Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 72 months
  • 5 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 72 months from the original
30 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
17 of 43Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 196 documents Report an error

Shubhada Co-operative Housing Society Ltd. is a Residential / Group Housing project by BHOOMIVIJAY PROPERTIES PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001693 on 29 Jul 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 72 months from the original filing. 26 of the 43 units on this registration are recorded sold or booked, and 30 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameShubhada Co-operative Housing Society Ltd.
  • TypeResidential / Group Housing
  • Location
    • Sahakar Road
    • Ville parle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001693
  • ReraGenie IDRG-MH-11881

Builder

  • NameBHOOMIVIJAY PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45201MH2006PTC162669
  • GSTIN27AADCB0560E1Z5
  • Managing DirectorsACHATH MOHANAN MENON, AVINASH GOVIND GHARAT

Key dates

this monthRegisteredJul 2017First promiseJun 2021Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed196 files

Current status

60%26 of 43 units booked
98.3%Work done, per cost certificate

Figures as on 21 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shubhada Wing - ANA10711011
Shubhada Wing - BNA10020020
Shubhada Wing - CNA10012012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 21 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Shubhada Wing - A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Shubhada Wing - B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Shubhada Wing - C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed148

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots148
Closed/Covered140
Open Space8
BuildingClosed/CoveredOpen SpaceTotal
Shubhada Wing - A49352
Shubhada Wing - B49554
Shubhada Wing - C42042

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,975 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Aug 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI7424.96
Proposed, not sanctioned3,375 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMittal Court Nariman Point, Mumbai
Estimated costRs 39.50 cr
Cost incurredRs 38.81 cr
Work done98.26%
BuildingWingEstimatedIncurred
Shubhada Wing - ANARs 10.73 crRs 10.57 cr
Shubhada Wing - BNARs 10.73 crRs 10.53 cr
Shubhada Wing - CNARs 10.73 crRs 10.53 cr
-NARs 7.31 crRs 7.17 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVartak Consultants Pvt Ltd
ArchitectUjwal Satish Bhole
EngineerKC Shah Consultants
EngineerSuman Kuttan
Chartered AccountantBharat Kumar Singhal
Chartered AccountantPawan Lakhotia
Chartered AccountantAML Agrawal and Company
Chartered AccountantR.S Dani & Co.
PartnerRole in project
BHOOMIVIJAY PROPERTIES PRIVATE LIMITED-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008431Jun 2021 → Jun 2022

Reason as filed by the promoterThe under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc due to the pandemic. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. Also, we had to halt our construction recently as a few of

EXT51800013335Jun 2021 → Dec 2023

Reason as filed by the promoterWe had applied for approval of Plans for 7 Floors of Wing A, B and C. The same got approved upto 3rd Floors for Wing A and C and Upto 4th Floor for wing B. So far we have completed 50% of slab structure and awaiting for further C.C. We had applied for further CC with reference to approved plan dated 22-11-2018. But the same got delayed due to ambiguity in DCR Rules and payment schemes. There were amendments in DCR Rules which lead to delay in various project approvals and hence the under- Construction project got delayed. In the year 2020, lockdown restrictions had disrupted the supply chains,

EXT51800018354Jun 2021 → Jun 2024

Reason as filed by the promoterProject got delayed in the first half of year 2023 due to critical shortages of key materials like sand and ready-mix concrete, causing delays in construction schedules. In third quarter 2023, implementation of stringent state regulations, particularly stricter air pollution control measures for developers significantly impeded procuring construction materials and managing debris disposal.

EXT51800025281Jun 2021 → Jun 2026

Reason as filed by the promoterThe primary reason for extension request is that particular flat belongs to an original member who has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The delay in execution of the PAAA is due to disputes among the original flat members, which is beyond the control of the developer. To address this situation, we submitted a Registered Undertaking in favor of the Deputy Chief Engineer of Brihanmumbai Mahanagar Palika (BMC), stating that we will not hand over possession of this flat until the original member signs and executes the PAAA and a copy of the registered PAAA i

EA22072621835Jun 2021 → Jun 2027

Reason as filed by the promoterWe declare that, the construction of the project has been completed in all respects, and the project is 100% physically completed. An Occupancy Certificate (OC) has been obtained for the entire project, except one unit - Flat No. 309, situated on the 3rd Floor of Wing C. The original member belongs to old Flat number C-35 & New Flat No C-309, despite of repeated request & reminders over the period of years has not yet executed the Permanent Alternate Accommodation Agreement (PAAA). The execution of the PAAA has been delayed due to disputes amongst the original members of the society, which are

Litigation declared1

CaseCourtStatus
96/2017Bombay High CourtSuit Pending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500565GIRISH SURESH BURDEBHOOMIVIJAY PROPERTIES PRIVATE LIMITED18/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jun 2024

Documents filed196

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 196 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_Q1 26 27_ Bajaj Shubhada.pdf21 Jul 2026
Withdrawal Update Form 2File: FORM 2_Q1 26 27_ Bajaj Shubhada.pdf21 Jul 2026
Withdrawal Update Form 3File: FORM 3_Q1 26 27_ Bajaj Shubhada.pdf21 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A 25_26 Bajaj Shubhada.pdf19 May 2026
Form 2A (FY 2024-2025)File: Form 2A 24_25 Bajaj Shubhada.pdf19 May 2026
Withdrawal Update Form 1File: Bajaj Shubhda_Form 1 Q4 25_26.pdf17 Apr 2026
Withdrawal Update Form 2File: Bajaj Shubhda_Form 2 Q4 25_26.pdf17 Apr 2026
Withdrawal Update Form 3File: Bajaj Shubhda_Form 3 Q4 25_26.pdf17 Apr 2026
Withdrawal Update Form 1File: Form 1 Bajaj Shubhada as on 30092025.pdf19 Jan 2026
Withdrawal Update Form 2File: Signed Form 2 BHV Q2 FY 25 26.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3_Q3 25 26_Shubhada CHSL.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1 Bajaj Shubhada as on 30092025.pdf13 Nov 2025
Withdrawal Update Form 2File: Signed Form 2 BHV Q2 FY 25 26.pdf13 Nov 2025
Withdrawal Update Form 3File: Shubhada form 3 as on 30092025.pdf13 Nov 2025
Form 5 (FY 2024-2025)File: Signed Form 5 of Bhoomivijay Properties Pvt Ltd.pdf13 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf11 Aug 2025
Withdrawal Update Form 2File: Bajaj Shubhada Form 2 Engineer Certificate 30 06 2025.pdf11 Aug 2025
Withdrawal Update Form 3File: SIGNED FORM-3 OF BHOOMIVIJAY PROPERTIES PVT LTD Q1 FY 25-26.pdf11 Aug 2025
Withdrawal Update Form 1File: Form 1.pdf8 Aug 2025
Withdrawal Update Form 1File: Form 1.pdf8 Aug 2025
Withdrawal Update Form 2File: Bajaj Shubhada Form 2 Engineer Certificate 30 06 2025.pdf8 Aug 2025
Withdrawal Update Form 2File: Bajaj Shubhada Form 2 Engineer Certificate 30 06 2025.pdf8 Aug 2025
Withdrawal Update Form 3File: SIGNED FORM-3 OF BHOOMIVIJAY PROPERTIES PVT LTD Q1 FY 25-26.pdf8 Aug 2025
Withdrawal Update Form 3File: SIGNED FORM-3 OF BHOOMIVIJAY PROPERTIES PVT LTD Q1 FY 25-26.pdf8 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Q4 of FY 24-25.pdf24 Apr 2025
Certificates of CA (Form 3)File: Form 3_Q4 of FY 24-25.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Q4 of FY 24-25.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: DOS.pdf24 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada- Form 1 - Architect Certificate 311224.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada - Form 2 - Engineer Certificate 31122024.pdf22 Jan 2025
Certificates of CA (Form 3)File: Bajaj Shubhada - Form 3 -C A Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada- Form 1 - Architect Certificate 311224.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada - Form 2 - Engineer Certificate 31122024.pdf22 Jan 2025
Certificates of CA (Form 3)File: Bajaj Shubhada - Form 3 -C A Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada- Form 1 - Architect Certificate 311224.pdf22 Jan 2025
Certificates of CA (Form 3)File: Bajaj Shubhada - Form 3 -C A Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada - Form 2 - Engineer Certificate 31122024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA_DISCLOSURE OF INVENTORY 300924.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A Bajaj Shubhada FY 2023-24.pdf11 Dec 2024
Declaration in FORM BFile: BAJAJ SHUBHADA- FORM B 2024 BVPPL.pdf2 Dec 2024
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA - DISCLOSURE OF INVENTORY 301124.pdf2 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 1 Architect Certificate 300924.pdf20 Nov 2024
Certificates of CA (Form 3)File: Bajaj Shubhada Form 3 C A Certificate 30062024.pdf20 Nov 2024
Certificates of CA (Form 3)File: Bajaj Shubhada Form 3 C A Certificate 30092024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 30062024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 30092024.pdf20 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 1 Architect Certificate 300924.pdf20 Nov 2024
Certificates of CA (Form 3)File: Bajaj Shubhada Form 3 C A Certificate 30062024.pdf20 Nov 2024
Certificates of CA (Form 3)File: Bajaj Shubhada Form 3 C A Certificate 30092024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 30062024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 30092024.pdf20 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - BAJAJ SHUBHADA FY 2023-24 (SD).pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - BAJAJ SHUBHADA FY 2023-24 (SD).pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SELF DECLARATION - BS-SCHS JULY 2024.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SELF DECLARATION - BS-SCHS JULY 2024.pdf31 Jul 2024
Certificates of CA (Form 3)File: SELF DECLARATION - BS-SCHS JULY 2024.pdf31 Jul 2024
Disclosure of sold/ booked inventoryFile: Bajaj Shubhada DOS.pdf26 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: BAJAJ SHUBHADA OC 31MAY2024.pdf6 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Revised.pdf27 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf27 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf27 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf27 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA DISCLOSURE OF INVENTORY 31dec23rev.pdf2 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 1 Architect Certificate 31dec23.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 31dec2023.pdf27 Jan 2024
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA DISCLOSURE OF INVENTORY 31dec23.pdf27 Jan 2024
Certificates of CA (Form 3)File: Bajaj Shubhada _Form 3 31dec2023_compressed.pdf27 Jan 2024
Details of encumbrances concerned to FinanceFile: Non Encumbrance - Legal.pdf22 Dec 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance - Legal.pdf22 Dec 2023
Declaration in FORM BFile: Form B.pdf22 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bajaj Shubhada Form 2 Engineer Certificate 30092023.pdf4 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BAJAJ SHUBHADA FORM 2A QUALITY ASSURANCE CERT SEPT2023.pdf4 Nov 2023
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA DISCLOSURE OF INVENTORY 300923.pdf4 Nov 2023
Certificates of CA (Form 3)File: Bajaj Shubhada Form 3 C A Certificate 30092023_compressed.pdf4 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - BAJAJ SHUBHADA FY 2022-23 (SD).pdf10 Oct 2023
Disclosure of sold/ booked inventoryFile: BAJAJ SHUBHADA DISCLOSURE OF INVENTORY 300623.pdf7 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11 Bajaj Shubhada Form 1 Architect Certificate 30 06 23.pdf5 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Bajaj Shubhada Form 2 Engineer Certificate 30 06 2023.pdf5 Aug 2023

How this compares with Mumbai Suburban

60%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shubhada Co-operative Housing Society Ltd. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ville parle6,700+ in Mumbai Suburban

2 kmShubhada Co-operative HoCompleted 167Lapsed / revoked 90Other 172Dot size: filed unitsN

Filed coordinates, straight-line distance. 429 registered projects within 2 km.

Builder: BHOOMIVIJAY PROPERTIES PRIVATE LIMITED

BHOOMIVIJAY PROPERTIES PRIVATE LIMITED has 1 registration on MahaRERA, including Shubhada Co-operative Housing Society Ltd.. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Shubhada Co-operative Housing Society Ltd. is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shubhada Co-operative Housing Society Ltd.?

The registered promoter entity is BHOOMIVIJAY PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U45201MH2006PTC162669 and GSTIN 27AADCB0560E1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shubhada Co-operative Housing Society Ltd.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shubhada Co-operative Housing Society Ltd.?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shubhada Co-operative Housing Society Ltd.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shubhada Co-operative Housing Society Ltd.?

The professionals named in the filing: Architect: Vartak Consultants Pvt Ltd; Architect: Ujwal Satish Bhole; Engineer: KC Shah Consultants; Engineer: Suman Kuttan; Chartered Accountant: Bharat Kumar Singhal; Chartered Accountant: Pawan Lakhotia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shubhada Co-operative Housing Society Ltd.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shubhada Co-operative Housing Society Ltd.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shubhada Co-operative Housing Society Ltd. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.