RG-MH-78800 · RERA P52100047124 · Last updated on MahaRERA portal: 25 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 75%
45 of 110Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 228 documents Report an error

SHYNI GOLD MANGALAM is a Others project by SHYNI GOLD MANGALAM LLP in Pune, Maharashtra, registered with MahaRERA as P52100047124 on 10 Oct 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 12 months from the original filing. 65 of the 110 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHYNI GOLD MANGALAM
  • TypeOthers
  • Location
    • WALHEKARWADI ROAD
    • WALHEKARWADI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047124
  • ReraGenie IDRG-MH-78800

Builder

  • NameSHYNI GOLD MANGALAM LLP
  • Entity typeCompany
  • CINN11111SK2024SKI242424
  • GSTIN27CAHPK3279C1ZP
  • Managing DirectorKUNJUMON BABY BABY

Key dates

this monthRegisteredOct 2022First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Oct 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed228 files

Current status

59%65 of 110 units booked
35.5%Work done, per cost certificate

Figures as on 25 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHYNI GOLD WING ANA200351550
SHYNI GOLD WING BNA200491160

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

SHYNI GOLD WING A48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SHYNI GOLD WING B48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed154

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots154
Closed/Covered2
Open Space152
BuildingClosed/CoveredOpen SpaceTotal
SHYNI GOLD WING A16364
SHYNI GOLD WING B18990

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024
LandownerVillageDistrict
SHINY KUNJUMONSomatanePune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Muncipal Corporation
Permissible FSI25675.0
Proposed, not sanctioned16,606 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchK8 to K13 Old Mumbai Pune Highway Empire Estate Phase1 Pimpri Colony Pimpri Chinchwad Maharashtra 411019
Estimated costRs 90.83 cr
Cost incurredRs 32.20 cr
Work done35.45%
BuildingWingEstimatedIncurred
SHYNI GOLD WING BNARs 45.03 crRs 15.96 cr
SHYNI GOLD WING ANARs 40.48 crRs 14.35 cr
-NARs 5.32 crRs 1.89 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSachin Barwade
ArchitectARISE
EngineerRahul Ramesh Kapase
EngineerVAIBHAV GAIKWAD
Chartered AccountantMaheshwar Marathe
Chartered AccountantSapana Abhilash Savalsure
Chartered AccountantAMRUTA SHINDE AND ASSOCIATES CHARTERED ACCOUNTANTS
Chartered AccountantCA Vikas Khadasare
Chartered AccountantNavdeep Jindal And Associates
PartnerRole in project
SHYNI GOLD MANGALAM LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07072621682Dec 2026 → Dec 2027

Reason as filed by the promoterThe ongoing geopolitical conflict in the West Asia region has significantly disrupted international shipping routes and logistics, resulting in delays in the availability and procurement of essential construction materials. Domestic manufacturing units, particularly ceramic and tile manufacturers in Morbi, Gujarat, have also experienced production and supply constraints, thereby affecting the timely execution of finishing works. The construction industry has witnessed an unprecedented increase in the prices of key construction materials. Steel prices have increased by approximately 12-18%, cem

