 Jul 2026
Form 2File: Form 2 Dec 19.pdf9 Jul 2026
Form 3File: FORM 03 SILVER DEC 19.pdf9 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL DEC 19.pdf9 Jul 2026
Form 1File: FORM 01 MAR 20.pdf9 Jul 2026
Form 2File: Form 2 Mar 20.pdf9 Jul 2026
Form 3File: FORM 03 SILVER MAR 20.pdf9 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL MAR 20.pdf9 Jul 2026
Form 1File: FORM 01 MAR 19.pdf8 Jul 2026
Form 2File: Form 2 Mar 19.pdf8 Jul 2026
Form 3File: FORM 03 SILVER MAR 19.pdf8 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL MAR 19.pdf8 Jul 2026
Form 1File: FORM 01 JUN 19.pdf8 Jul 2026
Form 2File: Form 2 Jun 19.pdf8 Jul 2026
Form 3File: FORM 03 SILVER JUNE 19.pdf8 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL JUN 19.pdf8 Jul 2026
Form 1File: FORM 01 JUN 20.pdf8 Jul 2026
Form 2File: Form 2 Jun 20.pdf8 Jul 2026
Form 3File: FORM 03 SILVER JUNE 20.pdf8 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL JUN 20.pdf8 Jul 2026
Form 1File: FORM 01 SEP 20.pdf8 Jul 2026
Form 2File: Form 2 Sep 20.pdf8 Jul 2026
Form 3File: FORM 03 SILVER SEPT 20.pdf8 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL SEP 20.pdf8 Jul 2026
Form 1File: FORM 01 DEC 20.pdf8 Jul 2026
Form 2File: Form 2 Dec 20.pdf8 Jul 2026
Form 3File: FORM 03 SILVER DEC 20.pdf8 Jul 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE SILVER CRYSTAL DEC 20.pdf8 Jul 2026
Form 1File: FORM 01 MAR 21.pdf8 Jul 2026
Form 2File: Form 2 Mar 21.pdf8 Jul 2026
Form 3File: FORM 03 SILVER MAR 21.pdf8 Jul 2026

How this compares with Pune

41%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 41 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SILVER CRYSTAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -14,000+ in Pune

Builder: SILVER CRYSTAL

SILVER CRYSTAL has 1 registration on MahaRERA, including SILVER CRYSTAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SILVER CRYSTAL is delayed beyond 14 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SILVER CRYSTAL?

The registered promoter entity is SILVER CRYSTAL, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SILVER CRYSTAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SILVER CRYSTAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SILVER CRYSTAL?

The professionals named in the filing: Architect: SIDDHARTH HARISHCHANDRAKAR; Engineer: NILESH DIGHE; Engineer: MAHADEV PARAJI ASWALE; Chartered Accountant: NAVDEEP JINDAL; Chartered Accountant: Prachi S Agarwal; Chartered Accountant: SUSHANT SANJAY MAHEKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SILVER CRYSTAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SILVER CRYSTAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SILVER CRYSTAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.