Home / Browse projects / Thane, Maharashtra / Shubh Atika
Shubh Atika
RG-MH-26901 · RERA P51700009680 · Last updated on MahaRERA portal: 19 Jan 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 7 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shubh Atika is a Others project by Ravi Developments in Thane, Maharashtra, registered with MahaRERA as P51700009680 on 22 Aug 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 7 complaints are on record with the regulator.
At a glance
Project
- NameShubh Atika
- TypeOthers
- Location
- Hatkesh Road
- Near GCC club
- Mira-Bhayandar (M Corp.)
- Thane
- 401107
- Pincode401107
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700009680
- ReraGenie IDRG-MH-26901
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion29 Dec 2024
- Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed45 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shubh Atika | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 67%.
Shubh Atika: 57% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 33% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 67% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 9% |
Progress on shared amenities15
As on 19 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed80
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Origin Realtors LLP | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANISH & ASSOCIATES |
| Engineer | Subhash Chandra Singh |
| Chartered Accountant | M/s. Dipika Patel & Co. |
| Chartered Accountant | Dhawan & Co. |
| Partner | Role in project |
|---|---|
| Ravi Developments | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project was impacted by the COVID-19 outbreak in 2020 and 2021, and the subsequent slow market conditions and labour shortages made it difficult for us to complete the project on time. Therefore, we are requesting an extension of time within which the project shall be completed by the promoter to 29th December 2024.
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000079148 | Mangesh Vaity | Origin Corporation & others | 12/05/2019 |
| CC006000000056847 | Bhawna Piyush Kumar & Piyush Kumar | Origin Realtors LLP | 12/11/2018 |
| CC006000000198080 | Prakash Keshari and Chetna Keshari | Ravi Developments | 24/08/2021 |
| CC12500491 | ISHVARLAL BHUPATBHAI JOSHI | Ravi Developments | 14/02/2025 |
| CC12401065 | Aditya Sudhir Pawar | Ravi Developments | 07/12/2024 |
| CC12501931 | SANTOSH BABAN DALVI | Ravi Developments | 12/06/2025 |
| CC12601071 | ANKIT HARIDAS YADAV | Ravi Developments | 26/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 May 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed45
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Draft Form 3 Shubh Atika 2022-23 Q1.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: Draft Form 3 Shubh Atika 2022-23 Q2.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: Draft Form 3 Shubh Atika 2022-23 Q3.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: Draft Form 3 Shubh Atika 2022-23 Q4.pdf | 19 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Shubh Atika.pdf | 11 Jan 2024 |
| CERSAI detailsFile: Shubh Atika CERSAI.pdf | 11 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Shubh Atika Inventory Disclosure.pdf | 8 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance Excellency.pdf | 3 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23 Shubh Atika.pdf | 2 Jan 2024 |
| Declaration in FORM BFile: Shubh Atika Form B.pdf | 27 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certifcate Shubh Atika September 2023.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 2017-18 Shubh Atika.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 2018-19 Shubh Atika.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 2019-20 Shubh Atika.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 2020-21 Shubh Atika.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 2021-22 Shubh Atika.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Shubh Atika 17-18.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Shubh Atika 18-19.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Shubh Atika 19-20.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Shubh Atika 20-21.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Shubh Atika 21-22.pdf | 24 Nov 2023 |
| Declaration about Commencement CertificateFile: Shubh atika Declaration on CC.pdf | 31 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: shubh atika_Bank Declaration.pdf | 30 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate - SHUBH ATIKA.pdf | 19 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: cc can order.pdf | 25 Sep 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Stay Order.pdf | 25 Sep 2019 |
| Layout approvalFile: Final Layout RERA.pdf | 27 May 2019 |
| Copy of Layout Approval (in case of layout)File: Final Layout RERA.pdf | 27 May 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Latest RERA.pdf | 27 May 2019 |
| OtherFile: DA for RD.pdf | 21 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 28 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubh Atika.pdf | 21 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: subh atika.pdf | 21 Mar 2018 |
| Building plan approvalFile: IOD Building Approval Plan.pdf | 29 Jul 2017 |
| Layout approvalFile: Copy of Layout Approval.pdf | 29 Jul 2017 |
| PAN CardFile: RD PAN CARD NEW.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: Copy of the Legal Title Report.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Details Encumberances.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: IOD Building Approval Plan.pdf | 29 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Attika Arc Certificate.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Atika.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate Subh Atika.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: Agreement Performa.pdf | 29 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Gaurav Woods i | Mira Road East | 234 | Completed | Dec 2011 | Late, Mar 2012 |
| Gaurav Excellency I | Mira road east | 510 | Completed | Sep 2011 | Late, Mar 2012 |
| Gaurav Valley 2 | Mira road east | 197 | Completed | Feb 2010 | Feb 2010 |
| Gaurav Valley 1 | Mira Road East | 270 | Completed | Mar 2009 | Mar 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 45 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shubh Atika on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near GCC club7,600+ in Thane
Filed coordinates, straight-line distance. 244 registered projects within 2 km.
Codename StarLife
JP Infra Realty Private Limited
Prestige Garden Trails
PRESTIGE ESTATES PROJECTS LIMITED
TIARA HILLS PHASE I BLDG NO 3, 5 AND 2
PNK SPACE DEVELOPMENT PVT LTD
The Palace Tower B
JP Infra Realty Private Limited
Sector 2A - Wings JKL
Eversmile Properties Private Limited
CRESCENT WTC - WESTERN TRADE CENTER - PHASE -
CRESCENT SHELTERS
See every Thane project, with the district possession charts
Builder: Ravi Developments
Ravi Developments has 13 registrations on MahaRERA, including Gaurav Excellency and Gaurav Crest. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 4 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Shubh Atika shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shubh Atika is delayed beyond 29 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shubh Atika?
The registered promoter entity is Ravi Developments, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shubh Atika?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shubh Atika?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shubh Atika?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shubh Atika?
The professionals named in the filing: Architect: ANISH & ASSOCIATES; Engineer: Subhash Chandra Singh; Chartered Accountant: M/s. Dipika Patel & Co.; Chartered Accountant: Dhawan & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shubh Atika?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback