SHREE GOVIND KRUPA

By MAMTORA FOUNDATION

RG-MH-98307 · RERA P51800046222 · Last updated on MahaRERA portal: 14 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
9 of 11Construction stages donefurthest along: Basement (if any), 0%
63 of 78Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

SHREE GOVIND KRUPA is a Residential / Group Housing project by MAMTORA FOUNDATION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046222 on 20 Jun 2022. Possession was promised by 15 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 15 of the 78 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE GOVIND KRUPA
  • TypeResidential / Group Housing
  • Location
    • RAMCHANDRA LANE
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • RERA no.P51800046222
  • ReraGenie IDRG-MH-98307

Builder

  • NameMAMTORA FOUNDATION
  • Entity typePartnership
  • PartnersNATWARLAL MATHURADAS LAL, HARSHA NATWAR LAL, RAJESH MATHURADAS LAL
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

4 months past promisethis monthRegisteredJun 2022First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Jun 2022
  • Promised completion15 Jun 2026
  • Revised completionRevised to 15 Jun 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed67 files

Current status

19%15 of 78 units booked
73.7%Work done, per cost certificate

Figures as on 14 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE GOVIND KRUPANA121178078

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SHREE GOVIND KRUPA: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Closed/Covered29

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,334 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Aug 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3961.2
Proposed, not sanctioned3,961 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI WEST
Estimated costRs 34.80 cr
Cost incurredRs 25.64 cr
Work done73.67%
BuildingWingEstimatedIncurred
SHREE GOVIND KRUPANARs 33.30 crRs 24.79 cr
-NARs 1.50 crRs 85.27 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS A R MEHTA AND ASSOCIATES
EngineerCSE CONSULTANS CONSULTING ENGINEERS
Chartered AccountantVAYEDA AND ASSOCIATES
PartnerRole in project
MAMTORA FOUNDATION-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025810Dec 2024 → Jun 2025

Reason as filed by the promoterTHE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY AS THE VARIOUS APPROVALS FROM CONCERNED DEPARTMENT LIKE FIRE NOC, LIFT CERTIFICATES TOOK LONGER TIME THEN ESTIMATED. ALL OUR CIVIL WORK WAS COMPLETED UPTO THE PROJECT COMPLETION DATE ie 31-12-2024 BUT FURTHER APPROVALS FROM THE CONCERNED DEPARTMENTS TOOK LONGER TIME THAN ESTIMATED. WE ARE IN THE PROCESS OF OBTAINING THE OCCUPATION CERTIFICATE FROM THE CONCERNED DEPARTMENT AND SINCE THE OCCUPATION CERTIFICATE HAS NOT BEEN OBTAINED UPTO THE PROJECT COMPLETION DATE OF 31-12-2024 WE ARE SEEKING FOR EXTENTION OF THE REGISTRATION OF THE PROJEC

EA14032620227Dec 2024 → Jun 2026

Reason as filed by the promoterOC Recived

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 by Architect for Q1.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 by Architect for Q1.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 by Architect for Q1.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate ONLH - 23 02 2026.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate ONLH - 23 02 2026.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate ONLH - 23 02 2026.pdf14 May 2026
Withdrawal Update Form 3File: form 3.pdf14 May 2026
Withdrawal Update Form 3File: form 3.pdf14 May 2026
Withdrawal Update Form 3File: form 3.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 by Architect for Q1.pdf27 Feb 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate ONLH - 23 02 2026.pdf27 Feb 2026
Withdrawal Update Form 3File: form 3.pdf27 Feb 2026
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD inventory SGK.pdf20 Feb 2025
CERSAI detailsFile: CERSAI details Ok.pdf15 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate on Quality Assurance (Form 2A FY 2022-23) Ok.pdf14 Feb 2025
Details of encumbrances concerned to FinanceFile: No encumbrance self declaration GB RERA.pdf8 Feb 2025
Details of encumbrances concerned to LegalFile: No encumbrance self declaration GB RERA.pdf8 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured Unsecured GB RERA.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q21.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3.pdf5 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 23-24.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 FY 24-25.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 FY 24-25.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Q3 FY 24-25.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 24-25.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 24-25.pdf3 Feb 2025
Proforma of Agreement for saleFile: Agreement for Sale.pdf3 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 FY 2023-24.pdf3 Feb 2025
Declaration in FORM BFile: Form B Notarised Declaration.pdf1 Feb 2025
CERSAI detailsFile: CERSAI Declaration.pdf1 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about Designated Bank Account.pdf1 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DOI All Partners.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: GB RERA Inventory 150125.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SGK 301223.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SGK 310324_compressed.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SGK 300625_compressed.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: SGK Inventory List 300624.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 RERA FY 2022-23.pdf10 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SGK RERA Form 3 Q2.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory List 300623.pdf6 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CA CERTIFICATE Shree Govind Krupa.pdf6 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CA CERTIFICATE Shree Govind Krupa.pdf6 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3_compressed.pdf12 May 2023
Disclosure of sold/ booked inventoryFile: Inventory List 310323.pdf8 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: organized (1)_compressed.pdf6 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory 311222.pdf4 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventories.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM-3 CA CERTIFICATE MAMTORA FOUNDATION.pdf7 Oct 2022
Copy of the legal title reportFile: TITLE REPORT.pdf13 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200239580339_For_Asset_Based_Search_13_06_2022_13_32_08_436.pdf13 Jun 2022
Proforma of Allotment letterFile: RERA Sale Agreement Govind Bhuvan.pdf11 Jun 2022
Proforma of Allotment letterFile: 1 Proforma of the allotment letter and agreement for sale.pdf30 May 2022
Layout approvalFile: PLANS 1.pdf19 May 2022
Layout approvalFile: PLANS 2.pdf19 May 2022
Building plan approvalFile: IOD.pdf19 May 2022
PAN CardFile: COMPANY PAN CARD.pdf19 May 2022
Details of encumbrancesFile: No Encumbrance Declaration.pdf19 May 2022
Copy of Layout Approval (in case of layout)File: PLANS 1.pdf19 May 2022
Copy of Layout Approval (in case of layout)File: PLANS 2.pdf19 May 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf19 May 2022
Commencement Certificates / NA Order for plotted developmentFile: 2321114_FirstCC_signed.pdf19 May 2022
Declaration about Commencement CertificateFile: CC Covering Letter Shree Govind Krupa.pdf19 May 2022
Declaration in FORM BFile: Form B (1).pdf19 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM 1.pdf19 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf19 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL FORM 3 SIGNED.pdf19 May 2022

How this compares with Mumbai Suburban

19%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE GOVIND KRUPA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

Builder: MAMTORA FOUNDATION

MAMTORA FOUNDATION has 2 registrations on MahaRERA, including SHREE GOVIND KRUPA and Shree Hari Krupa. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SHREE GOVIND KRUPA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE GOVIND KRUPA is delayed beyond 15 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE GOVIND KRUPA?

The registered promoter entity is MAMTORA FOUNDATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE GOVIND KRUPA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE GOVIND KRUPA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE GOVIND KRUPA?

The professionals named in the filing: Architect: MS A R MEHTA AND ASSOCIATES; Engineer: CSE CONSULTANS CONSULTING ENGINEERS; Chartered Accountant: VAYEDA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE GOVIND KRUPA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE GOVIND KRUPA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE GOVIND KRUPA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.