ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SIDDHIVINAYAK PRIDE

Completed No litigation declared Residential / Group Housing project

SIDDHIVINAYAK PRIDE

By SAGAR DILIP RUKARI

RG-MH-09312 · RERA P52100000491 · Last updated on MahaRERA portal: 15 May 2018

Source: official MahaRERA filing

Red flags

  • Completion date moved by 2 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2018Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

SIDDHIVINAYAK PRIDE is a Residential / Group Housing project by SAGAR DILIP RUKARI in Pune, Maharashtra, registered with MahaRERA as P52100000491 on 18 Jul 2017. The registration is recorded completed; possession was promised by 1 Feb 2018. The completion date has moved by 2 months from the original filing.

At a glance

Project

  • NameSIDDHIVINAYAK PRIDE
  • TypeResidential / Group Housing
  • Location
    • MANJARI Bk
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000491
  • ReraGenie IDRG-MH-09312

Builder

  • NameSAGAR DILIP RUKARI
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017First promiseDec 2017Revised toFeb 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Jul 2017
  • Promised completion1 Feb 2018
  • Revised completionRevised to 1 Feb 2018 (originally 31 Dec 2017)
  • Buildings1 building record
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIDDHIVINAYAK PRIDENA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 May 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

SIDDHIVINAYAK PRIDE: 84% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 15 May 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes60%
Open ParkingYes60%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered8

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,401 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4090.17
Proposed, not sanctioned3,288 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAGARPATTA CITY HADAPSAR PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTOSH RASKAR
EngineerSHISHIR DHAWADE
PartnerRole in project
SAGAR DILIP RUKARI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000025Dec 2017 → Feb 2018

Reason as filed by the promoterRespected Sir, Due to new tax reform introduced by Government of India in the name of GST on 1 July 2018 , We had unable to purchase material from our vendors in the month of July & August due to initial confusion of new GST tax. After many clarifications & notification by finance department trade had started working smoothly in first week of September, Even our National GDP had reduced with negative growth of 3 % in said period. Due to above tax reform our Project had delayed by two months. However we had completed the Building construction in all respect.& now we have submitted application f

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 4)File: santosh raskar.pdf15 May 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Nondni prmanpatra.pdf15 May 2018
OtherFile: bhogavta prmnpatra.pdf15 May 2018
Building plan approvalFile: 5 - 5.pdf15 Jul 2017
Building plan approvalFile: 4 - 5.PDF15 Jul 2017
Layout approvalFile: 1 - 5.PDF15 Jul 2017
Building plan approvalFile: 1 - 5.PDF15 Jul 2017
Building plan approvalFile: 2 - 5.PDF15 Jul 2017
Building plan approvalFile: 3 - 5.pdf15 Jul 2017
PAN CardFile: PAN Card.pdf15 Jul 2017
Copy of the legal title reportFile: Search Title Report Reduce.pdf15 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: 1 - 5.PDF15 Jul 2017
Building Plan Approval (IOD)File: 1 - 5.PDF15 Jul 2017
Building Plan Approval (IOD)File: 2 - 5.PDF15 Jul 2017
Building Plan Approval (IOD)File: 3 - 5.pdf15 Jul 2017
Building Plan Approval (IOD)File: 4 - 5.PDF15 Jul 2017
Building Plan Approval (IOD)File: 5 - 5.pdf15 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NA Order Reduce.pdf15 Jul 2017
Declaration in FORM BFile: Pride Form B.pdf15 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: santosh raskar New.pdf15 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Pride Certificate.pdf15 Jul 2017
Certificates of CA (Form 3)File: Shah Sir Doc.pdf15 Jul 2017
Proforma of Allotment letterFile: Agreement Draft pride.pdf15 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
AVISHKARS NO 177 34 FURSUNGI TAL HAVELI DIST PUNE40CompletedJan 2016Late, Sep 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 2 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHIVINAYAK PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MANJARI Bk13,700+ in Pune

2 kmSIDDHIVINAYAK PRIDECompleted 5Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: SAGAR DILIP RUKARI

SAGAR DILIP RUKARI has 1 registration on MahaRERA, including SIDDHIVINAYAK PRIDE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SIDDHIVINAYAK PRIDE is delayed beyond 1 Feb 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHIVINAYAK PRIDE?

The registered promoter entity is SAGAR DILIP RUKARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHIVINAYAK PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SIDDHIVINAYAK PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHIVINAYAK PRIDE?

The professionals named in the filing: Architect: SANTOSH RASKAR; Engineer: SHISHIR DHAWADE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHIVINAYAK PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHIVINAYAK PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHIVINAYAK PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.