ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2

Completed No litigation declared Plotted project

Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2

By M/s Shree Realtors

RG-MH-22966 · RERA P50500047391 · Last updated on MahaRERA portal: 19 Apr 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
23 of 31Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2 is a Plotted project by M/s Shree Realtors in Nagpur, Maharashtra, registered with MahaRERA as P50500047391 on 27 Oct 2022. The registration is recorded completed; possession was promised by 31 Mar 2025. 8 of the 31 units on this registration are recorded sold or booked.

At a glance

Project

  • NameShree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2
  • TypePlotted
  • Location
    • Lawa - Dawlameti State Highway
    • Near Lawa Chowk
    • Lavha
    • Nagpur (Rural)
    • Nagpur
    • 440023
  • Pincode440023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500047391
  • ReraGenie IDRG-MH-22966

Builder

  • NameM/s Shree Realtors
  • Entity typePartnership
  • PartnersVishakha Abhinav Welekar, Smita Pravin Dhiran, Gaurav Ishwarchandra Khosla, Pooja Atul Bhaiyya, Sushant Shishir Khangar, Saurabh Khosla HUF, Mansukhlal Vitthaldas saglani
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredOct 2022PromisedMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Oct 2022
  • Promised completion31 Mar 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed73 files

Current status

26%8 of 31 units booked

Figures as on 19 Apr 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes45%
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes35%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,599 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Sep 2024

Approvals and building plan

Sanctioning authorityNMRDA

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMahal Nagpur

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDivine projects
EngineerDivine Projects
Chartered AccountantDushyant Parekh & Co.
Chartered AccountantRahul panjwani & Co.
PartnerRole in project
M/s Shree Realtors-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Apr 2025

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Annexure-29 Sold Unsold Inventory 31-03-2025.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31-03-2025.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architech Certificate 31-03-2025.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer's Certificate 31-03-2025.pdf17 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Lava 28-1.pdf17 Apr 2025
Other - TechnicalFile: Screen shot Of CC.pdf17 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Mail1.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 31-12-2024.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Annexure-29 31-12-2024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dec-24 Laxmi Nagar-2.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architech Certificate 30-09-24.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer's Certificate 30-06-2024.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer's Certificate 30-09-2024.pdf25 Dec 2024
Disclosure of sold/ booked inventoryFile: Annexure-29 30-06-2024.pdf25 Dec 2024
Disclosure of sold/ booked inventoryFile: Annexure-29 30-09-2024.pdf25 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM-3 30-6-2024.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Binder1.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf17 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf8 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf8 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Shree Realtors Mar-24.pdf2 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 Shree Realtors 2023-24.pdf2 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-9.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture certificate 31-12.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-9.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Annexure 29 30-09-23.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: annexure 29.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_Form 3.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30-06-2023.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2 30-06-2023.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A.pdf21 Oct 2023
Disclosure of sold/ booked inventoryFile: Annexure 29 30-06-2023.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Annexure 29 30-09-23.pdf4 Oct 2023
Disclosure of sold/ booked inventoryFile: Annexure 29-31-03-2023.pdf22 Sep 2023
Disclosure of sold/ booked inventoryFile: Annexure 29 30-06-2023.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed.pdf22 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed.pdf22 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 signed.pdf22 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf25 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2.pdf25 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A.pdf25 May 2023
Disclosure of sold/ booked inventoryFile: Annexure 29- 31-3-23.pdf25 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20_NA order.pdf27 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form-3 Shree Realtors - Copy.pdf21 Oct 2022
Building plan approval or NA orderFile: 20_NA order.pdf13 Oct 2022
Layout approvalFile: 21_Map sanctioned by NA Department.pdf13 Oct 2022
Building plan approval or NA orderFile: 18_NMRDA Letter to Collector for NA.pdf13 Oct 2022
Copy of Layout Approval (in case of layout)File: 21_Map sanctioned by NA Department.pdf13 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: 20_NA order.pdf13 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: 18_NMRDA Letter to Collector for NA.pdf13 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: 20_NA order.pdf13 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: 18_NMRDA Letter to Collector for NA.pdf13 Oct 2022
PAN CardFile: Pan Card - Copy.pdf12 Oct 2022
Proforma of Agreement for saleFile: 8_Allotment letter.pdf12 Oct 2022
Proforma of Allotment letterFile: 8_Allotment letter.pdf12 Oct 2022
Proforma of Allotment letterFile: ATS with Sign.pdf12 Oct 2022
Proforma of Agreement for saleFile: ATS with Sign.pdf12 Oct 2022
Declaration about Commencement CertificateFile: 12_Circular 32.pdf10 Oct 2022
CERSAI detailsFile: 16_CERSAI_Search_Report_200248715411_For_Asset_Based_Search_01_10_2022_16_35_27_487.pdf10 Oct 2022
Copy of the legal title reportFile: Search Shree Realtors.pdf1 Oct 2022
Details of encumbrances concerned to FinanceFile: 5A Financial Encumbrance.pdf1 Oct 2022
Details of encumbrances concerned to LegalFile: 5B_Legal encumbrance.pdf1 Oct 2022
Declaration in FORM BFile: 6_Form B.pdf1 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 14_Declaration Bank Account.pdf1 Oct 2022
Deviation Report with respect to Allotment letterFile: 15_Deviation for Allotment Letter.pdf1 Oct 2022
Deviation Report with respect to model copy of AgreementFile: 13_Deviation for Model Agreement.pdf1 Oct 2022

How this compares with Nagpur

26%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Laxmi Nagar - 2 , Residential Layout P on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Lawa Chowk2,800+ in Nagpur

2 kmShree Laxmi Nagar - 2 , Completed 4Lapsed / revoked 1Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: M/s Shree Realtors

M/s Shree Realtors has 3 registrations on MahaRERA, including Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2 and Laxmi Nagar-3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2 is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2?

The registered promoter entity is M/s Shree Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2?

The professionals named in the filing: Architect: Divine projects; Engineer: Divine Projects; Chartered Accountant: Dushyant Parekh & Co.; Chartered Accountant: Rahul panjwani & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Laxmi Nagar - 2 , Residential Layout Plan for Kh No 28/1 and 28/2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Laxmi Nagar - 2 , Residential Layout P to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.