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed228

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 228 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Shyni Gold From-1.pdf25 Jul 2026
Withdrawal Update Form 2File: Form 2 Jun_26 (1).pdf25 Jul 2026
Withdrawal Update Form 3File: Form 3 Shyni Gold Jun_26 Signed compressed.pdf25 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A_FY_2024-25.pdf7 Jul 2026
Withdrawal Update Form 1File: Form 1 Arch Certificate Shyni Gold Mangalam Upto march 2026.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Shyni Gold Mangalam upto march 2026.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 shyni gold mangalam upto march 2026.pdf24 Apr 2026
Commencement certificateFile: CC 030925.pdf24 Jan 2026
Layout approvalFile: 1_compressed.pdf24 Jan 2026
Building plan approvalFile: 2_compressed.pdf24 Jan 2026
Building plan approvalFile: 3_compressed.pdf24 Jan 2026
Building plan approvalFile: 4_compressed.pdf24 Jan 2026
Building plan approvalFile: 5_compressed.pdf24 Jan 2026
Building plan approvalFile: 6_compressed.pdf24 Jan 2026
Building plan approvalFile: 7_compressed.pdf24 Jan 2026
Building plan approvalFile: 8_compressed.pdf24 Jan 2026
Building plan approvalFile: 9_compressed.pdf24 Jan 2026
Building plan approvalFile: 10_compressed.pdf24 Jan 2026
Building plan approvalFile: 11_compressed.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1 Shyni Gold upto Dec 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Shyni Gold mangalam upto dec 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: Shyni Gold Form 3 upto dec 2025compressed.pdf24 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 24to25 shyni.pdf19 Jan 2026
Form 5 (FY 2022-2023)File: Form 5 (2022 TO 2023).pdf17 Jan 2026
Form 5 (FY 2023-2024)File: Form 5 (2023 TO 2024).pdf17 Jan 2026
Withdrawal Update Form 1File: Shyni Arch Cert_0001.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 Engg Cert Shyni.pdf18 Oct 2025
Withdrawal Update Form 3File: Form -3 as on 30092025 - Shyni Gold_compressed (1).pdf18 Oct 2025
Form 1File: Form 1 upto June 25.pdf18 Jul 2025
Form 2File: Form 2 Engg Certificate.pdf18 Jul 2025
Form 3File: Form 3 upto 30 June.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 17-07-2025_0001.pdf18 Jul 2025
Form 1File: Form 1 upto mar 2025.pdf26 Jun 2025
Form 2File: march 2025 Form 2 Engineers certificate Shyni Gold Mangalam.pdf26 Jun 2025
Form 3File: Shyni Gold Mangalam LLP Form 3_compressed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: March 2025 Disclosure of sold and unsold inventory Shyni.pdf26 Jun 2025
Form 3File: Form 3 shyni gold mangalam Dec 2024compressed.pdf26 Jun 2025
Form 2File: Scan Form 2 Engineers certificate Shyni Gold Mangalam.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: scan Dec 2024 Disclosure of sold and unsold inventory Shyni.pdf26 Jun 2025
Form 1File: Form 1 upto dec 2024.pdf26 Jun 2025
Form 2File: 1 Engineers Certificate Dec 22.pdf26 Jun 2025
Form 1File: 1ArCertificate Upto 31stDEC2022age0001.pdf26 Jun 2025
Form 3File: 31 Dec 2022 Form 3.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1 DOSU DEC 2022 compressed.pdf26 Jun 2025
Form 1File: 2ArCertificate upto 31st Mar 2023.pdf26 Jun 2025
Form 2File: 2 Engineers Certificate March 23compressed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 2 DOSU 31Mar 23 compressed.pdf26 Jun 2025
Form 3File: 30 march 2023 Form 3.pdf26 Jun 2025
Form 3File: 30 june 2023 Form 3.pdf26 Jun 2025
Form 1File: 3ArCertificate upto 30th June 2023.pdf26 Jun 2025
Form 2File: 3 Engineers Certificate June 23compressed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 3 DOSU 30 June 23 compressed.pdf26 Jun 2025
Form 1File: 4ArCertificate upto 30th Sep 2023.pdf26 Jun 2025
Form 2File: 4 Engineers Certificate Sep 23compressed.pdf26 Jun 2025
Form 3File: 30 sept 2023 Form 3.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 4 DOSU 30 Sep 23 compressed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 5 DOSU 31Dec 23 compressed.pdf26 Jun 2025
Form 3File: 31 dec 2023 Form 3.pdf26 Jun 2025
Form 1File: 5ArCertificate upto 31st Dec 2023.pdf26 Jun 2025
Form 2File: 5 Engineers Certificate Dec 23compressed.pdf26 Jun 2025
Form 1File: 6ArCertificate upto 31st Mar 2024.pdf26 Jun 2025
Form 2File: 6 Engineers Certificate March 24compressed.pdf26 Jun 2025
Form 3File: 31 march 2024 Form 3.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: zz6 DOSU 31 Mar 24 compressed.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 7 DOSU 30 June24_compressed.pdf26 Jun 2025
Form 3File: 30 june 2024 Form 3.pdf26 Jun 2025
Form 2File: 7 June 2024.pdf26 Jun 2025
Form 1File: 7 Architech Certificate 30th June 24.pdf26 Jun 2025
Form 1File: Form1 Arch Certificate upto sept 2024.pdf26 Jun 2025
Form 2File: Form 2 Engineers certificate Shyni Gold.pdf26 Jun 2025
Form 3File: Form 3 SKINFRA upto Sep2024.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: DOSU upto sept 2024.pdf26 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 upto dec 2024.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: march 2025 Form 2 Engineers certificate Shyni Gold Mangalam.pdf7 May 2025
Disclosure of sold/ booked inventoryFile: March 2025 Disclosure of sold and unsold inventory Shyni.pdf7 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shyni Gold Mangalam LLP Form 3_compressed.pdf23 Apr 2025
Layout approvalFile: Plan 1_compressed.pdf28 Mar 2025
Building plan approvalFile: Plan 2_compressed.pdf28 Mar 2025
Building plan approvalFile: Plan 3_compressed.pdf28 Mar 2025
Building plan approvalFile: Plan 4_compressed.pdf28 Mar 2025

How this compares with Pune

59%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHYNI GOLD MANGALAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WALHEKARWADI13,700+ in Pune

2 kmSHYNI GOLD MANGALAMCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: SHYNI GOLD MANGALAM LLP

SHYNI GOLD MANGALAM LLP has 1 registration on MahaRERA, including SHYNI GOLD MANGALAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHYNI GOLD MANGALAM is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHYNI GOLD MANGALAM?

The registered promoter entity is SHYNI GOLD MANGALAM LLP, a company as per the filing. Its GSTIN 27CAHPK3279C1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHYNI GOLD MANGALAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHYNI GOLD MANGALAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHYNI GOLD MANGALAM?

The professionals named in the filing: Architect: Sachin Barwade; Architect: ARISE; Engineer: Rahul Ramesh Kapase; Engineer: VAIBHAV GAIKWAD; Chartered Accountant: Maheshwar Marathe; Chartered Accountant: Sapana Abhilash Savalsure. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHYNI GOLD MANGALAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHYNI GOLD MANGALAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHYNI GOLD MANGALAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.