Registration lapsed No litigation declared Residential / Group Housing project

SHIVTEJ ASHIYANA

By YOGESH RAMDAS SARJINE

RG-MH-39630 · RERA P51700011753 · Last updated on MahaRERA portal: 29 Sep 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 92 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

SHIVTEJ ASHIYANA is a Residential / Group Housing project by YOGESH RAMDAS SARJINE in Thane, Maharashtra, registered with MahaRERA as P51700011753 on 31 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 92 months from the original filing.

At a glance

Project

  • NameSHIVTEJ ASHIYANA
  • TypeResidential / Group Housing
  • Location
    • Navi Mumbai (M Corp.)
    • Thane
    • 400706
  • Pincode400706
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700011753
  • ReraGenie IDRG-MH-39630

Builder

  • NameYOGESH RAMDAS SARJINE
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseApr 2018Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Apr 2018)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVTEJ ASHIYANANA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHIVTEJ ASHIYANA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area680 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1013.0
Proposed, not sanctioned1,013 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNERUL WEST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAUSHALJADIA
EngineerRAM V MARATHE
PartnerRole in project
YOGESH RAMDAS SARJINE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010402Apr 2018 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 64.3 % allottees for purpose of extension of RERA registration period of the said project.

EXT51700006166Apr 2018 → Dec 2020

Reason as filed by the promoterBuilding Construction is already completed. No Dues Certificate is awaited from CIDCO to submit to NMMC for Occupancy Certificate.

EXT51700000297Apr 2018 → Apr 2019

Reason as filed by the promoterWe have already applied for NOC from CIDCO and completion certificate to NMMC Authority, but NOC from CIDCO is still awaited. Hence completion certificate is also not received till date. Once again we have sent request letter to CIDCO Authorities to issue NOC. So we can submit the same to obtain completion certificate from NMMC.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Jul 2021

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Shivtej Ashiyana as on 2022-23.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 630.pdf14 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Mar 2018 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Mar 2019 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Mar 2020 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Mar 2021 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Dec 2021 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Mar 2022 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Jun 2022 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Sept 2022 - Form 2.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivtej Ashiyana Dec 2022 - Form 2.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Mar 18.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Mar 19.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Mar 20.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Mar 21.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on DEC- 21.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Mar- 22.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on June 22.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Sept 22.pdf10 Mar 2023
Certificates of CA (Form 3)File: Form 3 of Shivtej Ashiyana as on Dec 22.pdf10 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-03-2018 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-03-2019 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-03-2020 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-03-2021 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-12-2021 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-03-2022 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 30-06-2022 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 30-09-2022 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 31-12-2022 (105A-50E Nerul).pdf1 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-Form-1 24-02-2023 (105A-50E Nerul).pdf1 Mar 2023
Declaration about Commencement CertificateFile: Format D Shivtej.pdf24 Aug 2022
CERSAI detailsFile: Shivtej Ashiyana.pdf24 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Shivtej Rera certificate FY 2020-21.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2a 2020-21.pdf19 Jul 2021
OtherFile: CONSENT LETTER FOR RERA.pdf19 Jul 2021
OtherFile: SHIV-TEJ Form D.pdf19 Jul 2021
Declaration about Commencement CertificateFile: CC 105A.pdf12 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2 A_compressed.pdf12 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Flat.pdf12 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 2017-18 Form5 Shivtej Ashiyana 105_.pdf12 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19 Form 5 Shivtej Ashiyana 105.pdf12 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20 Form 5 Shivtej Ashiyana 105.pdf12 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC application.pdf12 Jul 2021
Details of encumbrancesFile: ENCUMBER.pdf24 Aug 2017
Declaration in FORM BFile: FORM B.pdf24 Aug 2017
Certificates of CA (Form 3)File: CA CERTI.pdf24 Aug 2017
Layout approvalFile: BLUE PRINT (1).pdf23 Aug 2017
Building plan approvalFile: BLUE PRINT (1).pdf23 Aug 2017
Building plan approvalFile: CC.pdf23 Aug 2017
PAN CardFile: pan.pdf23 Aug 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf23 Aug 2017
Copy of Layout Approval (in case of layout)File: BLUE PRINT (1).pdf23 Aug 2017
Building Plan Approval (IOD)File: BLUE PRINT (1).pdf23 Aug 2017
Building Plan Approval (IOD)File: CC.pdf23 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI (1).pdf23 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERT (1).pdf23 Aug 2017
Proforma of Allotment letterFile: AGREEMENT.pdf23 Aug 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHIVTEJ PLAZAPLOT NO 326 SECTOR 6 SARSOLE8CompletedMar 2016Mar 2016
SHIVTEJ DARSHANPLOT NO 85 SECTOR 11 KOPARKHAIRANE8CompletedNov 2014Nov 2014
SHIVTEJ CHHAYAPLOT NO 41A SECTOR 20 NERUL9CompletedOct 2014Oct 2014

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 92 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVTEJ ASHIYANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Navi Mumbai (M Corp.)7,600+ in Thane

2 kmSHIVTEJ ASHIYANACompleted 20Lapsed / revoked 7Other 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: YOGESH RAMDAS SARJINE

YOGESH RAMDAS SARJINE has 2 registrations on MahaRERA, including SHIVTEJ ASHIYANA and SHIVTEJ PUSHPA. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that SHIVTEJ ASHIYANA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHIVTEJ ASHIYANA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVTEJ ASHIYANA?

The registered promoter entity is YOGESH RAMDAS SARJINE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVTEJ ASHIYANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVTEJ ASHIYANA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVTEJ ASHIYANA?

The professionals named in the filing: Architect: KAUSHALJADIA; Engineer: RAM V MARATHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVTEJ ASHIYANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVTEJ ASHIYANA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVTEJ ASHIYANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.