Home / Browse projects / Udupi, Karnataka / Shree Navadurga
Shree Navadurga
RG-KA-25582 · RERA PRM/KA/RERA/1273/319/PR/200205/003249 · Last updated on RERA Karnataka portal: 23 Jan 2020
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Shree Navadurga is a Mixed Development project by Sri Durga Associates in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/319/PR/200205/003249 on 5 Feb 2020. Possession is promised by 12 May 2023. The completion date has moved by 9 months from the original filing. 0 of the 26 units on this registration are recorded sold or booked, and 0 of 13 construction stages are filed complete.
At a glance
Project
- NameShree Navadurga
- TypeMixed Development
- Location
- Karkala
- Udupi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1273/319/PR/200205/003249
- ReraGenie IDRG-KA-25582
Builder
- NameSri Durga Associates
- Entity typePartnership Firm
- Authorized SignatoryN Sathyendra Bhat
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Feb 2020
- Promised completion12 May 2023
- Revised completionRevised to 12 May 2023 (originally 12 Aug 2022)
- Buildings1 building record
- Documents filed55 files
Current status
Figures as on 23 Jan 2020, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE NAVADURGA | - | - | - | - | - | 26 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 23 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 13 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.
Building: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | Not applicable |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
As on 23 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prakash Acharya M S |
| Engineer | M Gopal Bhat |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed55
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/319/PR/200205/003249 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Firm registration certificateFile: Firm registration certificate.pdf | 23 Jan 2020 |
| SANCTION PLANFile: SANCTION PLAN.pdf | 23 Jan 2020 |
| plan licence letterFile: plan licence letter.pdf | 23 Jan 2020 |
| development detailsFile: DEVELOPMENT DETAILS.pdf | 23 Jan 2020 |
| local water supply -NOCFile: local water supply NOC.pdf | 23 Jan 2020 |
| power supply-MESCOM NOCFile: power supply- MESCOM NOC.pdf | 23 Jan 2020 |
| PAYMENT RECIPT MESCOMFile: PAYMENT CHALLAN TEMPVERY CONECTION.jpeg | 23 Jan 2020 |
| Payment status for fees of Rs. 6070File: Challan acknowledgement.pdf | 7 Jan 2020 |
| Financial statementFile: NA - Since.pdf | 7 Jan 2020 |
| Notarised Form BFile: Notarised Form B.pdf | 7 Jan 2020 |
| Affidavit under section 3(1)File: Affidavit under section 3(1).pdf | 7 Jan 2020 |
| CertificateFile: Partnership deed.pdf | - |
| Commencement certificate | - |
| Approved building plan | - |
| Approved layout plan | - |
| Proforma sale deed | - |
| Proforma agreement for sale | - |
| Sale deed and Form 9 | - |
| Approved building plan | - |
| Approved building plan | - |
| Brochure of project | - |
| Brochure 2 | - |
| Encumbrance certificate | - |
| Khatha | - |
| Sale deed and Form 9 | - |
| 1 | - |
| Approved layout plan | - |
| Brochure 2 | - |
| 1 | - |
| Balance Sheet 2018 - 2019File: NA - Since.pdf | - |
| Balance Sheet 2017 - 2018File: NA - Since.pdf | - |
| Balance Sheet 2016 - 2017File: NA - Since.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: NA - Since.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: NA - Since.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: NA - Since.pdf | - |
| Director's Report 2018 - 2019File: NA - Since.pdf | - |
| Director's Report 2017 - 2018File: NA - Since.pdf | - |
| Director's Report 2016 - 2017File: NA - Since.pdf | - |
| Cash Flow Statement 2018 - 2019File: NA - Since.pdf | - |
| Cash Flow Statement 2017 - 2018File: NA - Since.pdf | - |
| Auditor's Report 2018 - 2019File: NA - Since.pdf | - |
| Auditor's Report 2017 - 2018File: NA - Since.pdf | - |
| Auditor's Report 2016 - 2017File: NA - Since.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: NA - Since.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: NA - Since.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: NA - Since.pdf | - |
| FORM B | - |
| Prospectus/BrochureFile: Navadurga Brochure.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1273_319_PR_200205_003249 (1).xlsx | - |
| Occupancy CertificateFile: occupancy certficate.jpeg | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: mescom.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: architect completion certficate.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: form 4 new ca certficate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT.pdf | - |
| ENGINEER CERTFICATEFile: engineer completion certificate.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep Shree Navadurga on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
GRASSLANDS - LAKESIDE
GRAZLANZ PROPERTIES LLP
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
KIRTHI PALMVILLE PHASE II
KIRTHI CONSTRUCTION
RAINTREE
VINIT S AMIN
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
Mandavi Casa Grande
J J Builders and Developers
See every Udupi project, with the district possession charts
Builder: Sri Durga Associates
Sri Durga Associates has 1 registration on RERA Karnataka, including Shree Navadurga. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if Shree Navadurga is delayed beyond 12 May 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Shree Navadurga?
The registered promoter entity is Sri Durga Associates, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Shree Navadurga?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Shree Navadurga?
The professionals named in the filing: Architect: Prakash Acharya M S; Engineer: M Gopal Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shree Navadurga?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback