ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SHRI VENKATESH KRUPA

Completed No litigation declared Residential / Group Housing project

SHRI VENKATESH KRUPA

By MODI DEVELOPERS

RG-MH-21631 · RERA P51700023261 · Last updated on MahaRERA portal: 8 May 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 6%
0Complaints at MahaRERAon this registration
Jump to the 39 documents Report an error

SHRI VENKATESH KRUPA is a Residential / Group Housing project by MODI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700023261 on 9 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSHRI VENKATESH KRUPA
  • TypeResidential / Group Housing
  • Location
    • S NO 87 H NO 9 P P NO 22
    • BADLAPUR
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700023261
  • ReraGenie IDRG-MH-21631

Builder

  • NameMODI DEVELOPERS
  • Entity typePartnership
  • PartnersRAMU BALAPPA CHINNABUKKA, RAJASHREE LALITKUMAR NALAWADE

Key dates

this monthRegisteredDec 2019First promiseDec 2022Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Dec 2019
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed39 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI VENKATESH KRUPANA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 6%.

SHRI VENKATESH KRUPA: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure6%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area468 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI891.0
Proposed, not sanctioned891 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANVELKAR PLAZA STATION ROAD

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPACE DESIGNERS
EngineerSAAD CONSULTANT
EngineerBobby Bhausaheab Burle
Chartered AccountantBMKD AND ASSOCIATES
PartnerRole in project
MODI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700013176Dec 2022 → Dec 2023

Reason as filed by the promoterDue to transportation issues delay in material of procurement Non-availability of workers/manpowers As per Banking and Registration department norms RERA extension certificate required for registration of unsold flats and claims for inventory of sold flats from bankers.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 May 2024

Documents filed39

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter MODI DEV.pdf8 May 2024
Building plan approvalFile: UPDATED MAPcompressed 3.pdf17 Feb 2023
Details of encumbrances concerned to FinanceFile: DEED OF RETIREMENT CUM RECONSTITUTION OF PARTNERSHIP FIRM 5.pdf17 Feb 2023
Details of encumbrances concerned to LegalFile: DEED OF RETIREMENT CUM RECONSTITUTION OF PARTNERSHIP FIRM 5.pdf17 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: UPDATED MAPcompressed 3.pdf17 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCENT CERITIFICATE_compressed.pdf17 Feb 2023
Declaration about Commencement CertificateFile: DELARATION ABOUT COMMENCEMENT CERTIFICATE FORMAT-D_compressed.pdf17 Feb 2023
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY compressed.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FORM 3_compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 2020-2021compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2020-2021compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2020-2021compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-2021compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-2022compressed.pdf17 Feb 2023
OtherFile: DEED OF RETIREMENT CUM RECONSTITUTION OF PARTNERSHIP FIRM 5.pdf17 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Modi developers ARCHITECT'S CERTIFICATE.pdf11 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MODI DEVELOPERS FORM-2A.pdf11 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: MODI DEVELOPERS FORM-2A.pdf11 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE FORM 2.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: MODI DEVELOPERS FORM-2A.pdf31 Jan 2023
Building plan approvalFile: BUILDING PLAN.pdf15 Nov 2019
Layout approvalFile: LAYOUT.pdf15 Nov 2019
PAN CardFile: MODI DEVELOPER PAN CARD.pdf15 Nov 2019
Copy of the legal title reportFile: TITAL and SEARCH REPORT.pdf15 Nov 2019
Details of encumbrancesFile: ENCOMBERANCE CERTIFICATE.pdf15 Nov 2019
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf15 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf15 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: DEVELOPMENT AGREEMENT_1.pdf15 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: DEVELOPMENT AGREEMENT_2.pdf15 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: DEVELOPMENT AGREEMENT_3.pdf15 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: DEVELOPMENT AGREEMENT_4.pdf15 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE 1.pdf15 Nov 2019
Declaration in FORM BFile: FORM B AFIDAVIT DECLARATION.pdf15 Nov 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE.pdf15 Nov 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf15 Nov 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_compressed (1).pdf15 Nov 2019
Proforma of Allotment letterFile: AGREEMENT TO SALE DRAFF.pdf15 Nov 2019
OtherFile: PARTNERSHIP DEED ADMITION.pdf15 Nov 2019
OtherFile: PARTNERSHIP DEED ORIGINAL.pdf15 Nov 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRI VENKATESH KRUPA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BADLAPUR7,600+ in Thane

2 kmSHRI VENKATESH KRUPACompleted 148Lapsed / revoked 58Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 301 registered projects within 2 km.

Builder: MODI DEVELOPERS

MODI DEVELOPERS has 1 registration on MahaRERA, including SHRI VENKATESH KRUPA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHRI VENKATESH KRUPA is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI VENKATESH KRUPA?

The registered promoter entity is MODI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI VENKATESH KRUPA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI VENKATESH KRUPA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI VENKATESH KRUPA?

The professionals named in the filing: Architect: SPACE DESIGNERS; Engineer: SAAD CONSULTANT; Engineer: Bobby Bhausaheab Burle; Chartered Accountant: BMKD AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI VENKATESH KRUPA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI VENKATESH KRUPA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI VENKATESH KRUPA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.