ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED

Registration lapsed No litigation declared Residential / Group Housing project

SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED

By RAJLAXMI SAMARTH DEVELOPERS

RG-MH-59707 · RERA P51700032714 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
38 of 59Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 154 documents Report an error

SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED is a Residential / Group Housing project by RAJLAXMI SAMARTH DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700032714 on 24 Jan 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 21 of the 59 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED
  • TypeResidential / Group Housing
  • Location
    • BELAVALI
    • AMBERNATH
    • Belvali
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700032714
  • ReraGenie IDRG-MH-59707

Builder

  • NameRAJLAXMI SAMARTH DEVELOPERS
  • Entity typePartnership
  • PartnerJAYWANTI JANARDAN GAIKWAD

Key dates

4 months past promisethis monthRegisteredJan 2022First promiseDec 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jan 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed154 files

Current status

36%21 of 59 units booked
99.1%Work done, per cost certificate

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE SAMARTH KRUPA PRASAD A WINGNA7636339
SHREE SAMARTH KRUPA PRASAD B WINGNA6520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

SHREE SAMARTH KRUPA PRASAD A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SHREE SAMARTH KRUPA PRASAD B WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered53
Open Space15
BuildingClosed/CoveredOpen SpaceTotal
SHREE SAMARTH KRUPA PRASAD A WING121527
SHREE SAMARTH KRUPA PRASAD B WING41041

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area910 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Apr 2026
LandownerVillageDistrict
Shree Samarth Krupa Prasad Co Operative Hsg Soc LtAmbarnath(M Cl)Thane

Approvals and building plan

Permissible FSI2480.65
Proposed, not sanctioned2,466 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYAN MALANG ROAD
Estimated costRs 4.51 cr
Cost incurredRs 4.47 cr
Work done99.09%
BuildingWingEstimatedIncurred
SHREE SAMARTH KRUPA PRASAD A WINGNARs 2.79 crRs 2.79 cr
SHREE SAMARTH KRUPA PRASAD B WINGNARs 1.46 crRs 1.44 cr
-NARs 26.55 lakhRs 23.89 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJ ASSOCIATE
EngineerATUL KUDTARKAR AND ASSOCIATE PVT LTD
EngineerRAGHAVENDRA WAKHARE
Chartered AccountantSAWANT AND KADREKAR LLP
Chartered AccountantGODSE AND ASSOCIATES
PartnerRole in project
RAJLAXMI SAMARTH DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24032620348Dec 2025 → Jun 2026

Reason as filed by the promoterDear Team, our project is completed and oc also received we would like to update our pending details in project tab, so we request you to please extend our project date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed154

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: FORM 5 31-03-2026.pdf14 Aug 2026
Form 5 (FY 2021-2022)File: FORM 5 31-03-2022.pdf13 Aug 2026
Form 2A (FY 2021-2022)File: form 2A 31032022.pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A-31032025.pdf10 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf31 Jul 2026
Building plan approvalFile: Sanctioned OC Building Plan dt 31 dec 2025.pdf15 Jun 2026
Building plan approvalFile: Completion Plan.pdf16 May 2026
Withdrawal Update Form 1File: Form 1.pdf14 May 2026
Withdrawal Update Form 2File: Form 2.pdf14 May 2026
Withdrawal Update Form 3File: Form 3.pdf14 May 2026
Form 2A (FY 2022-2023)File: Form 2A.pdf14 May 2026
Form 2A (FY 2023-2024)File: Form 2A.pdf14 May 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf14 May 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf2 Apr 2026
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf2 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf2 Apr 2026
Withdrawal Update Form 1File: Form 1 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 1File: Form 1 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 1File: Q 1 Form 1 April 25 to june 25.pdf9 Mar 2026
Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 1File: Q 3 Form 1 Oct 25 to Dec 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Form 2 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 2File: Form 2 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 2File: Q 1 Form 2 April 25 to june 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 2File: Q 3 Form 2 Oct 25 to Dec 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Oct 23 to Dec 23.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Q 1 April 25 to June 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf9 Mar 2026
Withdrawal Update Form 3File: Form 3 Q 3 Oct 25 to Dec 25.pdf9 Mar 2026
Form 1File: Q 4 Form 1 Jan 22 to March 22.pdf7 Feb 2026
Form 2File: Q 4 Jan 22 to March 22.pdf7 Feb 2026
Form 3File: Q 4 Form 3 Jan 22 to Mar 22.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 4 Sold Inventory Jan 22 to March 22.pdf7 Feb 2026
Form 1File: Q 1 Form 1 Apr 22 to June 22.pdf7 Feb 2026
Form 2File: Q 1 Form 2 Apr 22 to June 22.pdf7 Feb 2026
Form 3File: Q 1 Form 3 Apr 22 to June 22.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 1 Sold Inventory April 22 to June 22.pdf7 Feb 2026
Form 1File: Q 2 Form 1 July 22 to Sep 22.pdf7 Feb 2026
Form 2File: Q 2 Form 2 Jul 22 to Sep 22.pdf7 Feb 2026
Form 3File: Q 2 Form 3 July 22 to Sep 22.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 2 Sold INventory July 22 to Sep 22.pdf7 Feb 2026
Form 1File: Q 3 Form 1 Oct 22 to Dec 22.pdf7 Feb 2026
Form 2File: Q 3 Form 2 Oct 22 to Dec 22.pdf7 Feb 2026
Form 3File: Q 3 Form 3 Oct 22 to Dec 22.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 3 Sold Inventory Oct 22 to Dec 22.pdf7 Feb 2026
Form 1File: Q 4 Form 1 Jan 23 to Mar 23.pdf7 Feb 2026
Form 2File: Q 4 Form 2 Jan 23 to Mar 23.pdf7 Feb 2026
Form 3File: Q 4 Form 3 Jan 23 to Mar 23.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 4 Sold Inventory Jan 23 to March 23.pdf7 Feb 2026
Form 1File: Q 1 Form 1 Apr 23 to Jun 23.pdf7 Feb 2026
Form 2File: Q 1 Form 2 Apr 23 to Jun 23.pdf7 Feb 2026
Form 3File: Q 1 Form 3 April 23 to June 23.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 1 Sold April 23 to June 23.pdf7 Feb 2026
Form 1File: Q 2 Form 1 July 23 to Sep 23.pdf7 Feb 2026
Form 2File: Q 2 Form 2 Jul 23 to Sep 23.pdf7 Feb 2026
Form 3File: Q 2 Form 3 July 23 to Sep 23.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 2 Sold July 23 to Sep 23.pdf7 Feb 2026
Form 1File: Q 3 Form 1 oct 23 to Dec 23.pdf7 Feb 2026
Form 2File: Q 3 Form 2 Oct 23 to Dec 23.pdf7 Feb 2026
Form 3File: Q 3 Form 3 Oct 23 to Dec 23.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 3 Sol Oct 23 to Dec 23.pdf7 Feb 2026
Form 1File: Q 4 Form 1 Jan 24 to Mar 24.pdf7 Feb 2026
Form 2File: Q 4 Form 2 Jan 24 to Mar 24.pdf7 Feb 2026
Form 3File: Q 4 Form 3 Jan 24 to Mar 24.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 4 Sold Jan 24 to Mar 24.pdf7 Feb 2026
Form 1File: Q 1 Form 1 Apr 24 to Jun 24.pdf7 Feb 2026
Form 2File: Q 1 Form 2 April 24 to June 24.pdf7 Feb 2026
Form 3File: Q 1 Form 3 April 24 to June 24.pdf7 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q 1 Sold inventory April 24 to June 24.pdf7 Feb 2026
Form 1File: Q 2 Form 1 July 24 to Sep 24.pdf7 Feb 2026

How this compares with Thane

36%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 6 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBERNATH7,600+ in Thane

2 kmSHREE SAMARTH KRUPA PRASCompleted 59Lapsed / revoked 33Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: RAJLAXMI SAMARTH DEVELOPERS

RAJLAXMI SAMARTH DEVELOPERS has 1 registration on MahaRERA, including SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?

The registered promoter entity is RAJLAXMI SAMARTH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?

The professionals named in the filing: Architect: RAJ ASSOCIATE; Engineer: ATUL KUDTARKAR AND ASSOCIATE PVT LTD; Engineer: RAGHAVENDRA WAKHARE; Chartered Accountant: SAWANT AND KADREKAR LLP; Chartered Accountant: GODSE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.