ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / SHRI GAJANAN

Registered No litigation declared Others project

SHRI GAJANAN

By UTSAHI LILADHAR CHAVANDE

RG-MH-82135 · RERA P52800009842 · Last updated on MahaRERA portal: 31 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 84 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 84 months from the original
4 of 11Construction stages donefurthest along: Stilt Floor, 90%
11 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 263 documents Report an error

SHRI GAJANAN is a Others project by UTSAHI LILADHAR CHAVANDE in Ratnagiri, Maharashtra, registered with MahaRERA as P52800009842 on 22 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing. 7 of the 18 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHRI GAJANAN
  • TypeOthers
  • Location
    • ZARNI ROAD
    • Ratnagiri
    • Rahataghar
    • 415612
  • Pincode415612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800009842
  • ReraGenie IDRG-MH-82135

Builder

  • NameUTSAHI LILADHAR CHAVANDE
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed263 files

Current status

39%7 of 18 units booked
82.9%Work done, per cost certificate

Figures as on 31 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI GAJANANNA639918

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

SHRI GAJANAN: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 31 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area261 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityUtsahi Chavande
Permissible FSI387.97
Proposed, not sanctioned388 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAM ALI, RATNAGIRI, 415612
Estimated costRs 85.47 lakh
Cost incurredRs 70.86 lakh
Work done82.91%
BuildingWingEstimatedIncurred
SHRI GAJANANNARs 85.47 lakhRs 70.86 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUTSAHI L CHAVANDE
EngineerMANOJ JOSHI
Chartered AccountantVaradraj
Chartered AccountantAkshay
PartnerRole in project
UTSAHI LILADHAR CHAVANDE-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800018683Dec 2019 → Dec 2024

Reason as filed by the promoterDue to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers.

EXT52800005309Dec 2019 → Dec 2020

Reason as filed by the promoterPayment Recovery.

EXT52800013082Dec 2019 → Dec 2023

Reason as filed by the promoterDue to project plan revised with number 518/2817 dated 07/09/2021, economic slowdown, poor market conditions, labour unavailability and delay in payments from customers.

EXT52800009847Dec 2019 → Dec 2022

Reason as filed by the promoterDue to Covid 19 lockdown work was stopped, labour unavailability, poor market conditions, delay of payments from customers.

EXT52800026019Dec 2019 → Dec 2025

Reason as filed by the promoterDue to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers.

EA01042620524Dec 2019 → Dec 2026

Reason as filed by the promoterDue to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability, and delay in payments from customers.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed263

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 263 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q1 (June 2025).pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1 Q2 (September 2025).pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1 Q3 (December 2025).pdf31 Mar 2026
Withdrawal Update Form 2File: Shree Gajanan REERA 300625.pdf31 Mar 2026
Withdrawal Update Form 2File: Shree Gajanan REERA 300625.pdf31 Mar 2026
Withdrawal Update Form 2File: Shree Gajanan RERA 311225.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3 as on 30-06-2025.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3 as on 30-09-2025.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3 as on 30-09-2025.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf15 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf15 Feb 2026
Withdrawal Update Form 3File: Form 3 (2024-2025).pdf15 Feb 2026
Form 1File: Form 1 (31 March 2019).pdf13 Feb 2026
Form 2File: Form 2 (2018-2019).pdf13 Feb 2026
Form 3File: Form 3 (2018-2019).pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory (2019).pdf13 Feb 2026
Form 1File: Form 1 (31 March 2019).pdf13 Feb 2026
Form 2File: Form 2 (2018-2019).pdf13 Feb 2026
Form 3File: Form 3 (2018-2019).pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory (2019).pdf13 Feb 2026
Form 1File: Form 1 (31 March 2019).pdf13 Feb 2026
Form 2File: Form 2 (2018-2019).pdf13 Feb 2026
Form 3File: Form 3 (2018-2019).pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory (2019).pdf13 Feb 2026
Form 1File: Form 1 (31 March 2019).pdf13 Feb 2026
Form 2File: Form 2 (2018-2019).pdf13 Feb 2026
Form 3File: Form 3 (2018-2019).pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory (2019).pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026
Form 1File: Form 1.pdf13 Feb 2026
Form 2File: Form 2.pdf13 Feb 2026
Form 3File: Form 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_ Booked Inventory.pdf13 Feb 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SAI SHANTIRAHATAGHAR GUDHEVATHAR RATNAGIRI1CompletedApr 2011Apr 2011

How this compares with Ratnagiri

39%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one moved by 84 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep SHRI GAJANAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ratnagiri1,100+ in Ratnagiri

2 kmSHRI GAJANANCompleted 8Lapsed / revoked 6Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: UTSAHI LILADHAR CHAVANDE

UTSAHI LILADHAR CHAVANDE has 1 registration on MahaRERA, including SHRI GAJANAN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if SHRI GAJANAN is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI GAJANAN?

The registered promoter entity is UTSAHI LILADHAR CHAVANDE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI GAJANAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI GAJANAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI GAJANAN?

The professionals named in the filing: Architect: UTSAHI L CHAVANDE; Engineer: MANOJ JOSHI; Chartered Accountant: Varadraj; Chartered Accountant: Akshay. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI GAJANAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI GAJANAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI GAJANAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.