Home / Browse projects / Nashik, Maharashtra / MADHOORS ANANDAM

Registered No litigation declared Others project

MADHOORS ANANDAM

By Madhoor Buildwell Pvt. Ltd.

RG-MH-00473 · RERA P51600001270 · Last updated on MahaRERA portal: 27 Dec 2024

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 69 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 69 months from the original
44 of 77Construction stages doneacross 7 buildings; furthest along: Staircases, 95%
10 of 47Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

MADHOORS ANANDAM is a Others project by Madhoor Buildwell Pvt. Ltd. in Nashik, Maharashtra, registered with MahaRERA as P51600001270 on 27 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 69 months from the original filing. 37 of the 47 units on this registration are recorded sold or booked, and 44 of 77 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMADHOORS ANANDAM
  • TypeOthers
  • Location
    • Nasik Pune Road
    • Dwarka
    • Nashik (M Corp.)
    • Nashik
    • 422401
  • Pincode422401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600001270
  • ReraGenie IDRG-MH-00473

Builder

  • NameMadhoor Buildwell Pvt. Ltd.
  • Entity typeCompany
  • CINU45200MH1994PTC081387
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorPradip Ratilal Patel
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2017First promiseMar 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2021)
  • Buildings7 building records
  • Documents filed88 files

Current status

79%37 of 47 units booked
92.1%Work done, per cost certificate

Figures as on 27 Dec 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING-ANA55909
WING-BNA44909
WING-CNA55909
WING-DNA33606
WING-ENA33606
WING-FNA22202
WING-GNA22066

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 27 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

44 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Staircases, at 95%.

WING-A90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
WING-B81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
WING-C90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
WING-D76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
WING-E75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
WING-F76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
WING-G37%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure58%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes95%
Street LightingYes75%
Community BuildingsYes35%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes80%

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered2
Open Space45
BuildingClosed/CoveredOpen SpaceTotal
WING-A099
WING-B1910
WING-C1910
WING-D066
WING-E066
WING-G066

Land and ownership10

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners10
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Feb 2026
LandownerVillageDistrict
Ms. Sugrabai Jamal MansuriMumbai CityMumbai City
Ms. Zubeda Jamal MansuriMumbai CityMumbai City
Ms. Hurbanu Jamal Mansuri alias Nurbanoo J.MansuriMumbai CityMumbai City
Smt. Safiyabai Noormohamed MansuriMumbai CityMumbai City
Mrs. Samina Aziz MamunjiMumbai CityMumbai City
Mrs. Nasreen Mohd. Ayub MansooriMumbai CityMumbai City
Mr. Javed Aktar Noormohamed MansuriMumbai CityMumbai City
Mr. Sajjad Husain Noormohamad MansuriMumbai CityMumbai City
Smt. Jainabbai Abubakar MansuriMumbai CityMumbai City
Mr. Mohamad Asif Aboobakar MansuriMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityDEOLALI CANTONMENT BOARD
Permissible FSI4850.0
Proposed, not sanctioned4,849 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMahek Plaza Ground Floor Maharashtra Nagar Off Chandavarkar Road Borivali West Mumbai 400092
Estimated costRs 17.63 cr
Cost incurredRs 16.23 cr
Work done92.06%
BuildingWingEstimatedIncurred
WING-ANARs 3.30 crRs 3.28 cr
WING-CNARs 3.29 crRs 3.27 cr
WING-BNARs 3.26 crRs 3.26 cr
WING-DNARs 2.08 crRs 1.98 cr
WING-ENARs 1.71 crRs 1.57 cr
WING-GNARs 1.60 crRs 78.52 lakh
WING-FNARs 1.34 crRs 1.19 cr
-NARs 1.05 crRs 89.99 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHomework
ArchitectPradip Patel & Associates
ArchitectADWAIT INAMDAR
EngineerSANTOSH ASAWA
EngineerANIL BHAULA KUMAVAT
Chartered AccountantPIYUSH VERMA AND ASSOCIATES
Chartered AccountantMUKUND G KOKIL
Chartered AccountantPIYUSH LALIT VERMA
PartnerRole in project
Madhoor Buildwell Pvt. Ltd.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600016690Mar 2021 → Mar 2024

Reason as filed by the promotera) Residential Project is not completed b) Due to the COVID-19 pandemic, the regular flow of work is hampered on account of the unavailability of labor on a regular basis

EXT51600009413Mar 2021 → Dec 2021

Reason as filed by the promoterWe have to state that, though 90% of the work is completed; the said project is getting delayed, mainly because of the following reasons; which were beyond our control. a) Due to Covid-19 Pandemic b) Scarcity of building materials especially Natural Sand in Nasik city. In view of the above we therefore request you to grant us an extension of 9 Months i.e. 31/12/2021 in order to complete the said project.

EXT51600025267Mar 2021 → Dec 2026

Reason as filed by the promoterWe sincerely regret the delay in completing the project and submitting this application for an extension under the MahaRERA Act. Despite our consistent efforts, the following unforeseen challenges have significantly impacted the project's timeline: 1. Unfavorable Market Conditions: Prolonged economic uncertainties and reduced consumer demand have directly affected project funding and execution. 2. Labor and Resource Shortages: A sudden scarcity of skilled labor and essential materials due to some reasons caused project interruptions. 3. Unforeseen Technical Issues: On-site technical challenges

Litigation declared2

CaseCourtStatus
350/2014/2014Civil Judge Senior Division NashikPending
205/2014/2014Additional Revenue Commissioner Nashik DivisionPending

