Home / Browse projects / Pune, Maharashtra / Signature Tower II
Signature Tower II
By Summit Property Ventures LLP
RG-MH-04936 · RERA P52100021118 · Last updated on MahaRERA portal: 8 Mar 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 37 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Signature Tower II is a Residential / Group Housing project by Summit Property Ventures LLP in Pune, Maharashtra, registered with MahaRERA as P52100021118 on 31 May 2019. Possession was promised by 30 Sep 2023 and is now 37 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSignature Tower II
- TypeResidential / Group Housing
- Location
- Model Colony
- Shivajinagar
- Pune (M Corp.)
- Pune City
- Pune
- 411016
- Pincode411016
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100021118
- ReraGenie IDRG-MH-04936
Builder
- NameSummit Property Ventures LLP
- Entity typeOthers
- Named personsVijaykumar Janardhan Mundhe, Abhijeet Vasant Shende, Yogesh Ramesh Shende
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 May 2019
- Promised completion30 Sep 2023
- Revised completionRevised to 30 Sep 2023 (originally 30 Sep 2022)
- Buildings1 building record
- Documents filed63 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Signature Tower II | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.
Signature Tower II: 65% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 8 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed6
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| UMA Co-operative Housing Society Ltd | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Advantage Architect |
| Architect | Siddharth Harishchandrakar |
| Engineer | Vishal Khopkar |
| Chartered Accountant | CA Saransh Dey |
| Partner | Role in project |
|---|---|
| Summit Property Ventures LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Non availability of labour and construction raw materials such as cement and sand, Due to torrential monsoon rainfall, the water was accumulated on the project site resulting the ground on site turned into mud which made construction difficult at site of the project. The amount of work has been increased due to rainfall, The Cement bags on site got drenched in the rainwater, Limited access to the road to the construction site due to potholes & accumulated water caused due to heavy rainfall, resulting into the transportation of building material to the site is difficult, The quarters/she
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed63
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 20240308130930.pdf | 8 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Jun 23_Signature Tower II.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_M23_ST2_compressed.pdf | 2 May 2023 |
| Certificates of CA (Form 3)File: Form 03 Signature Tower II.pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_March23_Signature Tower2.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A_M23_ST2.pdf | 17 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No2 Signature Tower2_Dec22.pdf | 11 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No3 Signature Tower2_Dec22.pdf | 2 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 22_Signature Tower II.pdf | 2 Feb 2023 |
| Certificates of CA (Form 3)File: Form No3 Signature Tower2_Dec22.pdf | 2 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Discloser of Sold_Unsold_ST2_June22.pdf | 21 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Discloser of Sold_Unsold_ST2_Sept22.pdf | 21 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5_SignatureII_March19_compressed.pdf | 21 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5_SignatureII_March20_compressed.pdf | 21 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_SignatureII_March21_compressed.pdf | 21 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5_SignatureII_March22_compressed.pdf | 21 Nov 2022 |
| Certificates of CA (Form 3)File: Form3_ST2_June22_compressed.pdf | 14 Nov 2022 |
| Certificates of CA (Form 3)File: Form No3 Signature Tower2_Sept22_compressed.pdf | 14 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Mar 22 Signature Tower II registration_Q cert.pdf | 10 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Jun 22_Signature Tower II.pdf | 22 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No1 Signature Tower2_Sept22_compressed.pdf | 22 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No2 Signature Tower2_Sept22_compressed.pdf | 22 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_ST2_June22_compressed.pdf | 19 Aug 2022 |
| Certificates of CA (Form 3)File: Form No3 Signature Tower lI_March22_C.pdf | 18 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signature Tower II.pdf | 28 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 22Signature Tower II registration_e cert.pdf | 28 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Mar 22 Signature Tower II registration_Q cert.pdf | 28 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 21 Signature II Ar Certificate.pdf | 31 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 21 Signature II Engg Certificate.pdf | 31 Jan 2022 |
| Certificates of CA (Form 3)File: Form 3_Signature tower II_Sep21 Rera Certifiacte.pdf | 3 Nov 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signature-II Ar Certificate_Sept.pdf | 12 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signature-II Ar Certificate_Sept.pdf | 12 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIGNATURE-II_FORM 2.pdf | 12 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SIGNATURE-II _FORM 2A.pdf | 12 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Signature-II_Discloser of Sold Unsold.pdf | 12 Oct 2021 |
| Declaration about Commencement CertificateFile: Signature -II.pdf | 18 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Signature-II.pdf | 18 Aug 2021 |
| Layout approvalFile: 01-02 - Layout (1).pdf | 15 Aug 2021 |
| Building plan approvalFile: 02-02.pdf | 15 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: 01-02 - Layout (1).pdf | 15 Aug 2021 |
| Building Plan Approval (IOD)File: 02-02.pdf | 15 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate - 02112020.pdf | 15 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SIGNATURE ARECHITECT CERTIFICATE FORM 1.pdf | 15 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIGNATURE ENGINEER CERTIFICATE FORM 2.pdf | 15 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SIGNATURE QUALITY CERTIFICATE FORM 21.pdf | 15 Aug 2021 |
| Certificates of CA (Form 3)File: Signature Tower II CA Form 3.pdf | 15 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Cer Signature Tower II.pdf | 26 Jul 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Signature Tower II.pdf | 26 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Signature Tower II Form 2A.pdf | 26 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signature Tower II-min.pdf | 9 Feb 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signature Tower2.pdf | 9 Feb 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Signature Tower 2.pdf | 9 Feb 2021 |
| Copy of the legal title reportFile: title_compressed.pdf | 29 May 2019 |
| Building plan approvalFile: building plan.pdf | 14 May 2019 |
| Layout approvalFile: Layout.pdf | 14 May 2019 |
| Details of encumbrancesFile: No Encumbrance CERTIFICATE.pdf | 14 May 2019 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 14 May 2019 |
| Building Plan Approval (IOD)File: building plan.pdf | 14 May 2019 |
| Declaration in FORM BFile: Summit Properties Form B_compressed.pdf | 14 May 2019 |
| Certificates of CA (Form 3)File: C A Letter - Uma Soc.pdf | 14 May 2019 |
| Proforma of Allotment letterFile: Affidavit For Undertaking - Letter.pdf | 14 May 2019 |
| PAN CardFile: Summit Property Ventures LLP - Pan Card.pdf | 6 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate _compressed.pdf | 6 May 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 63 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Signature Tower II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shivajinagar13,700+ in Pune
Filed coordinates, straight-line distance. 131 registered projects within 2 km.
KUSUM CO. OPERATIVE HOUSING SOCIETY LIMITED
M/S FORTUNE DEVELOPERS
VB FOREST CASTLE BY ASCENT LANDMARKS
ASCENT LANDMARKS LLP
TEJ MAYURBAN
TEJRAJ PROFILE INFRA LLP
The Luxe Towers - Building I and J
Neelsidhi Mohar Raisoni Developers LLP
TEJ MIDTOWN
TEJRAJ GANPATRAO PATIL
Bellagio Courtyards
MICHELNGELO LLP
Builder: Summit Property Ventures LLP
Summit Property Ventures LLP has 2 registrations on MahaRERA, including Signature Tower II and TEJ ONE MODEL COLONY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Signature Tower II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Signature Tower II is delayed beyond 30 Sep 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Signature Tower II?
The registered promoter entity is Summit Property Ventures LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Signature Tower II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Signature Tower II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Signature Tower II?
The professionals named in the filing: Architect: Advantage Architect; Architect: Siddharth Harishchandrakar; Engineer: Vishal Khopkar; Chartered Accountant: CA Saransh Dey. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Signature Tower II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback