ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Sidhivinayak Orchid

Registered No litigation declared Mixed project

Sidhivinayak Orchid

By Sidhivinayak Developers

RG-MH-05562 · RERA P51800052348 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
4 of 11Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 50%
1 of 1Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

Sidhivinayak Orchid is a Mixed project by Sidhivinayak Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800052348 on 14 Aug 2023. Possession is promised by 31 Dec 2026. 0 of the 1 unit on this registration is recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSidhivinayak Orchid
  • TypeMixed
  • Location
    • Pantnagar
    • Ghatkopar East
    • Ghatkopar
    • Kurla
    • Mumbai Suburban
    • 400075
  • Pincode400075
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800052348
  • ReraGenie IDRG-MH-05562

Builder

  • NameSidhivinayak Developers
  • Entity typePartnership
  • GSTIN27ADAFS0217Q1ZW
  • PartnersHarshit Haresh Parekh, Pravin Panchabhai Patel, Bhupendra Shantilal Kapasi, Teja Kesha Ravariya
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredAug 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed64 files

Current status

0%0 of 1 units booked

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg No 59NA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

Bldg No 5941%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities16

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Fitness CenterYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area839 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Declared on4 Oct 2024
LandownerVillageDistrict
Pant Nagar Sangam Chs LtdGhatkoparMumbai Suburban

Approvals and building plan

Sanctioning authorityBuilding Permission Cell Greated Mumbai/ MAHADA
Permissible FSI5606.73
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVashi, Navi Mumbai

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpace Design
EngineerA G Gokhale & Associates
Chartered AccountantR B Singh & Associates
Chartered AccountantSachin K. Mishra & Co.
PartnerRole in project
Sidhivinayak Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 59 Form 1-30-6-25.pdf24 Apr 2026
Form 2File: 59 Form 2 -30-6-25.pdf24 Apr 2026
Form 3File: 59 Form 3-30-6-25.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: 59 Disclosure letter 30-6-25.pdf24 Apr 2026
Form 1File: 59 Form 1-30-9-25.pdf24 Apr 2026
Form 2File: 59 form 2-30-9-25.pdf24 Apr 2026
Form 3File: 59 form-3 30-9-25.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: 59 Disclosure Letter 30-9-25.pdf24 Apr 2026
Form 1File: 59- form 1-31-12-25.pdf24 Apr 2026
Form 2File: 59 Form 2-31-12-25.pdf24 Apr 2026
Form 3File: 59 Form-3 31-12-2025.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: 59 Disclosure 31-12-25.pdf24 Apr 2026
Form 1File: 59 Form 1 -31-3-26.pdf24 Apr 2026
Form 2File: 59 Form 2-31-3-26.pdf24 Apr 2026
Form 3File: Form 3 ..pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: 59 Disclosure 31-3-26.pdf24 Apr 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 59 Form 1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 59 Form 3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 59 form 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: 59-Disclosure Letter.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 59 Form 1.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 59 Form 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: 59-Disclosure Letter _singed.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: 59 Disclosure Letter.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSER OF SOLD FLAT.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Sep 24.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Sep 24.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Sep 24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- FY 23-24.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 59 Form1 -30-6-24.pdf8 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf8 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SD 59 - Form 1 -30-9-23_Q2.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SD 59 Form 1-31-12-23_Q3.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SD 59 form 1 -31-3-24_Q4.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SD 59 Form 2 _30-9-23.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SD 59 Form 2__ 31-12-23_Q3_.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SD 59 Form 2 _31-3-24.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SD 59 Form 3 _30-9-23_.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SD 59 Form 3 -31-12-23_.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SD 59 Form 3 _31-3-24_.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3 Sidhivinayak Developers.pdf18 Jul 2023
Building plan approval or NA orderFile: IOD_REVISED.pdf14 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD_REVISED.pdf14 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: All partners Annexure A.pdf14 Jul 2023
CERSAI detailsFile: 59 CERSAI Declaration.pdf8 Jul 2023
Layout approvalFile: Bldg Layout.pdf7 Jul 2023
Copy of Layout Approval (in case of layout)File: Bldg Layout.pdf7 Jul 2023
Copy of the legal title reportFile: Title Reoprt _riviesd_compressed.pdf30 Jun 2023
Details of encumbrances concerned to FinanceFile: 59-No Financial Encumbrance-29-05-2023 (1).pdf27 Jun 2023
Details of encumbrances concerned to LegalFile: 59-No Financial Encumbrance-29-05-2023 (1).pdf27 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 59-Format-A (2).pdf30 May 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER_PDF.pdf25 May 2023
Deviation Report with respect to Allotment letterFile: 59 Deviation allotment sheet.pdf24 May 2023
Deviation Report with respect to model copy of AgreementFile: 59 Deviation- Agreement sheet_compressed.pdf24 May 2023
Proforma of Agreement for saleFile: Agreement for sale_Rera Modal.pdf16 May 2023
Declaration about Commencement CertificateFile: Declaration CC.pdf4 May 2023
Declaration in FORM BFile: Form B- Promoter.pdf4 May 2023
Details of encumbrances concerned to FinanceFile: 59 Encumbrance certificate (1).pdf3 May 2023
Details of encumbrances concerned to LegalFile: 59 Encumbrance certificate (1).pdf3 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC 59.pdf29 Apr 2023
PAN CardFile: Siddhivinayak Orchid Pan Card.pdf28 Apr 2023

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sidhivinayak Orchid on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopar East6,700+ in Mumbai Suburban

2 kmSidhivinayak OrchidCompleted 132Lapsed / revoked 100Other 124Dot size: filed unitsN

Filed coordinates, straight-line distance. 356 registered projects within 2 km.

Builder: Sidhivinayak Developers

SIDHIVINAYAK DEVELOPERS has 2 registrations on MahaRERA, including MATOSHRI APARTMENT and Sidhivinayak Orchid. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sidhivinayak Orchid is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sidhivinayak Orchid?

The registered promoter entity is Sidhivinayak Developers, a partnership as per the filing. Its GSTIN 27ADAFS0217Q1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sidhivinayak Orchid?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sidhivinayak Orchid?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sidhivinayak Orchid?

The professionals named in the filing: Architect: Space Design; Engineer: A G Gokhale & Associates; Chartered Accountant: R B Singh & Associates; Chartered Accountant: Sachin K. Mishra & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sidhivinayak Orchid?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sidhivinayak Orchid. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sidhivinayak Orchid to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.