Home / Browse projects / Raigarh, Maharashtra / SHRI ANNAPURNA RESIDENCY
SHRI ANNAPURNA RESIDENCY
RG-MH-28472 · RERA P52000027674 · Last updated on MahaRERA portal: 14 Aug 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRI ANNAPURNA RESIDENCY is a Others project by SHRIKANT DEODHAR in Raigarh, Maharashtra, registered with MahaRERA as P52000027674 on 25 Dec 2020. The registration is recorded completed; possession was promised by 30 Sep 2023.
At a glance
Project
- NameSHRI ANNAPURNA RESIDENCY
- TypeOthers
- Location
- RAIGARD
- PEN
- Pen Rural
- Raigarh
- 402107
- Pincode402107
- RERA no.P52000027674
- ReraGenie IDRG-MH-28472
Builder
- NameSHRIKANT DEODHAR
- Entity typeOthers
- Named personsSHRIKANT DEODHAR, Lata Sadanand Lele
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on25 Dec 2020
- Promised completion30 Sep 2023
- Revised completionNone
- Buildings1 building record
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHRI ANNAPURNA RESIDENCY | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
SHRI ANNAPURNA RESIDENCY: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 14 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
| COMPOUND WALL | Yes | 100% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GRUHA KALPANA |
| Engineer | Mr Mahesh Chavan |
| Chartered Accountant | NEHALI AND CO |
| Partner | Role in project |
|---|---|
| SHRIKANT DEODHAR | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 May 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Aug 2023
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Architect form 4.pdf | 14 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 10 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 annapurna residency.pdf | 22 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 18 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 18 Jul 2023 |
| Layout approvalFile: REVISED APPROVED PLAN 11 AUGUST 2021_compressed.pdf | 11 May 2023 |
| Copy of Layout Approval (in case of layout)File: REVISED APPROVED PLAN 11 AUGUST 2021_compressed.pdf | 11 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 11 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 11 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3.pdf | 11 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SKMBT_C36022120415370.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 10 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 8 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 8 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3.pdf | 25 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 16 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 16 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3.pdf | 13 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 8 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 6 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3.pdf | 23 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan 11 Apr 2022_compressed.pdf | 16 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ACE - RCC March 22_compressed.pdf | 16 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA form 3.pdf | 24 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 11 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 11 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate Nehali.pdf | 19 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Sanjay Tupe.pdf | 19 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA.pdf | 15 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_merged.pdf | 14 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf | 14 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed CA Certificate-SHRIKANT DEODAR (1).pdf | 16 Aug 2021 |
| Layout approvalFile: PLANS.pdf | 14 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: PLANS.pdf | 14 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 14 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 14 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed CA Certificate-SHRIKANT DEODAR_2.pdf | 14 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed CA Certificate-SHRIKANT DEODAR_2.pdf | 15 Jun 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 12 Jun 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Jun 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate.pdf | 18 Dec 2020 |
| Building plan approvalFile: FLOOR PLAN.pdf | 11 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN.pdf | 11 Dec 2020 |
| PAN CardFile: Shrikant Pan Card.pdf | 8 Dec 2020 |
| Layout approvalFile: LAYOUT.pdf | 7 Dec 2020 |
| Copy of the legal title reportFile: TITLE 01.pdf | 7 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 7 Dec 2020 |
| Declaration in FORM BFile: FORM B 01.pdf | 7 Dec 2020 |
| Proforma of Allotment letterFile: ALLOTMENT AND AGREEMENT_compressed.pdf | 7 Dec 2020 |
| Details of encumbrancesFile: no encumbrance self declaration-pdf.pdf | 12 Aug 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: cc.pdf | 12 Aug 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 12 Aug 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 52 filed documents as one ZIP, foldered, with a manifest
Keep SHRI ANNAPURNA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PEN5,900+ in Raigarh
HAWARE GRANDE
HAWARE GRANDE
KALINDI ELITE
KALINDI REALTORS PRIVATE LIMITED
GOKUL
SUYASH BUILDERS AND DEVELOPERS
OSCAR HEIGHTS
OSCAR BUILDERS
dbafna ONE
D Bafna Properties
MITHILA
SATHE SCHEMES LLP
See every Raigarh project, with the district possession charts
Builder: SHRIKANT DEODHAR
SHRIKANT DEODHAR has 1 registration on MahaRERA, including SHRI ANNAPURNA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SHRI ANNAPURNA RESIDENCY is delayed beyond 30 Sep 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRI ANNAPURNA RESIDENCY?
The registered promoter entity is SHRIKANT DEODHAR, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRI ANNAPURNA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHRI ANNAPURNA RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRI ANNAPURNA RESIDENCY?
The professionals named in the filing: Architect: GRUHA KALPANA; Engineer: Mr Mahesh Chavan; Chartered Accountant: NEHALI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI ANNAPURNA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback