Home / Browse projects / Raigarh, Maharashtra / SHREE SIDDHIVINAYAK RESIDENCY
SHREE SIDDHIVINAYAK RESIDENCY
RG-MH-36943 · RERA P52000030593 · Last updated on MahaRERA portal: 2 Jun 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE SIDDHIVINAYAK RESIDENCY is a Residential / Group Housing project by MANGALMAY REALTIES in Raigarh, Maharashtra, registered with MahaRERA as P52000030593 on 1 Sep 2021. The registration is recorded completed; possession was promised by 31 Dec 2023.
At a glance
Project
- NameSHREE SIDDHIVINAYAK RESIDENCY
- TypeResidential / Group Housing
- Location
- UTKARSH NAGAR
- PEN
- Pen (M Cl)
- Raigarh
- 402107
- Pincode402107
- RERA no.P52000030593
- ReraGenie IDRG-MH-36943
Builder
- NameMANGALMAY REALTIES
- Entity typePartnership
- PartnerMAMTA MANISH JAIN
- Other registrations2 more →
- Completed1 of 3
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on1 Sep 2021
- Promised completion31 Dec 2023
- Revised completionNone
- Buildings3 building records
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 8 | 0 | 0 | 0 | 0 |
| WING B | NA | 8 | 0 | 0 | 0 | 0 |
| WING C | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 2 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 33 construction stages are filed complete across 3 buildings.
WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING A | 0 | 7 | 7 |
| WING B | 1 | 7 | 8 |
| WING C | 1 | 9 | 10 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GEETA KATWE |
| Engineer | STRUCON CONSULTING ENGINEERS |
| Chartered Accountant | NEHA VIRA |
| Partner | Role in project |
|---|---|
| MANGALMAY REALTIES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Jun 2025
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for | 2 Jun 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for | 27 Mar 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: organized (82).pdf | 18 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC CERTIFICATE-18-08-2023.pdf | 18 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate OK.pdf | 22 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (2).pdf | 22 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance certificate no-2A.pdf | 22 May 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY OK1.pdf | 22 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 22 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Phase 1.pdf | 22 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Phase 1.pdf | 29 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 1 Dec 22 Architect's certificate.pdf | 21 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate (Dec 22) .pdf | 21 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg 31032022.pdf | 21 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June 22 Engineer Certificate.pdf | 21 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sept 22 Engineer certificate.pdf | 21 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I Dec 22 A B AND C_compressed.pdf | 21 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 1 Architect's certificate Jun 22.pdf | 20 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 1 Architect's certificate Sep 22.pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I March 22 A B AND C_compressed.pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I June 22 A wing inventory details .pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I June 22 B wing inventory details .pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I June 22 C wing inventory details .pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I Sept 22 A wing Inventory.pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I Sept 22 B wing Inventory.pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Phase I Sept 22 C wing Inventory.pdf | 20 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase-1 Form -3 March22_compressed.pdf | 20 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase -1Form-3 June22_compressed.pdf | 20 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase-1 Form-3 Sep 22 _compressed.pdf | 20 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase -1 Form-3 Dec22_compressed.pdf | 20 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 1 Architect Certificate.pdf | 8 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 (Phase1).pdf | 25 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH mangalmay pen rera.pdf | 24 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG rera pen 1 p3.pdf | 24 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: rera pen 1 p2.pdf | 8 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH phase 1_compressed.pdf | 7 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: phase 1 (3)_compressed.pdf | 6 Oct 2021 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 26 Aug 2021 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 23 Aug 2021 |
| Layout approvalFile: Building Layout_compressed_compressed.pdf | 11 Aug 2021 |
| Building plan approvalFile: 1 to 3 compress.pdf | 11 Aug 2021 |
| Building plan approvalFile: 4 to 6 compress.pdf | 11 Aug 2021 |
| PAN CardFile: Mangalmay Realties Pan Card.pdf | 11 Aug 2021 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 11 Aug 2021 |
| Details of encumbrancesFile: Encumbrance letter.pdf | 11 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: Building Layout_compressed_compressed.pdf | 11 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 to 3 compress.pdf | 11 Aug 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 to 6 compress.pdf | 11 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 11 Aug 2021 |
| Declaration about Commencement CertificateFile: COMMENCEMENT DECLARATION.pdf | 11 Aug 2021 |
| Declaration in FORM BFile: Form B.pdf | 11 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE PHASE 1.pdf | 11 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vimal solanki Associates.pdf | 11 Aug 2021 |
| Proforma of Allotment letterFile: Allotment Letter Format Shree Siddhivinay Residency-converted.pdf | 11 Aug 2021 |
| Proforma of Allotment letterFile: Phase 1 Agreement.pdf | 11 Aug 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
Keep SHREE SIDDHIVINAYAK RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PEN5,900+ in Raigarh
HAWARE GRANDE
HAWARE GRANDE
KALINDI ELITE
KALINDI REALTORS PRIVATE LIMITED
GOKUL
SUYASH BUILDERS AND DEVELOPERS
OSCAR HEIGHTS
OSCAR BUILDERS
dbafna ONE
D Bafna Properties
MITHILA
SATHE SCHEMES LLP
See every Raigarh project, with the district possession charts
Builder: MANGALMAY REALTIES
MANGALMAY REALTIES has 3 registrations on MahaRERA, including SHREE SIDDHIVINAYAK RESIDENCY and SHREE SIDDHIVINAYAK RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SHREE SIDDHIVINAYAK RESIDENCY is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE SIDDHIVINAYAK RESIDENCY?
The registered promoter entity is MANGALMAY REALTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE SIDDHIVINAYAK RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE SIDDHIVINAYAK RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE SIDDHIVINAYAK RESIDENCY?
The professionals named in the filing: Architect: GEETA KATWE; Engineer: STRUCON CONSULTING ENGINEERS; Chartered Accountant: NEHA VIRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE SIDDHIVINAYAK RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback