ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / SHREE CHINTAMANI CO OP HSG SOC LTD

Registration lapsed No litigation declared Others project

SHREE CHINTAMANI CO OP HSG SOC LTD

By SHREE GANESH CONSTRUCTION

RG-MH-87250 · RERA P51700047303 · Last updated on MahaRERA portal: 20 Aug 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

SHREE CHINTAMANI CO OP HSG SOC LTD is a Others project by SHREE GANESH CONSTRUCTION in Thane, Maharashtra, registered with MahaRERA as P51700047303 on 17 Oct 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSHREE CHINTAMANI CO OP HSG SOC LTD
  • TypeOthers
  • Location
    • KUMBHARWADA SHIVAJI PATH
    • THANE
    • Thane (M Corp.)
    • 400602
  • Pincode400602
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700047303
  • ReraGenie IDRG-MH-87250

Builder

  • NameSHREE GANESH CONSTRUCTION
  • Entity typeOthers
  • GSTIN27AAUPP3329H2Z7
  • PramoterShree Ganesh Patil Kamlakar Patil
  • Other registrations9 more →
  • Completed2 of 10
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

19 months past promisethis monthRegisteredOct 2022First promiseMar 2024Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Oct 2022
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 31 Mar 2024)
  • Buildings1 building record
  • Documents filed82 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE CHINTAMANI CO OP HSG SOC LTDNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

SHREE CHINTAMANI CO OP HSG SOC LTD: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 20 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed121

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots121
Closed/Covered8
Open Space113

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area800 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
Declared on13 Sep 2024
LandownerVillageDistrict
SHREE GANESH CONSTRUCTIONThane (M Corp.)Thane

Approvals and building plan

Permissible FSI5638.49
Proposed, not sanctioned3,442 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHEMENDRA SHOPPING CENTRE 1ST FLOOR GOKHALE ROAD NAUPADA 400602

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR ULHAS G PRADHAN
ArchitectM/S. ULHAS PRADHAN & ASSOCIATES
EngineerPRAFUL K VISARIA
EngineerPraful Visaria
Chartered AccountantCA RAHUL N GHARAT & CO
Chartered AccountantRAHUL NARAYAN GHARAT
Chartered AccountantABNJ & Co.
Chartered AccountantRahul Gharat
PartnerRole in project
Ganesh Patil-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024118Mar 2024 → Mar 2025

Reason as filed by the promoterBuilding complete in all aspect, we will be applying for OC in coming one month. Due to parliamentary election, our various NOC's till got delayed & yet therefor pending as on date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Shree Ganesh Construction.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24-12-2022.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 26-06-2023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31-10-2023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 25-01-2024.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05-06-2024.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05-07-2024.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-01-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-04-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-07-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-10-2023.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05-01-2024.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12-06-2024.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 07-07-2024.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold unsold inventory June 24.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ June 24 signed.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct 22-Dec 22.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Apr 23-Jun 23.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jul 23-Sep 23.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct 23-Dec 23.pdf10 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan 24-Mar 24.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct 22-Dec 22.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 23-Mar 23.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Apr 23-Jun 23.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jul 23-Sep 23.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct 23-Dec 23.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 24-Mar 24.pdf10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf10 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23 scan.pdf9 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24 scan.pdf9 Aug 2024
Disclosure of sold/ booked inventoryFile: upto 31-12-22 Q4.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: upto 31-03-23 Q1.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: upto 30-06-23 Q2.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: upto 30-09-23 Q3.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: upto 31-12-23 Q4.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: upto 31-03-24 Q1.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shree Ganesh Construction.pdf11 Jul 2024
Declaration in FORM BFile: Form B.pdf6 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct 22-Dec 22.pdf6 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Apr 23-Jun 23.pdf6 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jul 23-Sep 23.pdf6 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Oct 23-Dec 23.pdf6 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan 24-Mar 24.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct 22-Dec 22.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 23-Mar 23.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Apr 23-Jun 23.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jul 23-Sep 23.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Oct 23-Dec 23.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan 24-Mar 24.pdf6 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf6 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf6 Jul 2024
CERSAI detailsFile: Undertaking for Not Creation of Charged on Project.pdf6 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf6 Jul 2024
Other - LegalFile: deviation-1.pdf13 Oct 2022
Proforma of Allotment letterFile: Allotment Letter (2).pdf11 Oct 2022
Proforma of Allotment letterFile: SALE AGREEMENT 10102022.pdf11 Oct 2022
Other - LegalFile: Agreement for development-1.pdf11 Oct 2022
Other - LegalFile: Agreement for development-II.pdf11 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank declaration (Format A) final.pdf14 Sep 2022
Other - FinanceFile: Form 3 _final version.pdf12 Sep 2022
Details of encumbrances concerned to FinanceFile: Finance encumbrance.pdf10 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech_Certificate_1.pdf5 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate compressed.pdf5 Sep 2022
CERSAI detailsFile: New Search Report.pdf5 Sep 2022
CERSAI detailsFile: Undertaking final.pdf5 Sep 2022
Other - TechnicalFile: Development agreement_Marathi.pdf2 Sep 2022
Declaration about Commencement CertificateFile: CC Declaration (final).pdf1 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 final version.pdf29 Aug 2022
Layout approvalFile: PROFORMA I.pdf23 Aug 2022
Building plan approvalFile: PROFORMA II.pdf23 Aug 2022
PAN CardFile: PAN CARD.pdf23 Aug 2022
Copy of the legal title reportFile: Legal Title_Signed copy_.pdf23 Aug 2022
Details of encumbrances concerned to LegalFile: legel encumbrance scanned.pdf23 Aug 2022
Copy of Layout Approval (in case of layout)File: PROFORMA I.pdf23 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: PROFORMA II.pdf23 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Aug 2022
Declaration in FORM BFile: Promoters Signed new scn.pdf23 Aug 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE CHINTAMANI CO OP HSG SOC LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

2 kmSHREE CHINTAMANI CO OP HCompleted 175Lapsed / revoked 63Other 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 394 registered projects within 2 km.

Builder: SHREE GANESH CONSTRUCTION

SHREE GANESH CONSTRUCTION has 10 registrations on MahaRERA, including ANAND VIHAR and GANESH SHRUSHTI. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SHREE CHINTAMANI CO OP HSG SOC LTD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE CHINTAMANI CO OP HSG SOC LTD is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE CHINTAMANI CO OP HSG SOC LTD?

The registered promoter entity is SHREE GANESH CONSTRUCTION, an others as per the filing. Its GSTIN 27AAUPP3329H2Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE CHINTAMANI CO OP HSG SOC LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE CHINTAMANI CO OP HSG SOC LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE CHINTAMANI CO OP HSG SOC LTD?

The professionals named in the filing: Architect: MR ULHAS G PRADHAN; Architect: M/S. ULHAS PRADHAN & ASSOCIATES; Engineer: PRAFUL K VISARIA; Engineer: Praful Visaria; Chartered Accountant: CA RAHUL N GHARAT & CO; Chartered Accountant: RAHUL NARAYAN GHARAT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE CHINTAMANI CO OP HSG SOC LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE CHINTAMANI CO OP HSG SOC LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE CHINTAMANI CO OP HSG SOC LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.