Red flags

  • 24 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
75 of 110Construction stages doneacross 10 buildings; furthest along: Slabs of Super Structure, 12%
24Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

SIDDHICITY PHASE-V is a Residential / Group Housing project by Siddhitech Homes Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700001928 on 29 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 24 complaints are on record with the regulator.

At a glance

Project

  • NameSIDDHICITY PHASE-V
  • TypeResidential / Group Housing
  • Location
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001928
  • ReraGenie IDRG-MH-20700

Builder

  • NameSiddhitech Homes Private Limited
  • Entity typeCompany
  • Managing DirectorHemant Mohan Agrawal
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings10 building records
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
16 As per Approved plan Bldg No 1NA90000
17 As per Approved plan Bldg No 2NA90000
18 As per Approved plan Bldg No 3NA90000
19 As per Approved plan Bldg No 4NA90000
20 As per Approved plan Bldg No 5NA90000
21 As per Approved plan Bldg No 6NA90000
22 As per Approved plan Bldg No 7NA90000
23 As per Approved plan Bldg No 8NA90000
14 As per Approved plan Bldg No 9NA90000
15 As per Approved plan Bldg No 10NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 21 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

75 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Slabs of Super Structure, at 12%.

16 As per Approved plan Bldg No 137%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure12%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
17 As per Approved plan Bldg No 237%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure12%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
18 As per Approved plan Bldg No 337%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure12%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
19 As per Approved plan Bldg No 427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
20 As per Approved plan Bldg No 591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
21 As per Approved plan Bldg No 691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
22 As per Approved plan Bldg No 791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
23 As per Approved plan Bldg No 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
14 As per Approved plan Bldg No 991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
15 As per Approved plan Bldg No 1091%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,192 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PREMAL CHANDRAKANT DESAIAndheriMumbai Suburban

Approvals and building plan

Permissible FSI9420.2
Proposed, not sanctioned9,420 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 797 Casa Maria Building Gokhale Road Dadar West Mumbai 400028

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectURBAN VASTU DESIGNER
PartnerRole in project
Siddhitech Homes Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700005089Dec 2019 → Dec 2020

Reason as filed by the promoteras per the stop work notice issued by the KBMC (approving authority) dated 16/05/2015., Construction of the Building no.16,17,18 and 19 , as per approve plan building no-1,2,3 and 4 was stopped

Litigation declared5

CaseCourtStatus
147/2015/2015Civil Court Junior Division UlhasnagarPending
ARB/JN/RFL/128/2017/2017Arbitrationagainst us gone in appeal in delhi high court
147/2015/2015Civil Court Junior Division UlhasnagarPending
RFL/MORTGAGE/L-1/306 of 2016/0ArbitrationDischarged
Complaint no 105 of 2017/2017District Consumer Dispute Redressal ForumPending

Complaints filed with MahaRERA24

Case no.ComplainantRespondentFiled
CC006000000001096Ajay NairHemant Mohan Agrawal05/10/2017
CC006000000068152Eknath Krishna DeshmukhM/S Siddhitech Homes PVT LTD19/02/2019
CC006000000078203Jayadevan Pillai K RM/s Siddhitech Homes Private Limited22/02/2019
CC006000000078205Jay Ramchandra JangamM/s Siddhitech Homes Private Limited22/02/2019
CC006000000078208VISHAL CHANDRAKANT TAMBEM/s Siddhitech Homes Private Limited22/02/2019
CC006000000078212Achari Subhalatha SathyanM/s Siddhitech Homes Private Limited22/02/2019
CC006000000078215KATHIRESH SATHYAN ACHARYM/s SIDDHITECH HOMES PRIVATE LIMITED22/02/2019
CC006000000078216SHALINI RAMESH KAMBLEM/s SIDDHITECH HOMES PRIVATE LIMITED22/02/2019
CC006000000078217RAVINDRAN V GANGADHARANM/s SIDDHITECH HOMES PRIVATE LIMITED22/02/2019
CC006000000078218SOKESH SIVALINGAM NADARM/S SIDDHITECH HOMES PRIVATE LIMITED22/02/2019
CC006000000078219BALU GORAKH BHITADEM/S SIDDHITECH HOMES PRIVATE LIMITED22/02/2019
CC006000000182110Ajay NairSiddhitech Homes Pvt Ltd13/01/2020
CC006000000199081Mr Ajeet Singh HindujaM/s Siddhitech Homes Pvt Ltd23/11/2021
CC006000000199206Mrs Muskan Kaur HindujaM/s Siddhitech Homes Pvt Ltd30/11/2021
CC006000000303184Rajendrakumar Krishankumar KalraSIDDHITECH HOMES PVT.LTD. & ORS.31/10/2022
CC006000000395534KRUPA SAMIR KAPADIASIDDHITECH HOMES PVT. LTD04/05/2023
CC006000000591043MOHAMMED TAHIR SAYEDHemant Mohan Agarwal17/07/2024
CC006000000591202ROSHAN JAHAN MOHD. TAHIR SAYEDHEMANT MOHAN AGARWAL17/07/2024
CC12604068MOHAMMED TAHIR SAYEEDSiddhitech Homes Private Limited30/06/2026
CC12604080MOHAMMED TAHIR SAYEEDSiddhitech Homes Private Limited30/06/2026
CC12604083MOHAMMED TAHIR SAYEEDSiddhitech Homes Private Limited30/06/2026
CC12604086MOHAMMED TAHIR SAYEEDSiddhitech Homes Private Limited30/06/2026
CC12604091ROSHAN JAHAN MOHD. TAHIR SAYEDSiddhitech Homes Private Limited30/06/2026
CC12604090ROSHAN JAHAN MOHD. TAHIR SAYEDSiddhitech Homes Private Limited30/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: STY REGISTRATION CERTIFICATE PHASE V.pdf21 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: shpl form 5 fy 2018-19signed.pdf17 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: SHPL Form 5 FY 17-18signed.pdf19 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch cert 10122019compressed.pdf18 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng cert 310318.pdf17 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng cert 310319.pdf17 Dec 2019
Certificates of Architect (Form 4)File: form 4 bldg no2220191212_13260107.pdf12 Dec 2019
Certificates of Architect (Form 4)File: form no4 bldg 23 20191212_13263667.pdf12 Dec 2019
Certificates of Architect (Form 4)File: form no4 bldg 1420191212_13273042.pdf12 Dec 2019
Certificates of Architect (Form 4)File: form no4 bldg 1520191212_13283897.pdf12 Dec 2019
Certificates of Architect (Form 4)File: form no4 bldg 2020191212_13280945.pdf12 Dec 2019
OtherFile: bldg no-9(15)of phase v pwd licence20191106_10450992.pdf6 Nov 2019
OtherFile: bldg no-10phasevpwd licence20191106_10474370.pdf6 Nov 2019
OtherFile: Stability Certificate buld no 3.pdf4 Nov 2019
OtherFile: Stabilty Certificate 14-23_compressed.pdf4 Nov 2019
OtherFile: Stabilty Certificate 14-23_compressed.pdf4 Nov 2019
OtherFile: Stabilty Certificate 14-23_compressed.pdf4 Nov 2019
Certificates of Architect (Form 4)File: form no-4-b-n-21.pdf16 Jul 2019
OtherFile: 23012017.pdf12 Mar 2019
OtherFile: court commisnner application.pdf12 Mar 2019
OtherFile: court order 13022017.pdf12 Mar 2019
OtherFile: stay order for construction16052015.pdf12 Mar 2019
OtherFile: stay order07092015.pdf12 Mar 2019
OtherFile: courtorder 01062015.pdf12 Mar 2019
Proforma of Allotment letterFile: Siddhicity Phase V Agreement As Per RERA - Draft Copy.pdf9 Sep 2017
Details of encumbrancesFile: Details of Encumbrance -Phase-V.pdf26 Jul 2017
Declaration in FORM BFile: form B affidavit1.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert-Phase-V.pdf26 Jul 2017
Certificates of CA (Form 3)File: CA certificate Phase V.pdf26 Jul 2017
Proforma of Allotment letterFile: Allotment Letter-Phase-V.pdf26 Jul 2017
OtherFile: DEVELOPMENT AGREEMENT WITH FOUR OTHERS PHASE V.pdf26 Jul 2017
OtherFile: DEVLOPMENT AGREEMENT WITH PREMAL PHASE V.pdf26 Jul 2017
Layout approvalFile: Scan-3.pdf25 Jul 2017
Building plan approvalFile: CC COPY.pdf25 Jul 2017
Layout approvalFile: Scan-1.pdf25 Jul 2017
Layout approvalFile: Scan-2.pdf25 Jul 2017
PAN CardFile: Siddhitech Homes Pvt ltd - PAN.pdf25 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: Scan-3.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: Scan-1.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: Scan-2.pdf25 Jul 2017
Building Plan Approval (IOD)File: CC COPY.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certi-Phase-V.pdf25 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Siddhi City D to MBadlapur East252CompletedOct 2013Late, Dec 2013
Siddhi City Morning Star C wingBadlapur East45CompletedFeb 2012Late, Apr 2012

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHICITY PHASE-V on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur (M Cl)7,600+ in Thane

2 kmSIDDHICITY PHASE-VCompleted 53Lapsed / revoked 14Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 97 registered projects within 2 km.

Builder: Siddhitech Homes Private Limited

Siddhitech Homes Private Limited has 2 registrations on MahaRERA, including SIDDHICITY and SIDDHICITY PHASE-V. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SIDDHICITY PHASE-V is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHICITY PHASE-V?

The registered promoter entity is Siddhitech Homes Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHICITY PHASE-V?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIDDHICITY PHASE-V?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SIDDHICITY PHASE-V?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHICITY PHASE-V?

The professionals named in the filing: Architect: URBAN VASTU DESIGNER. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHICITY PHASE-V?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHICITY PHASE-V. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHICITY PHASE-V to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.