ReraGenieLog inGet a buyer report

Home / Browse projects / Dadra & Nagar Haveli / SHREE SAKHA SADAN

Registration lapsed No litigation declared Mixed project

SHREE SAKHA SADAN

By SHREE SAKHA DEVELOPERS PRIVATE LIMITED

RG-MH-00610 · RERA P49600000059 · Last updated on MahaRERA portal: 24 May 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 55 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Mar 2022Possession promised55 months past this date
7 of 22Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 44%
120 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

SHREE SAKHA SADAN is a Mixed project by SHREE SAKHA DEVELOPERS PRIVATE LIMITED in Dadra & Nagar Haveli, registered with MahaRERA as P49600000059 on 7 Aug 2018. Possession was promised by 10 Mar 2022 and is now 55 months past that date. The completion date has moved by 18 months from the original filing. 0 of the 120 units on this registration are recorded sold or booked, and 7 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREE SAKHA SADAN
  • TypeMixed
  • Location
    • 235/1/2
    • NEAR JAIN TEMPLE
    • SILVASSA-VAPI ROAD
    • DADRA
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000059
  • ReraGenie IDRG-MH-00610

Builder

  • NameSHREE SAKHA DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45201GJ2011PTC067686
  • DirectorAPOORVE RAJENDRA TALERA

Key dates

55 months past promisethis monthRegisteredAug 2018First promiseSep 2020Revised toMar 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2018
  • Promised completion10 Mar 2022
  • Revised completionRevised to 10 Mar 2022 (originally 30 Sep 2020)
  • Buildings2 building records
  • Documents filed28 files

Current status

0%0 of 120 units booked
81.2%Work done, per cost certificate

Figures as on 24 May 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA11049655
B BUILDINGNA12064064

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 44%.

A BUILDING40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure44%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B BUILDING31%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
A BUILDING11
B BUILDING11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,000 sq m
Land owned byThe promoter
Named landownersNone
Declared on27 Sep 2024

Approvals and building plan

Permissible FSI5367.9
Proposed, not sanctioned5,368 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR EMPEROR ARCADE HIGH LAND PARK CO OP SOCIETY DAMAN ROAD CHALA VAPI
Estimated costRs 18.53 cr
Cost incurredRs 15.05 cr
Work done81.25%
BuildingWingEstimatedIncurred
NA Plot Without StructureNARs 9.26 crRs 9.26 cr
A BUILDINGNARs 5.56 crRs 3.47 cr
B BUILDINGNARs 3.71 crRs 2.32 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKa Architecture
ArchitectPramod Joshi
EngineerMR Sachin Doshi
Chartered AccountantR.K
Chartered AccountantAditya P Shah & Co.
PartnerRole in project
SHREE SAKHA DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT49600024674Sep 2020 → Mar 2022

Reason as filed by the promoterDue to COVID-19 pandamic.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: Occupancy Certificate.pdf24 May 2024
Layout approvalFile: PDF 1.pdf31 Jul 2018
Building plan approval or NA orderFile: PDF 2.pdf31 Jul 2018
Building plan approval or NA orderFile: PDF 3.pdf31 Jul 2018
Building plan approval or NA orderFile: PDF 4.pdf31 Jul 2018
Building plan approval or NA orderFile: PDF 5.pdf31 Jul 2018
Building plan approval or NA orderFile: PDF 6.pdf31 Jul 2018
Details of encumbrancesFile: Encum.pdf31 Jul 2018
Copy of Layout Approval (in case of layout)File: PDF 1.pdf31 Jul 2018
Building Plan Approval (IOD)File: PDF 2.pdf31 Jul 2018
Building Plan Approval (IOD)File: PDF 3.pdf31 Jul 2018
Building Plan Approval (IOD)File: PDF 4.pdf31 Jul 2018
Building Plan Approval (IOD)File: PDF 5.pdf31 Jul 2018
Building Plan Approval (IOD)File: PDF 6.pdf31 Jul 2018
Commencement CertificatesFile: CP-min.pdf31 Jul 2018
Certificates of CA (Form 3) (UT)File: CA FORM 3 - PDF.pdf31 Jul 2018
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: FY 14-15.pdf31 Jul 2018
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: FINANCIAL(2016-17).pdf31 Jul 2018
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: 16-17 Ackno.pdf31 Jul 2018
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: AC FY 15-16.pdf31 Jul 2018
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: STAT fy 15-16.pdf31 Jul 2018
PAN CardFile: Pan Card.pdf29 Jul 2018
Copy of the legal title reportFile: TCR.pdf29 Jul 2018
Declaration in FORM BFile: compressed_Form B1.pdf29 Jul 2018
Declaration in FORM BFile: compressed_FORM B2.pdf29 Jul 2018
Declaration in FORM BFile: compressed_FORM B3.pdf29 Jul 2018
Certificates of Architect (Form 1) (UT)(Mandatory for only ongoing project)File: rera form 1.pdf29 Jul 2018
Proforma of Allotment letterFile: AFS copy.pdf29 Jul 2018

How this compares with Dadra & Nagar Haveli

0%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one moved by 18 months
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is among them

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep SHREE SAKHA SADAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SILVASSA-VAPI ROAD, DADRA210+ in Dadra & Nagar Haveli

2 kmSHREE SAKHA SADANCompleted 23Lapsed / revoked 17Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: SHREE SAKHA DEVELOPERS PRIVATE LIMITED

SHREE SAKHA DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including SHREE SAKHA SADAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What does it mean that SHREE SAKHA SADAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE SAKHA SADAN is delayed beyond 10 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SAKHA SADAN?

The registered promoter entity is SHREE SAKHA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45201GJ2011PTC067686 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SAKHA SADAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SAKHA SADAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SAKHA SADAN?

The professionals named in the filing: Architect: VKa Architecture; Architect: Pramod Joshi; Engineer: MR Sachin Doshi; Chartered Accountant: R.K; Chartered Accountant: Aditya P Shah & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SAKHA SADAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SAKHA SADAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SAKHA SADAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.