Shreeji Plaza Wing A
RG-MH-54444 · RERA P51800007051 · Last updated on MahaRERA portal: 17 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 39 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shreeji Plaza Wing A is a Residential / Group Housing project by SIDDHARTH ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007051 on 17 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 39 months from the original filing. 132 of the 165 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameShreeji Plaza Wing A
- TypeResidential / Group Housing
- Location
- VALNAI
- MALAD WEST
- Borivali
- Mumbai Suburban
- 400064
- Pincode400064
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007051
- ReraGenie IDRG-MH-54444
Builder
- NameSIDDHARTH ENTERPRISES
- Entity typePartnership
- PartnersNimesh Desai, Bhushan Patil
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
- Past their filed date2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Aug 2017
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed177 files
Current status
Figures as on 17 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shreeji Plaza Wing A | NA | 39 | 38 | 165 | 0 | 165 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Shreeji Plaza Wing A: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed95
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Mr Rajesh Patil and Mr Maksud Rana | - | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Shreeji Plaza Wing A | NA | Rs 66.29 cr | Rs 94.34 cr |
| - | NA | Rs 28.17 cr | Rs 27.89 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V S VAIDYA AND ASSOCIATES |
| Engineer | CNS CONSULTANTS |
| Chartered Accountant | NEHALI DHAVAL DOSHI |
| Partner | Role in project |
|---|---|
| SIDDHARTH ENTERPRISES | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2025
Reason as filed by the promoter1. 1/We hereby apply for extension of registration of the following project Shreeji Plaza Wing A,Plot Bearing/CTS/Survey/Final Plot No.: CTS No 1 Pt and 2 Pt of Village Valnai Taluka Borivali Orlem Malad West Mumbai at Borivali, Borivali, Mumbai Suburban, 400064; registered with the regulatory a uthority vide project registration certificate bearing No. P51800007051 which shall expires on 30th June 2025. 2. As required I/we submit the following documents and information, namely: a. Authenticated copy of proposed Plan of the project showing the stage of development works undertaken till date; b
Reason as filed by the promoterOC Recived
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504106 | Ryan Jashnani | SIDDHARTH ENTERPRISES | 21/11/2025 |
| CC12602276 | Aijaz Amiruddin Kazi | SIDDHARTH ENTERPRISES | 17/04/2026 |
| CC12602572 | Daniel Jashnani | SIDDHARTH ENTERPRISES | 02/05/2026 |
| CC12603073 | Latesh Shownkeen | SIDDHARTH ENTERPRISES | 23/05/2026 |
| CC12603209 | Avinash Ajit Udeshi | SIDDHARTH ENTERPRISES | 28/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed177
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 177 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Plaza A.pdf | 17 Sep 2026 |
| Withdrawal Update Form 2File: Signed Engineer Certificate Plaza A Wing Jun 26.pdf | 17 Sep 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate A wing Siddharth Jun 26.pdf | 17 Sep 2026 |
| Withdrawal Update Form 1File: Signed Shreeji Plaza A Wing.pdf | 16 Sep 2026 |
| Withdrawal Update Form 2File: Plaza A engineer cer-Mar 26.pdf | 16 Sep 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate - A wing Siddharth m26_compressed.pdf | 16 Sep 2026 |
| Form 2A (FY 2025-2026)File: Plaza B Form 2A FY 25-26.pdf | 6 Jul 2026 |
| Form 2A (FY 2024-2025)File: form 2A 24-25 new.pdf | 4 Jul 2026 |
| Form 5 (FY 2024-2025)File: Signed Form 5 Plaza A.pdf | 4 Jul 2026 |
| Withdrawal Update Form 1File: Signed Architect Shreeji Plaza A (1).pdf | 3 Jun 2026 |
| Withdrawal Update Form 2File: Signed Enginner cer-plaza A dec 25.pdf | 3 Jun 2026 |
| Withdrawal Update Form 3File: Signed Plaza A wing CA certificate Dec 25.pdf | 3 Jun 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 19 Dec 2025 |
| Withdrawal Update Form 2File: Signed Plaza A Enginner Cer sep 25.pdf | 19 Dec 2025 |
| Withdrawal Update Form 3File: Signed CA certificate-Plaza A sep 25.pdf | 19 Dec 2025 |
| Withdrawal Update Form 1File: form 1 june 25.pdf | 29 Nov 2025 |
| Withdrawal Update Form 2File: form 2 june 25.pdf | 29 Nov 2025 |
| Withdrawal Update Form 3File: form 3 june 25.pdf | 29 Nov 2025 |
| Form 1File: form 1.pdf | 17 Jun 2025 |
| Form 2File: form 2.pdf | 17 Jun 2025 |
| Form 3File: form 3.pdf | 17 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory disclosure-Plaza A.pdf | 17 Jun 2025 |
| Declaration in FORM BFile: Plaza A- form B.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Plaza A-Engineer certificate.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 14 Apr 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 14 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 11 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Signed Plaza A.pdf | 10 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 24 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf | 23 Jan 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 11 Jan 2025 |
| Layout approvalFile: plans_1-2.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_3-4.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_5-6.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_7-8.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_9-10.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_11-12.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_13-14.pdf | 21 Dec 2024 |
| Layout approvalFile: plans_15-end.pdf | 21 Dec 2024 |
| Building plan approvalFile: Theory.PDF | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_3-4.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_5-6.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_7-8.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_9-10.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_11-12.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_13-14.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_15-end.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: plans_1-2.pdf | 21 Dec 2024 |
| Building Plan Approval (IOD)File: Theory.PDF | 21 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: shreeji plaza full CC dtd 19-12-24.pdf | 20 Dec 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 22 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 10 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 16 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 11 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SHREEJI PLAZA A WING.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed architect certificate ( shreeji PLAZA wing A.pdf | 17 Apr 2024 |
| Certificates of CA (Form 3)File: Signed CA certificate ( SHREEJI PLAZA WING A ).pdf | 17 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: shreeji plaza a wing 22-23.pdf | 6 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Dec 23 SHREEJI PLAZA A.pdf | 23 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Dec 23.pdf | 23 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 Ca Certificate Dec 23 Siddharth Plaza A Wing.pdf | 23 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Plaza A Wing DEC 23.pdf | 10 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Siddharth A Wing.pdf | 26 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Plaza A Wing Architect cer.pdf | 25 Oct 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate plaza A Wing FORM 3.pdf | 16 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Siddharth A as on June 23 01-Aug-2023 18-30-21.pdf | 2 Aug 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate Siddharth (Plaza) A Wing as on june 23(1) 01-Aug-2023 18-37-46.pdf | 2 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate Siddharth A wing.pdf | 21 Jun 2023 |
| Details of encumbrancesFile: plaza a wing No encumbrance.pdf | 25 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Architect cer Plaza A wing.pdf | 27 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Engineer Certificate Plaza A Wing.pdf | 27 Apr 2023 |
| Certificates of CA (Form 3)File: FORM 3 PLAZA A.pdf | 21 Apr 2023 |
| PAN CardFile: Siddharth pan card.pdf | 28 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Signed plaza A annual certificate 21-22.pdf | 27 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 plaza A wing_compressed.pdf | 17 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 plaza A wing_compressed.pdf | 17 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 plaza A wing_compressed.pdf | 17 Jan 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 177 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Shreeji Plaza Wing A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MALAD WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 376 registered projects within 2 km.
Ruparel Stardom
AMI MODISPACES LLP
Chandak Treesourus
CHANDAK REALTORS PRIVATE LIMITED
ANCHORPOINT AVIARA
YUKTI INFRAPROJECTS LLP
AURIS ILARIA TOWER A
TRANSCON-SHETH CREATORS PRIVATE LIMITED
ADHRIT
MUNDARA DEVELOPERS
IRENE WING B PHASE 1
Sheth Creators and Sunvision Private Limit
See every Mumbai Suburban project, with the district possession charts
Builder: SIDDHARTH ENTERPRISES
SIDDHARTH ENTERPRISES has 3 registrations on MahaRERA, including Shreeji Plaza Wing A and Shreeji Plaza Wing B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Shreeji Plaza Wing A is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shreeji Plaza Wing A?
The registered promoter entity is SIDDHARTH ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shreeji Plaza Wing A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shreeji Plaza Wing A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shreeji Plaza Wing A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shreeji Plaza Wing A?
The professionals named in the filing: Architect: V S VAIDYA AND ASSOCIATES; Engineer: CNS CONSULTANTS; Chartered Accountant: NEHALI DHAVAL DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shreeji Plaza Wing A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback