SHREEPATI ARADHANA
By SHREEPATI BUILD INFRA INVESTMENT LIMITED
RG-MH-01075 · RERA P51900000558 · Last updated on MahaRERA portal: 31 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEPATI ARADHANA is a Residential / Group Housing project by SHREEPATI BUILD INFRA INVESTMENT LIMITED in MUMBAI, 400002, registered with MahaRERA as P51900000558 on 18 Jul 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameSHREEPATI ARADHANA
- TypeResidential / Group Housing
- Location
- MUMBAI
- 400002
- Pincode400002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900000558
- ReraGenie IDRG-MH-01075
Builder
- NameSHREEPATI BUILD INFRA INVESTMENT LIMITED
- Entity typeCompany
- Managing DirectorRAJENDRA RAMESHCHANDRA CHATURVEDI
- Other registrations2 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Jul 2017
- Promised completion30 Dec 2022
- Revised completionRevised to 30 Dec 2022 (originally 31 Dec 2019)
- Buildings3 building records
- Documents filed127 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 20 | 0 | 0 | 0 | 0 |
| WING B | NA | 22 | 0 | 0 | 0 | 0 |
| WING C | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 31 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.
WING A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities18
As on 31 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 99% |
| Water Supply | Yes | 98% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 99% |
| Storm Water Drains | Yes | 98% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 99% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 99% |
| Energy managemcnt | Yes | 98% |
| Fire protection and fire safety requirements | Yes | 99% |
| Electrical meter room, sub-station, receiving station | Yes | 99% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Society Office for Wing A B | Yes | 100% |
| Society Office | Yes | 100% |
| Fitness Center | Yes | 99% |
Parking filed108
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 3 | 3 |
| WING B | 105 | 105 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KALPESH SHAH |
| Partner | Role in project |
|---|---|
| SHREEPATI BUILD INFRA INVESTMENT LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterEarlier Wing A was proposed from Ground to 16th floors now the plans have been amended on 06/11/2020 and Wing A is now proposed from ground to 19th Floors also commencement certificate for the same has been issued upto 19th floor on 1st April 2021 for full work of Wing A. Revised approved plans provided herewith.
Reason as filed by the promoterIn the project “Shreepati Aradhana” the building consists of three wings namely wing-“A”, “B” and “C” out of which wing “B” and “C” are completed. we have received revised NOC from M.H.A.D.A. as per DCPR 2034 on 09.04.2019 with its validity extended upto 20.02.2021. We have also received approval to plans for additional seven floors in Wing “A” as per DCPR 2034. The Plans were approved by Hon. Municipal Commissioner on 24.04.2019 and the same were amended on 04.06.2019 up to 17th (pt) Floor and further C.C upto 12th floor was issued on 10.06.2019. Therefore, as per the earlier mentioned comple
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 May 2022
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 31 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 31 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure March 1.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure June 2.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure September 3.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure December 4.pdf | 27 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed form 5 Aradhana 2022.pdf | 27 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate 3.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 1.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 3.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate 1.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate 2.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate 1.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate 2.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate 3.pdf | 25 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Aradhana 24.pdf | 21 Feb 2025 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 12 Feb 2025 |
| Certificates of CA (Form 3)File: Form3.pdf | 12 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE M.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 11 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf | 11 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Acrh Cert form 1 Mar 24 Updated.pdf | 24 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2.pdf | 22 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec24.pdf | 21 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar24.pdf | 21 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aug24.pdf | 21 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf | 8 Nov 2024 |
| Certificates of CA (Form 3)File: ca march 2023.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: SBIIL Form 3 June2023_1_11zon.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: SBIIL Form 3 Sept 23_2_11zon.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: SBIIL Form 3 Dec 23_3_11zon.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: Scaned form 3 signed and ack June22.pdf | 17 Jul 2024 |
| Certificates of CA (Form 3)File: Scaned form 3 signed and ack Sep22.pdf | 17 Jul 2024 |
| Certificates of CA (Form 3)File: Scaned form 3 signed and ack Dec22.pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Form 1 june 22.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Form 1 Sep 22.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SBIIL Arch Cert Dec 22.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Form 1 march 23.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert Form 1 June 23.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert Form 1 Sept 23.pdf | 15 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AcrhCert form 1 Dec 23.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert Form 2 June 2022.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert Form 2 Sept 2022.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SBIIL Eng Cert Dec 22.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SBIIL Eng Cert March 23.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert Form2 Aradhana June 2023.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert Form2 Aradhana Sept 2023.pdf | 15 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert Form2 Aradhana Dec 2023.pdf | 15 Jul 2024 |
| Certificates of CA (Form 3)File: 4_11zon.pdf | 28 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Aradhana.pdf | 2 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate FORM 1.pdf | 4 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf | 4 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3 Final.pdf | 4 Apr 2023 |
| Certificates of CA (Form 5)File: form 5 Aradhana 2022.pdf | 4 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 Aradhana 2022.pdf | 4 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 from Architech.pdf | 4 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 from Architech.pdf | 4 Jan 2023 |
| Building plan approvalFile: Drawing B Wing 2nd to 6th.pdf | 3 Jan 2023 |
| Building Plan Approval (IOD)File: Drawing B Wing 2nd to 6th.pdf | 3 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE LEGAL TITLE TO LAND.pdf | 21 Dec 2022 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE LEGAL TITLE TO LAND.pdf | 21 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 21 Dec 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: NO ENCUMBRANCE FINANCE.pdf | 21 Dec 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA BANK LETTER (1).pdf | 21 Dec 2022 |
| Building plan approvalFile: Plan for Wing B Ext portion.pdf | 19 Dec 2022 |
| Building Plan Approval (IOD)File: Plan for Wing B Ext portion.pdf | 19 Dec 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC up to 19th of Wing A and 4th flr of WIng B.pdf | 19 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate.pdf | 19 Dec 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC wing A.pdf | 24 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Aradhana compressed.pdf | 24 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf | 23 Jun 2022 |
| Declaration about Commencement CertificateFile: CCDeclaration.pdf | 22 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf | 20 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 20 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 20 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 2A 20-21.pdf | 20 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHREEPATI ARADHANA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MUMBAI
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
KRISHVI ESCAPE
SHAGUN REALTY
One Marina
VALENCIA AND MISHAL VENTURES PVT LTD
La Belleza
Qaswa Enterprises
AJMERA DOWNTOWN
ASHJIT REALTIES PVT. LTD.
Prestige Ocean Towers - South
Prestige Projects Private Limited
Prestige Ocean Towers - North
Prestige Projects Private Limited
Builder: SHREEPATI BUILD INFRA INVESTMENT LIMITED
SHREEPATI BUILD INFRA INVESTMENT LIMITED has 3 registrations on MahaRERA, including SHREEPATI ARADHANA and SHREEPATI CORONET. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What does it mean that SHREEPATI ARADHANA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREEPATI ARADHANA is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEPATI ARADHANA?
The registered promoter entity is SHREEPATI BUILD INFRA INVESTMENT LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEPATI ARADHANA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREEPATI ARADHANA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEPATI ARADHANA?
The professionals named in the filing: Architect: KALPESH SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEPATI ARADHANA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback