ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Shree Balaji 135

Registration lapsed No litigation declared Residential / Group Housing project

Shree Balaji 135

By Saptrishi Infracon Private Limited

RG-MH-30454 · RERA P51800030686 · Last updated on MahaRERA portal: 14 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 80%
3Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

Shree Balaji 135 is a Residential / Group Housing project by Saptrishi Infracon Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030686 on 8 Sep 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 3 complaints are on record with the regulator.

At a glance

Project

  • NameShree Balaji 135
  • TypeResidential / Group Housing
  • Location
    • Station Road
    • Pantnagar Ghatkopar East
    • Kurla
    • Mumbai Suburban
    • 400075
  • Pincode400075
  • RERA no.P51800030686
  • ReraGenie IDRG-MH-30454

Builder

  • NameSaptrishi Infracon Private Limited
  • Entity typeCompany
  • DirectorsVital Vijay Takatrao, Abhay Avinash Parab, Anant Jagannath Talawdekar, Prasad Murlidhar Chindarkar
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredSep 2021PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Sep 2021
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Balaji 135NA1717000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 80%.

Shree Balaji 135: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 14 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered19
Open Space6

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area489 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Vishal Pant Nagar CHSLAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3184.75
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThakur College Of Science and Commshyam Narayan thakur Marg Thakur Village mumbai 400101

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShelter Associates
EngineerShahanavaj Khan Pathan
EngineerRajesh Laxman Patil
Chartered AccountantR B Karandikaar & Co
PartnerRole in project
Saptrishi Infracon Private Limited-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12502225Prashant Kantilal LathiaSaptrishi Infracon Private Limited04/07/2025
CC12502226Prashant Kantilal LathiaSaptrishi Infracon Private Limited04/07/2025
CC12502220Prashant Kantilal LathiaSaptrishi Infracon Private Limited04/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Achitect Cert - July 2024 to Sept 2024.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - October 2024 to December 2024.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - April 2024 to June 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2023.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2023.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate April 2024 to June 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate July 2024 to September 2024.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate October 2024 to December 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 April 2024 to June 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 October 2024 to Decmber 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 July 2024 to Sept 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 April 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 January 2024 1.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 June 2023 1.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 April 2024.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate March 2023 1.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate March 2022 1.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate Bldg 135 October 2023 1.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 Dec 2023.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 December 2024.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 Sept 2024.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: June 2024 of Sold Booked Inventory.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 March 2024.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 Sept 2023.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 JUNE 2023.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 March 2022.pdf14 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory Bldg No 135 March 2023.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -Bldg No 135 2023.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-2023.pdf14 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Bldg No135 2024.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 -2023-20224.pdf14 Feb 2025
Layout approvalFile: Copy of Layout Approval (in case of layout).pdf14 Aug 2021
Building plan approvalFile: Copy of Layout Approval (in case of layout).pdf14 Aug 2021
PAN CardFile: SAPT Infracon PVT LLP pan card.pdf14 Aug 2021
Copy of the legal title reportFile: Title Certificate.pdf14 Aug 2021
Details of encumbrancesFile: NON ENCUMBRANCES CERTIFICATE 135.pdf14 Aug 2021
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval (in case of layout).pdf14 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Copy of Layout Approval (in case of layout).pdf14 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates _ NA Order for plotted development.pdf14 Aug 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate 135.pdf14 Aug 2021
Declaration in FORM BFile: Declaration Form B Developer.pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf14 Aug 2021
Proforma of Allotment letterFile: Draft Booking cum Allotment Form 135.pdf14 Aug 2021
Proforma of Allotment letterFile: ProforMA agreement for sale.pdf14 Aug 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
SHREE BALAJI ORCHIDP51800021261Pant nagar Ghatkopar east, Mumbai SuburbanJun 2019OngoingMay 2025Not delivered

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Balaji 135 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pantnagar Ghatkopar East6,700+ in Mumbai Suburban

Builder: Saptrishi Infracon Private Limited

SAPTRISHI INFRACON PRIVATE LIMITED has 3 registrations on MahaRERA, including SHREE BALAJI ORCHID and Shree Balaji 135. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shree Balaji 135 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shree Balaji 135 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Balaji 135?

The registered promoter entity is Saptrishi Infracon Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Balaji 135?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shree Balaji 135?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shree Balaji 135?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Balaji 135?

The professionals named in the filing: Architect: Shelter Associates; Engineer: Shahanavaj Khan Pathan; Engineer: Rajesh Laxman Patil; Chartered Accountant: R B Karandikaar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Balaji 135?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Balaji 135. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Balaji 135 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.