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC001000000010156Prakash KewlaniMadhoor Buildwell Pvt Ltd29/09/2020
CC001000000010158Prakash KewlaniMadhoor Buildwell PvtLtd29/09/2020
CC001000000050292NAVEEN MANOHARLAL NAGPALMADHOOR BUILDWELL PRIVARE LIMITED17/12/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf27 Dec 2024
Other - TechnicalFile: Madhoors Anandam reply.pdf27 Dec 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate Anandam 30092024 Final.pdf22 Nov 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate Anandam 30062024 Final.pdf22 Nov 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate Anandam 31032024 Final.pdf22 Nov 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate Anandam 31122023 Final.pdf22 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA Certificate Anandam 31032024.pdf22 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - Anandam - 31122023.pdf20 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - Anandam - 31032024.pdf20 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - Anandam - 30062024.pdf20 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate - Anandam - 30092024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Anandam - 31122023.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Anandam - 31032024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Anandam - 30062024.pdf20 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate - Anandam - 30092024.pdf20 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Engineer Certificate - Anandam - 31032024.pdf20 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form_5_March_2023_Anandam.pdf13 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Anandam.pdf12 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Anandam.pdf12 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure 30092023 Anandam.pdf12 Oct 2023
Certificates of CA (Form 3)File: Form 3_Anandam.pdf12 Oct 2023
Disclosure of sold/ booked inventoryFile: 1.pdf13 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 19-20 bW.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 20-21BW.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22BW.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23BW.pdf10 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31032023.pdf3 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032023.pdf3 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31032023.pdf3 May 2023
Certificates of CA (Form 3)File: CA Certificate as on 31032023.pdf3 May 2023
Details of encumbrances concerned to FinanceFile: Encumbrances to Legal Title 04032023.pdf6 Mar 2023
Details of encumbrances concerned to LegalFile: Encumbrances to Legal Title 04032023.pdf6 Mar 2023
Copy of the legal title reportFile: Title Certificate 04032023.pdf4 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA Certified 31032022.pdf9 Feb 2023
Proforma of Agreement for saleFile: Agreement To Sell 'Anandam' Draft 09 Feb 2023.pdf9 Feb 2023
Proforma of Allotment letterFile: Allotment_Letter_Anandam.pdf9 Feb 2023
Deviation Report with respect to Allotment letterFile: No Daviation Report to Allotment.pdf9 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Sheet_Anandam.pdf9 Feb 2023
Declaration about Commencement CertificateFile: Declaration about Commencement.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31032022.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31032021.pdf5 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31032022.pdf5 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf5 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Orgnaisations PRP A.pdf5 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf5 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31032020.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31032021.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31032022.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31122022.pdf4 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31032019.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032019.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032020.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032021.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032022.pdf4 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31122022.pdf4 Feb 2023
Certificates of CA (Form 3)File: CA Certificate as on 31032019.pdf4 Feb 2023
Certificates of CA (Form 3)File: CA Certificate as on 31032020.pdf4 Feb 2023
Certificates of CA (Form 3)File: CA Certificate as on 31032021.pdf4 Feb 2023
Certificates of CA (Form 3)File: CA Certificate as on 31032022.pdf4 Feb 2023
Certificates of CA (Form 3)File: CA Certificate as on 31122022.pdf4 Feb 2023
Certificates of CA (Form 5)File: Form 5 CA Certified 31032019.pdf4 Feb 2023
Certificates of CA (Form 5)File: Form 5 CA Certified 31032022.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 CA Certified 31032019.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 CA Certified 31032020.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 CA Certified 31032021.pdf4 Feb 2023
Disclosure of sold/ booked inventoryFile: Anandam.pdf25 May 2021
Details of encumbrancesFile: NOC from SBI - Anandam Project.pdf4 Aug 2020
Details of encumbrancesFile: Index-II.pdf4 Aug 2020
Details of Restarting of Construction work post lockdownFile: Madhoor's_Anandam_Covid_06072020.pdf6 Jul 2020
Certificates of CA (Form 5)File: Madhoors Anandam.pdf15 Oct 2018
Layout approvalFile: Layout.pdf21 Jul 2017
Building plan approvalFile: A-B-C-Wing.pdf21 Jul 2017
Building plan approvalFile: D-E-Wing.pdf21 Jul 2017
PAN CardFile: PAN Card of Company.pdf21 Jul 2017
Copy of the legal title reportFile: Titel Certificate Madhoor Anandam.pdf21 Jul 2017
Details of encumbrancesFile: Titel Certificate Madhoor Anandam.pdf21 Jul 2017
Details of encumbrancesFile: Encumbrance Details.pdf21 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf21 Jul 2017
Building Plan Approval (IOD)File: A-B-C-Wing.pdf21 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Beverlly Hills Phase - IILam Road Deolali Nasik 42240127CompletedJun 2017May 2017
Beverlly Hills Phase - ILam Road Deolali Nasik 42240165CompletedDec 2015Late, Aug 2016
Teerthankar ApartmentOpp Gurudwara Near Fire Brigade Office Shingada Talav Nasik 42200230CompletedMar 2013Late, Jun 2013

How this compares with Nashik

79%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 69 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MADHOORS ANANDAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dwarka4,100+ in Nashik

Builder: Madhoor Buildwell Pvt. Ltd.

Madhoor Buildwell Pvt. Ltd. has 4 registrations on MahaRERA, including MADHOORS ANANDAM and BEVERLLY HILLS PHASE - III. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if MADHOORS ANANDAM is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MADHOORS ANANDAM?

The registered promoter entity is Madhoor Buildwell Pvt. Ltd., a company as per the filing. Its CIN U45200MH1994PTC081387 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MADHOORS ANANDAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MADHOORS ANANDAM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MADHOORS ANANDAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MADHOORS ANANDAM?

The professionals named in the filing: Architect: Homework; Architect: Pradip Patel & Associates; Architect: ADWAIT INAMDAR; Engineer: SANTOSH ASAWA; Engineer: ANIL BHAULA KUMAVAT; Chartered Accountant: PIYUSH VERMA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MADHOORS ANANDAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MADHOORS ANANDAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MADHOORS ANANDAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.