SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED
By RAJLAXMI SAMARTH DEVELOPERS
RG-MH-59707 · RERA P51700032714 · Last updated on MahaRERA portal: 14 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED is a Residential / Group Housing project by RAJLAXMI SAMARTH DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700032714 on 24 Jan 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 21 of the 59 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.
At a glance
Project
- NameSHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED
- TypeResidential / Group Housing
- Location
- BELAVALI
- AMBERNATH
- Belvali
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700032714
- ReraGenie IDRG-MH-59707
Builder
- NameRAJLAXMI SAMARTH DEVELOPERS
- Entity typePartnership
- PartnerJAYWANTI JANARDAN GAIKWAD
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Jan 2022
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed154 files
Current status
Figures as on 14 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE SAMARTH KRUPA PRASAD A WING | NA | 7 | 6 | 36 | 3 | 39 |
| SHREE SAMARTH KRUPA PRASAD B WING | NA | 6 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
SHREE SAMARTH KRUPA PRASAD A WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHREE SAMARTH KRUPA PRASAD B WING91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed68
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SHREE SAMARTH KRUPA PRASAD A WING | 12 | 15 | 27 |
| SHREE SAMARTH KRUPA PRASAD B WING | 41 | 0 | 41 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Shree Samarth Krupa Prasad Co Operative Hsg Soc Lt | Ambarnath(M Cl) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREE SAMARTH KRUPA PRASAD A WING | NA | Rs 2.79 cr | Rs 2.79 cr |
| SHREE SAMARTH KRUPA PRASAD B WING | NA | Rs 1.46 cr | Rs 1.44 cr |
| - | NA | Rs 26.55 lakh | Rs 23.89 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJ ASSOCIATE |
| Engineer | ATUL KUDTARKAR AND ASSOCIATE PVT LTD |
| Engineer | RAGHAVENDRA WAKHARE |
| Chartered Accountant | SAWANT AND KADREKAR LLP |
| Chartered Accountant | GODSE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| RAJLAXMI SAMARTH DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Team, our project is completed and oc also received we would like to update our pending details in project tab, so we request you to please extend our project date.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Feb 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed154
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: FORM 5 31-03-2026.pdf | 14 Aug 2026 |
| Form 5 (FY 2021-2022)File: FORM 5 31-03-2022.pdf | 13 Aug 2026 |
| Form 2A (FY 2021-2022)File: form 2A 31032022.pdf | 10 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A-31032025.pdf | 10 Aug 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 31 Jul 2026 |
| Building plan approvalFile: Sanctioned OC Building Plan dt 31 dec 2025.pdf | 15 Jun 2026 |
| Building plan approvalFile: Completion Plan.pdf | 16 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 14 May 2026 |
| Form 2A (FY 2022-2023)File: Form 2A.pdf | 14 May 2026 |
| Form 2A (FY 2023-2024)File: Form 2A.pdf | 14 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 14 May 2026 |
| Form 5 (FY 2022-2023)File: Form 5 22-23.pdf | 2 Apr 2026 |
| Form 5 (FY 2023-2024)File: Form 5 23-24.pdf | 2 Apr 2026 |
| Form 5 (FY 2024-2025)File: Form 5 24-25.pdf | 2 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Q 1 Form 1 April 25 to june 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Q 2 Form 1 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Q 3 Form 1 Oct 25 to Dec 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Q 1 Form 2 April 25 to june 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Q 2 Form 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 2File: Q 3 Form 2 Oct 25 to Dec 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Oct 23 to Dec 23.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q 1 April 25 to June 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q 2 July 25 to Sep 25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Q 3 Oct 25 to Dec 25.pdf | 9 Mar 2026 |
| Form 1File: Q 4 Form 1 Jan 22 to March 22.pdf | 7 Feb 2026 |
| Form 2File: Q 4 Jan 22 to March 22.pdf | 7 Feb 2026 |
| Form 3File: Q 4 Form 3 Jan 22 to Mar 22.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 4 Sold Inventory Jan 22 to March 22.pdf | 7 Feb 2026 |
| Form 1File: Q 1 Form 1 Apr 22 to June 22.pdf | 7 Feb 2026 |
| Form 2File: Q 1 Form 2 Apr 22 to June 22.pdf | 7 Feb 2026 |
| Form 3File: Q 1 Form 3 Apr 22 to June 22.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 1 Sold Inventory April 22 to June 22.pdf | 7 Feb 2026 |
| Form 1File: Q 2 Form 1 July 22 to Sep 22.pdf | 7 Feb 2026 |
| Form 2File: Q 2 Form 2 Jul 22 to Sep 22.pdf | 7 Feb 2026 |
| Form 3File: Q 2 Form 3 July 22 to Sep 22.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 2 Sold INventory July 22 to Sep 22.pdf | 7 Feb 2026 |
| Form 1File: Q 3 Form 1 Oct 22 to Dec 22.pdf | 7 Feb 2026 |
| Form 2File: Q 3 Form 2 Oct 22 to Dec 22.pdf | 7 Feb 2026 |
| Form 3File: Q 3 Form 3 Oct 22 to Dec 22.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 3 Sold Inventory Oct 22 to Dec 22.pdf | 7 Feb 2026 |
| Form 1File: Q 4 Form 1 Jan 23 to Mar 23.pdf | 7 Feb 2026 |
| Form 2File: Q 4 Form 2 Jan 23 to Mar 23.pdf | 7 Feb 2026 |
| Form 3File: Q 4 Form 3 Jan 23 to Mar 23.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 4 Sold Inventory Jan 23 to March 23.pdf | 7 Feb 2026 |
| Form 1File: Q 1 Form 1 Apr 23 to Jun 23.pdf | 7 Feb 2026 |
| Form 2File: Q 1 Form 2 Apr 23 to Jun 23.pdf | 7 Feb 2026 |
| Form 3File: Q 1 Form 3 April 23 to June 23.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 1 Sold April 23 to June 23.pdf | 7 Feb 2026 |
| Form 1File: Q 2 Form 1 July 23 to Sep 23.pdf | 7 Feb 2026 |
| Form 2File: Q 2 Form 2 Jul 23 to Sep 23.pdf | 7 Feb 2026 |
| Form 3File: Q 2 Form 3 July 23 to Sep 23.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 2 Sold July 23 to Sep 23.pdf | 7 Feb 2026 |
| Form 1File: Q 3 Form 1 oct 23 to Dec 23.pdf | 7 Feb 2026 |
| Form 2File: Q 3 Form 2 Oct 23 to Dec 23.pdf | 7 Feb 2026 |
| Form 3File: Q 3 Form 3 Oct 23 to Dec 23.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 3 Sol Oct 23 to Dec 23.pdf | 7 Feb 2026 |
| Form 1File: Q 4 Form 1 Jan 24 to Mar 24.pdf | 7 Feb 2026 |
| Form 2File: Q 4 Form 2 Jan 24 to Mar 24.pdf | 7 Feb 2026 |
| Form 3File: Q 4 Form 3 Jan 24 to Mar 24.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 4 Sold Jan 24 to Mar 24.pdf | 7 Feb 2026 |
| Form 1File: Q 1 Form 1 Apr 24 to Jun 24.pdf | 7 Feb 2026 |
| Form 2File: Q 1 Form 2 April 24 to June 24.pdf | 7 Feb 2026 |
| Form 3File: Q 1 Form 3 April 24 to June 24.pdf | 7 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Q 1 Sold inventory April 24 to June 24.pdf | 7 Feb 2026 |
| Form 1File: Q 2 Form 1 July 24 to Sep 24.pdf | 7 Feb 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 154 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AMBERNATH7,600+ in Thane
Filed coordinates, straight-line distance. 127 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: RAJLAXMI SAMARTH DEVELOPERS
RAJLAXMI SAMARTH DEVELOPERS has 1 registration on MahaRERA, including SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?
The registered promoter entity is RAJLAXMI SAMARTH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?
The professionals named in the filing: Architect: RAJ ASSOCIATE; Engineer: ATUL KUDTARKAR AND ASSOCIATE PVT LTD; Engineer: RAGHAVENDRA WAKHARE; Chartered Accountant: SAWANT AND KADREKAR LLP; Chartered Accountant: GODSE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback