Home / Browse projects / Thane, Maharashtra / SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6
SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6
RG-MH-12547 · RERA P51700000988 · Last updated on MahaRERA portal: 13 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 7 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6 is a Residential / Group Housing project by SHREE VIGNAHARTA DEVELOPER in Thane, Maharashtra, registered with MahaRERA as P51700000988 on 25 Jul 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 24 months from the original filing. 7 complaints are on record with the regulator.
At a glance
Project
- NameSHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6
- TypeResidential / Group Housing
- Location
- Diva Shill Road
- Dawle
- Thane (M Corp.)
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700000988
- ReraGenie IDRG-MH-12547
Builder
- NameSHREE VIGNAHARTA DEVELOPER
- Entity typePartnership
- PartnersMUSTAK SAIFAN SHAIKH, NAJMA MUSTAK SHAIKH
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on25 Jul 2017
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 30 Dec 2021)
- Buildings4 building records
- Documents filed87 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B3 | NA | 17 | 0 | 0 | 0 | 0 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B4 | NA | 16 | 0 | 0 | 0 | 0 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B5 | NA | 16 | 0 | 0 | 0 | 0 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B6 | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 13 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
24 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 93%.
SHREE VIGNAHARTA RESIDENCY BUILDING NO B391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHREE VIGNAHARTA RESIDENCY BUILDING NO B491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHREE VIGNAHARTA RESIDENCY BUILDING NO B556%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 93% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHREE VIGNAHARTA RESIDENCY BUILDING NO B69%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B3 | 1 | 1 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B4 | 1 | 1 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B5 | 1 | 1 |
| SHREE VIGNAHARTA RESIDENCY BUILDING NO B6 | 1 | 1 |
Land and ownership5
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BHARAT KRISHNA ALIMKAR | Thane (M Corp.) | Thane |
| GOPAL ARJUN MHATRE | Thane (M Corp.) | Thane |
| KATHOD ZIPRYA KHARPATIL | Thane (M Corp.) | Thane |
| RAKHMABAI KATHOD KHARPATIL | Thane (M Corp.) | Thane |
| BHAGWAN KACHRU KHARPATIL | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMEER S LOTKE AND ASSOCIATES |
| Engineer | AJAY MAHALE AND ASSOCIATES |
| Engineer | SHRAVANI CONSULTANTS BAHUBALI TATYASO DHAMANE |
| Partner | Role in project |
|---|---|
| SHREE VIGNAHARTA DEVELOPER | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project is situated at newly developing area Diva Junction which is away from Thane City having lack of infrastructure namely water , electricity, road transport and drainage etc . Developers are facing various issues pertaining to project development. Further, COVID 19 outbreak has added fuel to the fire and the purchasing power of the middle class group is highly impacted on account of loss of job opportunities. Our project mainly caters to affordable housing having middle and lower middle class as our prospective customers. Due to this entire cash flow has been affected resulting in del
Reason as filed by the promoterThis application is u/s 6 of the Act for getting extension without consent of the allottee. The original timeline for completion of the project was 31-12-2020 and developer got suo moto covid 19 extension from maharera for one year and accordingly revised time line for completion is now 30-12-2021 after covid extension of one year. Developers are facing various issues pertaining to project development. Further, COVID 19 outbreak has added fuel to the fire and the purchasing power of the middle class group is highly impacted on account of loss of job opportunities. Our project mainly caters to
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001710 | Navnath kharpatil | M/s. Vignaharta Developers | 04/11/2017 |
| CC006000000001768 | ARJUN KACHRU KHARPATIL | M/S. VIGNAHARTA DEVELOPERS | 06/11/2017 |
| CC006000000171857 | Vishal Palekar | Mr. Mustak Shaikh | 24/01/2020 |
| CC12500746 | Jigna Ashwin Shah | SHREE VIGNAHARTA DEVELOPER | 05/03/2025 |
| CC12500747 | Ashwin Bhavanji Shah | SHREE VIGNAHARTA DEVELOPER | 05/03/2025 |
| CC12500808 | SUNNY VINODKUMAR SHARMA | SHREE VIGNAHARTA DEVELOPER | 09/03/2025 |
| CC12503227 | SUNNY VINODKUMAR SHARMA | SHREE VIGNAHARTA DEVELOPER | 12/09/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Dec 2022
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: Self Declaration-SVD.pdf | 13 Jan 2025 |
| CERSAI detailsFile: Aeest Based Report- SVD.pdf | 13 Jan 2025 |
| CERSAI detailsFile: Debtor Based Report- SVD.pdf | 13 Jan 2025 |
| Details of encumbrances concerned to LegalFile: Self Declaration-SVD.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: unsod sold Dec 2023 vignaharta.pdf | 13 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31-12-2023.pdf | 24 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 31-12-2023.pdf | 24 Feb 2024 |
| Declaration in FORM BFile: Form B Vighnaharta.pdf | 22 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- 31-12-23-SVD.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Vignaharta Developer - Sold-Unsold.pdf | 22 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 30-09-2023.pdf | 22 Feb 2024 |
| Certificates of CA (Form 5)File: SVD Form 5 2022 - 23 Sign.pdf | 22 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shree Vignaharta Developer Form 1.pdf | 5 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Shree Vighnaharta Developers Form 2A FY 23.pdf | 11 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SVD Form 5 2022 - 23 Sign.pdf | 11 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 22-23.pdf | 8 May 2023 |
| Certificates of CA (Form 5)File: Letter for form5_22-23.pdf | 8 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold List.pdf | 27 Mar 2023 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 27 Mar 2023 |
| Proforma of Agreement for saleFile: Agreement for Sale.pdf | 27 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: SVD No Diviation Allotment Letter B3, B4, B5, B6.pdf | 27 Mar 2023 |
| Deviation Report with respect to model copy of AgreementFile: Agreement for Sale.pdf | 27 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 21 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf | 20 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf | 20 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Shree Vignaharta Developer Form 2A.pdf | 22 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SVD disclosure of interest in real estate - Najma Shaikh.pdf | 30 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SVD Disclosure of Interest Mustak Shaikh.pdf | 30 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: SVD Declaration of No encumbrance legal.pdf | 28 Jan 2023 |
| Details of encumbrances concerned to LegalFile: SVD Declaration of No encumbrance legal.pdf | 28 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SVD Format A SEparate Bank Account.pdf | 28 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 6 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B4 - Occupancy Certificate.pdf | 27 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A signed_compressed.pdf | 24 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A signed_compressed.pdf | 24 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Declaration.pdf | 22 Jan 2022 |
| CERSAI detailsFile: VIGNAHARTA CERSAI.pdf | 21 Dec 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SVD Society Formation.pdf | 21 Dec 2021 |
| Status of ConveyanceFile: SVD Conveyance.pdf | 21 Dec 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Exhibit C_compressed.pdf | 9 Dec 2021 |
| Declaration about Commencement CertificateFile: CC Declaration SVD.pdf | 8 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: SVD Sold unsold_compressed.pdf | 8 Nov 2021 |
| Details of Restarting of Construction work post lockdownFile: vighnaharta declaration work halt.pdf | 26 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SVD3456_FORM 5_2018-19_Scan.PDF | 8 Nov 2019 |
| Certificates of CA (Form 5)File: Shree Vighnaharta Developer B3,B4,B5, B6.pdf | 29 Sep 2018 |
| Building plan approvalFile: 1.pdf | 22 Jul 2017 |
| Building plan approvalFile: 2.pdf | 22 Jul 2017 |
| Building plan approvalFile: B3.pdf | 22 Jul 2017 |
| Building plan approvalFile: B4.pdf | 22 Jul 2017 |
| Building plan approvalFile: B5.pdf | 22 Jul 2017 |
| Building plan approvalFile: B6.pdf | 22 Jul 2017 |
| Building plan approvalFile: Club House.pdf | 22 Jul 2017 |
| Layout approvalFile: LAYOUT.pdf | 22 Jul 2017 |
| PAN CardFile: SVD.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: 01.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: 02.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: 03.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: 04.pdf | 22 Jul 2017 |
| Details of encumbrancesFile: SVD.pdf | 22 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 1.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: 2.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: B3.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: B4.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: B5.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: B6.pdf | 22 Jul 2017 |
| Building Plan Approval (IOD)File: Club House.pdf | 22 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: SVD.pdf | 22 Jul 2017 |
| Declaration in FORM BFile: Mustak Shaikh SVD.pdf | 22 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SVD.pdf | 22 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SVD.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: Certificate.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: addi info0001.PDF | 22 Jul 2017 |
| Certificates of CA (Form 3)File: annex A1.pdf | 22 Jul 2017 |
| Certificates of CA (Form 3)File: annex A2.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: Allotement letter.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: 1.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: 2.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: 3.pdf | 22 Jul 2017 |
| Proforma of Allotment letterFile: 4.pdf | 22 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHREE VIGNHARTA RESIDENCY BUILDING NO B1 B2 | KHARDI PADA DIVA SHILL ROAD DAWALE THANE 400 612 | 56 | Completed | Mar 2016 | Late, Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dawle7,600+ in Thane
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: SHREE VIGNAHARTA DEVELOPER
SHREE VIGNAHARTA DEVELOPER has 1 registration on MahaRERA, including SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6 is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
The registered promoter entity is SHREE VIGNAHARTA DEVELOPER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
The professionals named in the filing: Architect: SAMEER S LOTKE AND ASSOCIATES; Engineer: AJAY MAHALE AND ASSOCIATES; Engineer: SHRAVANI CONSULTANTS BAHUBALI TATYASO DHAMANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback