Home / Browse projects / Nashik, Maharashtra / SHRI LAXMI NARAYAN VILLAS
SHRI LAXMI NARAYAN VILLAS
By Madhoor Buildwell Pvt. Ltd.
RG-MH-95691 · RERA P51600051490 · Last updated on MahaRERA portal: 23 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRI LAXMI NARAYAN VILLAS is a Residential / Group Housing project by Madhoor Buildwell Pvt. Ltd. in Nashik, Maharashtra, registered with MahaRERA as P51600051490 on 23 Jun 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 17 of the 24 units on this registration are recorded sold or booked, and 3 of 22 construction stages are filed complete.
At a glance
Project
- NameSHRI LAXMI NARAYAN VILLAS
- TypeResidential / Group Housing
- Location
- JOHN AUGUSTIN ROAD
- NARAYAN BAPU NAGAR
- JAIL ROAD
- NASHIK
- Dasak
- Nashik
- 422101
- Pincode422101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600051490
- ReraGenie IDRG-MH-95691
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Jun 2023
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed94 files
Current status
Figures as on 23 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 3 | 3 | 12 | 0 | 12 |
| WING B | NA | 3 | 3 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 50%.
WING A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B32%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed56
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| WING A | 33 | 33 |
| WING B | 23 | 23 |
Land and ownership12
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MADHOOR BUILDWELL PRIVATE LIMITED | Nashik | Nashik |
| HIRALAL JAIRAM CHAUHAN | Nashik | Nashik |
| VIJAYKUMAR TRIMBAKLAL CHAUHAN | Nashik | Nashik |
| INDIRA HIRALAL CHAUHAN | Nashik | Nashik |
| GOPAL TRIMBAKLAL CHAUHAN | Nashik | Nashik |
| RAMESH TRIMBAKLAL CHAUHAN | Nashik | Nashik |
| JAI HARSUKHLAL CHAUHAN | Nashik Road | Nashik |
| PHALGUNI ASHISH NAIK | Nashik Road | Nashik |
| REKHA HARSUKHLAL CHAUHAN | Nashik Road | Nashik |
| BHARATI DIPAK RATHOD | - | Cuttack |
| MADHU BHARAT CHAUHAN | - | Visakhapatnam |
| GEETABEN RAJENDRAKUMAR RATHOD | - | Valsad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 3.51 cr | Rs 38.50 lakh |
| WING B | NA | Rs 3.51 cr | Rs 38.50 lakh |
| - | NA | Rs 20.00 lakh | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Avinash G Kothawade |
| Architect | ADWAIT INAMDAR |
| Engineer | Rahul Bahirao Bagale |
| Engineer | DHANANJAY BHAGWANRAO JADHAV |
| Chartered Accountant | PIYUSH LALIT VERMA |
| Chartered Accountant | MUKUND G KOKIL |
| Partner | Role in project |
|---|---|
| Madhoor Buildwell Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promotera. Workforce and Material Issues: • Labor Shortages: Availability of skilled manpower, especially in structural and MEP (Mechanical, Electrical & Plumbing) areas, was restricted due to migration and contractual disruptions, slowing down project execution. • Supply Chain Disruptions: Escalation in raw material costs and delays in delivery of essential materials further extended the project timeline. b. Financial Constraints: • Due to market slowdown, the project faced liquidity constraints, delaying scheduled construction activities.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Dec 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Dec 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 March 26.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 March 26 signed.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 March 26 signed.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Dec 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Dec 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Dec 25.pdf | 5 Feb 2026 |
| Form 2A (FY 2023-2024)File: 2A 23-24.pdf | 31 Jan 2026 |
| Form 2A (FY 2024-2025)File: 2A 24-25.pdf | 31 Jan 2026 |
| Form 1File: 5 Architect Certificate as on 30062024.pdf | 30 Jan 2026 |
| Form 2File: 5 Engineer Certificate Form 2 as on 30062024.pdf | 30 Jan 2026 |
| Form 3File: 5 Form 3 June 24.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 5 Disclosure of Sold Booked Inventory 30062024.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 6 Disclosure of Sold Booked Inventory 30092024.pdf | 30 Jan 2026 |
| Form 1File: 6 Architect Certificate as on 30092024.pdf | 30 Jan 2026 |
| Form 2File: 6 Engineer Certificate Form 2 as on 30092024.pdf | 30 Jan 2026 |
| Form 3File: 6 Form 3 Sept 24.pdf | 30 Jan 2026 |
| Form 1File: 7 Architect Certificate as on 31122024.pdf | 30 Jan 2026 |
| Form 2File: 7 Engineer Certificate Form 2 as on 31122024.pdf | 30 Jan 2026 |
| Form 3File: 7 Form 3 Dec 24.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 7 Disclosure of Sold Booked Inventory 31122024.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 8 Disclosure of Sold Booked Inventory 31032025.pdf | 30 Jan 2026 |
| Form 1File: 8 Architect Certificate as on 31032025.pdf | 30 Jan 2026 |
| Form 2File: 8 Engineer Certificate Form 2 as on 31032025.pdf | 30 Jan 2026 |
| Form 3File: 8 Form 3 March 25.pdf | 30 Jan 2026 |
| Withdrawal Update Form 1File: 9 Architect Certificate as on 30062025.pdf | 30 Jan 2026 |
| Withdrawal Update Form 1File: 10 Architect Certificate as on 30092025.pdf | 30 Jan 2026 |
| Withdrawal Update Form 2File: 9 Engineer Certificate Form 2 as on 30062025.pdf | 30 Jan 2026 |
| Withdrawal Update Form 2File: 10 Engineer Certificate Form 2 as on 30092025.pdf | 30 Jan 2026 |
| Withdrawal Update Form 3File: 9 Form 3 June 25.pdf | 30 Jan 2026 |
| Withdrawal Update Form 3File: 10 Form 3 Sept 25.pdf | 30 Jan 2026 |
| Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (3).pdf | 30 Jan 2026 |
| Form 1File: 1 Architect Certificate as on 30062023.pdf | 15 Jan 2026 |
| Form 2File: 1 Engineer Certificate Form 2 as on 30062023.pdf | 15 Jan 2026 |
| Form 3File: 1 Form 3 June 23.pdf | 15 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of Sold Booked Inventory 30062023.pdf | 15 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 2 Disclosure of Sold Booked Inventory 30092023.pdf | 15 Jan 2026 |
| Form 1File: 2 Architect Certificate as on 30092023.pdf | 15 Jan 2026 |
| Form 2File: 2 Engineer Certificate Form 2 as on 30092023.pdf | 15 Jan 2026 |
| Form 3File: 2 Form 3 Sept 23.pdf | 15 Jan 2026 |
| Form 1File: 3 Architect Certificate as on 31122023.pdf | 15 Jan 2026 |
| Form 2File: 3 Engineer Certificate Form 2 as on 31122023.pdf | 15 Jan 2026 |
| Form 3File: 3 Form 3 Dec 23.pdf | 15 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 3 Disclosure of Sold Booked Inventory 31122023.pdf | 15 Jan 2026 |
| Form 1File: 4 Architect Certificate as on 31032024.pdf | 15 Jan 2026 |
| Form 2File: 4 Engineer Certificate Form 2 as on 31032024.pdf | 15 Jan 2026 |
| Form 3File: 4 Form 3 March 24.pdf | 15 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 4 Disclosure of Sold Booked Inventory 31032024.pdf | 15 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5 24-25.pdf | 27 Sep 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Shree Laxmi Narayan Villas 31122023 Final.pdf | 22 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Shree Laxmi Narayan Villas 31032024 Final.pdf | 22 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Shree Laxmi Narayan Villas 30062024 Final.pdf | 22 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Shree Laxmi Narayan Villas 30092024 Final.pdf | 22 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certificate SLNV 31032024.pdf | 22 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - SLNV - 31122023.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - SLNV - 31032024.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - SLNV - 30062024.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate - SLNV - 30092024.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - SLNV - 31122023.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - SLNV - 31032024.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - SLNV - 30062024.pdf | 20 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate - SLNV - 30092024.pdf | 20 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Engineer Certificate - SLNV - 31032023.pdf | 20 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Engineer Certificate - SLNV - 31032024.pdf | 20 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ADWAIT INAMDAR.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 2 RAHUL BAGALE.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_05102023_Final.pdf | 5 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_30062023.pdf | 8 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate.pdf | 23 Aug 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration_cum_Undertaking.pdf | 23 Aug 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration_Bank_Account.pdf | 11 Jul 2023 |
| Copy of the legal title reportFile: Title_with_Annexures.pdf | 5 Jun 2023 |
| Proforma of Agreement for saleFile: Final AFS 28012023.pdf | 28 Jan 2023 |
| Deviation Report with respect to model copy of AgreementFile: Daviation of AFS 28012023.pdf | 28 Jan 2023 |
| Proforma of Allotment letterFile: Allotment Letter Final_27012023.pdf | 27 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance Certificate 03012023.pdf | 23 Jan 2023 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance Certificate 03012023.pdf | 23 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account 03012023.pdf | 23 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Orgnaisations PRP A.pdf | 9 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Final.pdf | 7 Jan 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| MADHOORS ANANDAMP51600001270 | Dwarka, Nashik | 45 | Jul 2017 | Ongoing | Mar 2024Registered original: Mar 2021 | Not delivered |
| Beverlly Hills Phase - II | Lam Road Deolali Nasik 422401 | 27 | - | Completed | Jun 2017 | May 2017 |
| Beverlly Hills Phase - I | Lam Road Deolali Nasik 422401 | 65 | - | Completed | Dec 2015 | Late, Aug 2016 |
| Teerthankar Apartment | Opp Gurudwara Near Fire Brigade Office Shingada Talav Nasik 422002 | 30 | - | Completed | Mar 2013 | Late, Jun 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHRI LAXMI NARAYAN VILLAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NARAYAN BAPU NAGAR, JAIL ROAD, NASHIK4,100+ in Nashik
Filed coordinates, straight-line distance. 65 registered projects within 2 km.
The Exchange
Viraj Estates Pvt. Ltd. & Others
HARI SANSKRUTI PHASE II
KBC GLOBAL LIMITED
ARRPAN HOUSING
A C JAIN BUILDERS AND DEVELOPERS LLP
Shilpa Madhuvan
Shilpa Estate
STAR PLUS B
DEEPAK KALYANJI CHANDE
SKY ONE
OM SAI OM BUILDERS
See every Nashik project, with the district possession charts
Builder: Madhoor Buildwell Pvt. Ltd.
Madhoor Buildwell Pvt. Ltd. has 4 registrations on MahaRERA, including MADHOORS ANANDAM and BEVERLLY HILLS PHASE - III. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SHRI LAXMI NARAYAN VILLAS is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRI LAXMI NARAYAN VILLAS?
The registered promoter entity is Madhoor Buildwell Pvt. Ltd., a company as per the filing. Its CIN U45200MH1994PTC081387 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRI LAXMI NARAYAN VILLAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHRI LAXMI NARAYAN VILLAS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRI LAXMI NARAYAN VILLAS?
The professionals named in the filing: Architect: Avinash G Kothawade; Architect: ADWAIT INAMDAR; Engineer: Rahul Bahirao Bagale; Engineer: DHANANJAY BHAGWANRAO JADHAV; Chartered Accountant: PIYUSH LALIT VERMA; Chartered Accountant: MUKUND G KOKIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI LAXMI NARAYAN VILLAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback